44000-P127837
World Bank
Access and Renewable Energy Project
International Development Association
MINISTRY OF HYDROCARBONS AND ENERGY
International Development Association
MINISTRY OF HYDROCARBONS AND ENERGYPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Lucia Spinelli
+1-202-473-1000lspinelli@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
Departamento de Potosi
-20.6670 -67.0000
Departamento de Chuquisaca
-20.0000 -64.3330
Public Administration - Energy and ExtractivesEnergy Transmission and DistributionRenewable Energy SolarRural Infrastructure and service deliveryClimate changeRural DevelopmentMitigation
0.00
0.00
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
583333.33
583333.33
583333.34
583333.33
583333.33
583333.34
583333.33
583333.33
583333.34
583333.33
583333.33
583333.34
1291666.66
1291666.67
1291666.67
1291666.66
1291666.67
1291666.67
1291666.66
1291666.67
1291666.67
1291666.66
1291666.67
1291666.67
1375000.00
1375000.00
1375000.00
1375000.00
1375000.00
1375000.00
1375000.00
1375000.00
1375000.00
1375000.00
1375000.00
1375000.00
458333.33
458333.33
458333.34
458333.33
458333.33
458333.34
458333.33
458333.33
458333.34
458333.33
458333.33
458333.34
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
133333.33
133333.33
133333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
89385.02
89385.02
89385.02
435426.48
435426.48
435426.49
224767.98
224767.99
224767.99
384206.54
384206.54
384206.54
574870.64
574870.65
574870.65
429587.59
429587.59
429587.60
533333.33
533333.33
533333.34
450000.00
450000.00
450000.00
1849785.27
1849785.27
1849785.28
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
50000000Total Commitment in Second Quarter of 2014
International Development Association400000Total Disbursement in First Quarter of 2016
International Development Association-1381Total Interest Repayment in First Quarter of 2016
International Development Association-4051Total Interest Repayment in Third Quarter of 2016
International Development Association-3930Total Interest Repayment in First Quarter of 2017
International Development Association268155Total Disbursement in Second Quarter of 2017
International Development Association506279Total Disbursement in Third Quarter of 2017
International Development Association800000Total Disbursement in Third Quarter of 2017
International Development Association-8792Total Interest Repayment in Third Quarter of 2017
International Development Association674304Total Disbursement in Fourth Quarter of 2017
International Development Association1152620Total Disbursement in First Quarter of 2018
International Development Association-25444Total Interest Repayment in First Quarter of 2018
International Development Association-34685911Total Commitment Cancellations in Second Quarter of 2018
International Development Association342874Total Disbursement in Second Quarter of 2018
International Development Association436264Total Disbursement in Second Quarter of 2018
International Development Association945474Total Disbursement in Second Quarter of 2018
International Development Association526828Total Disbursement in Third Quarter of 2018
International Development Association1288763Total Disbursement in Third Quarter of 2018
International Development Association-51347Total Interest Repayment in Third Quarter of 2018
International Development Association310862Total Disbursement in Fourth Quarter of 2018
International Development Association534291Total Disbursement in Fourth Quarter of 2018
International Development Association1059545Total Disbursement in Fourth Quarter of 2018
International Development Association573787Total Disbursement in First Quarter of 2019
International Development Association-86450Total Interest Repayment in First Quarter of 2019
International Development Association127606Total Disbursement in Second Quarter of 2019
International Development Association473113Total Disbursement in Second Quarter of 2019
International Development Association-99517Total Interest Repayment in Third Quarter of 2019
International Development Association-179720Total Loan Repayment in Third Quarter of 2019
International Development Association-15839Total Disbursement in Fourth Quarter of 2019
International Development Association-724324Total Commitment Cancellations in First Quarter of 2020
International Development Association-100292Total Interest Repayment in First Quarter of 2020
International Development Association-180374Total Loan Repayment in First Quarter of 2020
International Development AssociationProject Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Finance Agreement :PCU | Description :The Recipient, through MHE shall maintain, throughout Project implementation, a unit (“PCU”)with structure, functions and responsibilities acceptable to the Association as set forth in the Operational Manual, includinginteralia, the responsibility of the PCU to implement, monitor and supervise the carrying out of the Project (including itsfinancial and procurement aspects) | Frequency :CONTINUOUS
Finance Agreement :PCU Staff | Description :The Recipient, through MHE shall ensure that (i) the PCU is, throughout Projectimplementation, headed by a Project coordinator, and staffed with adequate professional, fiduciary, administrative and technicalpersonnel (including social and environmental specialists), all with qualifications, experience and terms of employment acceptableto the Association | Frequency :CONTINUOUS
Finance Agreement :Environmental Management Framework | Description :The Recipient, through MHE, shall: (a) implement the Projectin accordance with the Environmental Management Framework (EMF); and (b) implement and/or cause to be implemented the pertinentenvironmental management plan, in accordance with its terms and in a manner acceptable to the Association | Frequency :CONTINUOUS
Finance Agreement :Resettlement Policy Framework | Description :The Recipient, through MHE, shall: (a) implement the Project inaccordance with the Resettlement Policy Framework (RPF), includingthe procedures detailed in said RPF; and (b) implement and/orcause to implement the pertinent resettlement action plan in accordance with its terms and in a manner acceptable to theAssociation | Frequency :CONTINUOUS
Finance Agreement :Indigenous People Planning Framework | Description :The Recipient, through MHE, shall: (a) implement the Projectin accordance with the Indigenous People Planning Framework (IPPF); and (b) implement the pertinent indigenous peoples plan inaccordance with its terms, and in a manner acceptable to the Association. | Frequency :CONTINUOUS
Finance Agreement :Safeguards Review of Terms of Reference | Description :The Recipient shall, through MHE, ensure that the termsof reference for any consultancies related to the technical assistance provided under the Project, shall be acceptable to theAssociation and, to that end, such terms of reference shall require that the advice conveyed through such technical assistance beconsistent with the requirements of the Association's Safeguard Policies | Frequency :CONTINUOUS
PDO Indicator
People provided with access to electricity by household connections
PDO Indicator
Capacity building activities for subnational entities implemented under the Project
PDO Indicator
People provided with access to electricity by hhold connections-Grid
Intermediate Results Indicator
Direct project beneficiaries
Intermediate Results Indicator
Number of outreach and training activities implemented (for beneficiaries, Distribution Companies, contractors, and other relevant stakeholders)
Intermediate Results Indicator
No Indicators
Intermediate Results Indicator
Number of energy sector studies supported
Intermediate Results Indicator
Female beneficiaries
Intermediate Results Indicator
Distribution lines constructed or rehabilitated under the project
Intermediate Results Indicator
Distribution lines constructed under the project
44000-P107137
World Bank
BO PICAR Community Investment in Rural Areas
International Development Association
MINISTRY OF RURAL DEVELOPMENT, AGRICULTURE AND ENVIRONMENT
International Development Association
MINISTRY OF RURAL DEVELOPMENT, AGRICULTURE AND ENVIRONMENTPlanned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Garry Charlier
+1-202-473-1000gcharlier@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
Departamento de Pando
-11.3330 -67.6670
Oruro
-18.6670 -67.5000
Departamento de La Paz
-15.5000 -68.0000
Departamento de Cochabamba
-17.5000 -65.6670
Departamento de Chuquisaca
-20.0000 -64.3330
Social ProtectionSub-National GovernmentPublic Administration - Agriculture, Fishing & ForestrySocial InclusionAdaptationClimate changeRural Infrastructure and service deliveryRural DevelopmentIndigenous People and Ethnic Minorities
0.00
0.00
0.00
166666.67
166666.67
166666.66
333333.33
333333.33
333333.34
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
333333.33
333333.33
333333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
333333.33
333333.33
333333.34
0.00
0.00
0.00
70871.66
70871.67
70871.67
140034.17
140034.17
140034.18
41572.54
41572.55
41572.55
1919767.28
1919767.29
1919767.29
1717453.47
1717453.48
1717453.48
545004.41
545004.42
545004.42
637441.19
637441.19
637441.19
716688.24
716688.24
716688.24
1203932.93
1203932.93
1203932.93
0.00
0.00
0.00
1510738.69
1510738.70
1510738.70
665735.78
665735.78
665735.79
1161542.79
1161542.79
1161542.79
0.00
0.00
0.00
0.00
0.00
0.00
541286.87
541286.87
541286.87
271547.20
271547.20
271547.21
541109.50
541109.50
541109.51
837202.94
837202.94
837202.94
350091.05
350091.06
350091.06
1633878.28
1633878.29
1633878.29
1040433.33
1040433.33
1040433.33
2569526.56
2569526.57
2569526.57
1073501.28
1073501.28
1073501.28
4535391.03
4535391.04
4535391.04
737007.25
737007.26
737007.26
2700072.62
2700072.62
2700072.62
1782583.15
1782583.15
1782583.16
1166666.66
1166666.67
1166666.67
833333.33
833333.33
833333.34
447421.49
447421.49
447421.49
40000000Total Commitment in Third Quarter of 2011
International Development Association1000000Total Disbursement in Second Quarter of 2012
International Development Association-5202Total Interest Repayment in Third Quarter of 2012
International Development Association212615Total Disbursement in Fourth Quarter of 2012
International Development Association420103Total Disbursement in First Quarter of 2013
International Development Association-10805Total Interest Repayment in First Quarter of 2013
International Development Association124718Total Disbursement in Second Quarter of 2013
International Development Association1145375Total Disbursement in Third Quarter of 2013
International Development Association1848775Total Disbursement in Third Quarter of 2013
International Development Association2765152Total Disbursement in Third Quarter of 2013
International Development Association-16103Total Interest Repayment in Third Quarter of 2013
International Development Association1288485Total Disbursement in Fourth Quarter of 2013
International Development Association3863875Total Disbursement in Fourth Quarter of 2013
International Development Association1635013Total Disbursement in First Quarter of 2014
International Development Association-77297Total Interest Repayment in First Quarter of 2014
International Development Association1912324Total Disbursement in Second Quarter of 2014
International Development Association2150065Total Disbursement in Third Quarter of 2014
International Development Association-152976Total Interest Repayment in Third Quarter of 2014
International Development Association1669248Total Disbursement in Fourth Quarter of 2014
International Development Association1942551Total Disbursement in Fourth Quarter of 2014
International Development Association-183512Total Interest Repayment in First Quarter of 2015
International Development Association1736317Total Disbursement in Second Quarter of 2015
International Development Association2795899Total Disbursement in Second Quarter of 2015
International Development Association1997207Total Disbursement in Third Quarter of 2015
International Development Association-213210Total Interest Repayment in Third Quarter of 2015
International Development Association55700000Total Commitment in Third Quarter of 2015
International Development Association4300000Total Commitment in Third Quarter of 2015
International Development Association1432052Total Disbursement in Fourth Quarter of 2015
International Development Association2052576Total Disbursement in Fourth Quarter of 2015
International Development Association-275724Total Interest Repayment in First Quarter of 2016
International Development Association1623861Total Disbursement in Third Quarter of 2016
International Development Association-302968Total Interest Repayment in Third Quarter of 2016
International Development Association814642Total Disbursement in Fourth Quarter of 2016
International Development Association1623329Total Disbursement in First Quarter of 2017
International Development Association-310949Total Interest Repayment in First Quarter of 2017
International Development Association-557391Total Loan Repayment in First Quarter of 2017
International Development Association511568Total Disbursement in Second Quarter of 2017
International Development Association2000000Total Disbursement in Second Quarter of 2017
International Development Association-326021Total Interest Repayment in Third Quarter of 2017
International Development Association-573569Total Loan Repayment in Third Quarter of 2017
International Development Association1050273Total Disbursement in Third Quarter of 2017
International Development Association-11216Total Interest Repayment in Third Quarter of 2017
International Development Association-235311Total Commitment Cancellations in Fourth Quarter of 2017
International Development Association-235311Total Disbursement in Fourth Quarter of 2017
International Development Association5136945Total Disbursement in Fourth Quarter of 2017
International Development Association-5223Total Commitment Cancellations in First Quarter of 2018
International Development Association-5223Total Disbursement in First Quarter of 2018
International Development Association-346739Total Interest Repayment in First Quarter of 2018
International Development Association-591092Total Loan Repayment in First Quarter of 2018
International Development Association3126523Total Disbursement in First Quarter of 2018
International Development Association-28468Total Interest Repayment in First Quarter of 2018
International Development Association608511Total Disbursement in Second Quarter of 2018
International Development Association7100069Total Disbursement in Second Quarter of 2018
International Development Association-343164Total Interest Repayment in Third Quarter of 2018
International Development Association-574185Total Loan Repayment in Third Quarter of 2018
International Development Association1447458Total Disbursement in Third Quarter of 2018
International Development Association1773046Total Disbursement in Third Quarter of 2018
International Development Association-118992Total Interest Repayment in Third Quarter of 2018
International Development Association4453389Total Disbursement in Fourth Quarter of 2018
International Development Association4473006Total Disbursement in Fourth Quarter of 2018
International Development Association4679778Total Disbursement in Fourth Quarter of 2018
International Development Association-314722Total Interest Repayment in First Quarter of 2019
International Development Association-571453Total Loan Repayment in First Quarter of 2019
International Development Association2211022Total Disbursement in First Quarter of 2019
International Development Association-261354Total Interest Repayment in First Quarter of 2019
International Development Association5695874Total Disbursement in Second Quarter of 2019
International Development Association2404344Total Disbursement in Second Quarter of 2019
International Development Association-322491Total Interest Repayment in Third Quarter of 2019
International Development Association-567120Total Loan Repayment in Third Quarter of 2019
International Development Association3472180Total Disbursement in Third Quarter of 2019
International Development Association-382336Total Interest Repayment in Third Quarter of 2019
International Development Association1458Total Disbursement in Third Quarter of 2019
International Development Association1874112Total Disbursement in Third Quarter of 2019
International Development Association4621963Total Disbursement in Fourth Quarter of 2019
International Development Association-306087Total Interest Repayment in First Quarter of 2020
International Development Association-565777Total Loan Repayment in First Quarter of 2020
International Development Association2686725Total Disbursement in First Quarter of 2020
International Development Association-474727Total Interest Repayment in First Quarter of 2020
International Development Association-41986Total Interest Repayment in First Quarter of 2020
International Development Association1305300Total Disbursement in Second Quarter of 2020
International Development AssociationProject Information DocumentProject Information DocumentProject Information DocumentProject Appraisal DocumentProject Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementAgreementFinancing AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Finance Agreement :Article IV, Section 4.01(a) | Description :Maintain the legal framework enabling the communities to carry outthe Community Investment Subproject. | Frequency :Yearly
Finance Agreement :Article IV, Section 4.01(b) | Description :Maintain the Normas Básicas del Sistema de Administración de Bienes yServicios (procurement enabling legislation) | Frequency :Yearly
Finance Agreement :Article IV, Section 4.01(c) | Description :Apply the contractual remedies in case of non-compliance with the CIGrant Agreement | Frequency :Monthly
Finance Agreement :Article V, Section 5.01 & Schedule 2, Section I.B | Description :Adopt the Operational Manual for the carryingout of the Project. | Due Date :21-Nov-2011
Finance Agreement :Schedule 2, Section I.A.1(a) | Description :Maintain the Unidad Desconcentrada Empoderar (implementing agency) |Frequency :Monthly
Finance Agreement :Schedule 2, Section I.A.1(b) | Description :Strengthen the Unidad Desconcentrada Empoderar through therecruitment and set-up of a Project Coordination Team (PCT). | Due Date :31-Jan-2012
Finance Agreement :Schedule 2, Section I.A.1(c) | Description :Establish, at least two Regional Operating Units reportingadministratively to the PCT | Due Date :31-Jan-2012
Finance Agreement :Schedule 2, Section I.A.1(e) | Description :Cause participating municipalities to establish Municipal Committeesfor the endorsements of Community Investment Subprojects. | Frequency :Monthly
Finance Agreement :Schedule 2, Section I.C | Description :Prepare and furnish to the Association detailed annual operating plans |Frequency :Yearly
Finance Agreement :Schedule 2, Section D.1(a) | Description :Municipalities to enter into MOU with the Unidad DesconcentradaEmpoderar, in order to participate in the Project | Frequency :Quarterly
Finance Agreement :Schedule 2, Section D.1(b) | Description :Call for Subprojects proposal and selected Communities, publiclydisclosed. | Frequency :Monthly
Finance Agreement :Schedule 2, Section D.1(c) | Description :Community Investment Subproject proposals to comply with selectioncriteria set forth in the Operational Manual. | Frequency :Quarterly
Finance Agreement :Schedule 2, Section D.2 | Description :Second Community Investment Subprojects to comply with Genderprioritization requirements | Frequency :Monthly
Finance Agreement :Schedule 2, Section D.3 | Description :Recipient to enter into CI Grant Agreements (sub-financing agreements)with Communities for the financing of selected Community Investment Subprojects | Frequency :Quarterly
Finance Agreement :Schedule 2, Section F | Description :Recipient shall comply with the provisions of the ESMF, PMP in thescreening of Community Investment Subprojects, and ensure that no Category A activities are carried out under the Project, nor d |Frequency :Quarterly
Finance Agreement :Schedule 2, Section III.D | Description :Procurement audits to be carried out by independent auditors |Frequency :Yearly
Finance Agreement :Section I.A.1. (c) of schedule 2 | Description :The Recipient shall vest the overall responsibility for theimplementation of the Project in the MDRyT, and to this end shall, through MDRyT no later than three (3) months after the EffectiveDate complete the staffing of the ROUs, in a manner acceptable to the Bank. | Due Date :28-Feb-2017
Finance Agreement :Section I. D. 1. (a) of Schedule 2 | Description :Prior to the implementation of any Subproject, the Recipientthrough EMPODERAR shall, when applicable, enter into a memorandum of understanding with each Participating Municipality where thoseCommunities are located, under terms and conditions acceptable to the Association and substantially similar to those provided inthe OM. | Frequency :CONTINUOUS
Finance Agreement :Section I. D. 1. (b) of Schedule 2 | Description :Prior to the implementation of Subprojects, the Recipientthrough EMPODERAR shall, upon having selected a Community Investment Subproject, enter into a written agreement with each Communityor cluster thereof, as the case may be, for the provision of the respective Community Investment Grant, on terms and conditionsacceptable to the Association. | Frequency :CONTINUOUS
Finance Agreement :Section I.F.1 of Schedule 2 | Description :The Recipient shall implement the Project through MDRyT (throughEMPODERAR) and/or cause the Communities to implement their respective Subprojects, in accordance with the ESMF and the RPF. Exceptas the Association shall otherwise agree, the Recipient, through MDRyT (through EMPODERAR) shall and/or shall cause the Communitiesto, not assign amend, abrogate or waive the ESMF and the RPF or any of t | Frequency :CONTINUOUS
PDO Indicator
Direct project beneficiaries
PDO Indicator
Female beneficiaries
PDO Indicator
Indigenous beneficiaries
PDO Indicator
Female heads of household (considered most vulnerable in targeted communities)
PDO Indicator
Subproject fully functional 12 months after their completion
PDO Indicator
Improved access to basic infrastructure and services in targeted communities
Intermediate Results Indicator
Number of beneficiaries trained in project management (of which women)
Intermediate Results Indicator
Number of beneficiaries engaged in sub-project implementation committees (of which women)
Intermediate Results Indicator
Percentage of community members satisfied with sub-project outputs (infrastructure/service) (of which female)
Intermediate Results Indicator
Percentage of community members satisfied with planning process and sub-project identification (of which women)
Intermediate Results Indicator
Percent of subprojects satisfactorily completed implementation, including final accounting
Intermediate Results Indicator
Percentage of completed subprojects whose technical and fiduciary audits have no substantial remarks
44000-P144597
World Bank
BO Road Sector Capacity Development Project
International Bank for Reconstruction and Development
ADMINISTRADORA BOLIVIANA DE CARRETERAS
International Bank for Reconstruction and Development
International Development Association
International Development Association
ADMINISTRADORA BOLIVIANA DE CARRETERASPlanned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Felipe Targa Rodriguez
+1-202-473-1000ftarga@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
El Beni
-14.0000 -14.0000
Provincia Chiquitos
-18.0000 -18.0000
Provincia Nuflo de Chavez
-15.9170 -15.9170
Provincia Marban
-15.6670 -15.6670
Provincia Cercado
-14.5000 -14.5000
Provincia Andres Ibanez
-17.7500 -17.7500
San Julian
-17.8120 -17.8120
Santa Maria
-18.3670 -18.3670
San Ramon
-18.5170 -18.5170
Yotau
-16.0930 -16.0930
Pailon
-17.6500 -17.6500
El Puente
-16.3260 -16.3260
Cotoca
-17.8170 -17.8170
Trinidad
-14.8330 -14.8330
Santa Cruz de la Sierra
-17.7860 -17.7860
Puearto Pailas
-17.6630 -62.8120
Ascencion de Guarayos
-15.8930 -15.8930
Public Administration - TransportationRural and Inter-Urban RoadsTradeTrade Facilitation
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1000000.00
1000000.00
1000000.00
666666.66
666666.67
666666.67
333333.33
333333.33
333333.34
5000000.00
5000000.00
5000000.00
5000000.00
5000000.00
5000000.00
666666.66
666666.67
666666.67
1666666.66
1666666.67
1666666.67
8333333.33
8333333.33
8333333.34
8333333.33
8333333.33
8333333.34
8333333.33
8333333.33
8333333.34
3333333.33
3333333.33
3333333.34
3333333.33
3333333.33
3333333.34
2333333.33
2333333.33
2333333.34
2333333.33
2333333.33
2333333.34
2333333.33
2333333.33
2333333.34
3666666.66
3666666.67
3666666.67
3666666.66
3666666.67
3666666.67
2333333.33
2333333.33
2333333.34
2666666.66
2666666.67
2666666.67
3333333.33
3333333.33
3333333.34
3333333.33
3333333.33
3333333.34
3000000.00
3000000.00
3000000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2284421.33
2284421.33
2284421.34
0.00
0.00
0.00
1493781.74
1493781.74
1493781.75
403202.81
403202.81
403202.80
6448743.83
6448743.83
6448743.83
0.00
0.00
0.00
7447923.70
7447923.70
7447923.70
0.00
0.00
0.00
1358282.77
1358282.77
1358282.78
12733747.00
12733747.00
12733747.00
12314986.68
12314986.68
12314986.69
5477823.55
5477823.55
5477823.56
2721701.97
2721701.97
2721701.96
2340537.41
2340537.41
2340537.40
1873002.43
1873002.43
1873002.44
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
56550000Total Commitment in Fourth Quarter of 2015
International Development Association
2500000Total Commitment in Fourth Quarter of 2015
International Development Association
165950000Total Commitment in Fourth Quarter of 2015
International Bank for Reconstruction and Development
414875Total Disbursement in Third Quarter of 2016
International Bank for Reconstruction and Development
-414875Total Interest Repayment in Third Quarter of 2016
International Bank for Reconstruction and Development
-289986Total Interest Repayment in First Quarter of 2017
International Bank for Reconstruction and Development
-211226Total Interest Repayment in Third Quarter of 2017
International Bank for Reconstruction and Development
-215002Total Interest Repayment in First Quarter of 2018
International Bank for Reconstruction and Development
6853264Total Disbursement in Second Quarter of 2018
International Bank for Reconstruction and Development
-211622Total Interest Repayment in Third Quarter of 2018
International Bank for Reconstruction and Development
4481345Total Disbursement in Fourth Quarter of 2018
International Bank for Reconstruction and Development
1209608Total Disbursement in First Quarter of 2019
International Bank for Reconstruction and Development
-394940Total Interest Repayment in First Quarter of 2019
International Bank for Reconstruction and Development
2823248Total Disbursement in Second Quarter of 2019
International Development Association
16522984Total Disbursement in Second Quarter of 2019
International Bank for Reconstruction and Development
-13102Total Interest Repayment in Third Quarter of 2019
International Development Association
-464369Total Interest Repayment in Third Quarter of 2019
International Bank for Reconstruction and Development
153797Total Disbursement in Fourth Quarter of 2019
International Development Association
22189974Total Disbursement in Fourth Quarter of 2019
International Bank for Reconstruction and Development
-28686Total Interest Repayment in First Quarter of 2020
International Development Association
-990401Total Interest Repayment in First Quarter of 2020
International Bank for Reconstruction and Development
Project Information DocumentProject Information DocumentProject Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportLoan AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Finance Agreement :Project Management, Schedule 2, Section I, A, 1 of the FA and LA | Description :The Borrower shall cause ABC toassign responsibility internally for the management, implementation, monitoring and reporting of the Project among its central andregional offices, as described in detail in the Operational Manual. | Frequency :CONTINUOUS
Finance Agreement :Safeguards, Schedule 2, Section I, D, 1 of the FA and LA | Description :The Borrower shall cause ABC to carryout the Project in accordance with the Environmental Management Framework (EMF), the Resettlement Policy Framework (RPF) and theIndigenous Peoples Plan (IPP). Except as the Bank shall otherwise agree, the Borrower shall cause ABC to not assign, amend,abrogate or waive the EMF, the RPF and the IPP, or any of their provisions. | Frequency :CONTINUOUS
Finance Agreement :Terms of References, Schedule 2, Section I, D, 3 of the FA and LA | Description :The Borrower shall cause ABC toensure that the terms of reference for any consultancies related to the technical assistance provided under the Project, shall besatisfactory to the Bank and, to that end, such terms of reference shall require that the advice conveyed through such technicalassistance be consistent with the requirements of the Bank's Safeguard Policies. | Frequency :CONTINUOUS
Finance Agreement :Technical Audits, Schedule 2, Section II, C of the FA and LA | Description :In implementing Part B.2 of theProject, if applicable, as determined by the Association, the Recipient shall cause ABC to: (a) prepare and furnish to the Bank, anindependent technical audit (Technical Audit) in form and substance acceptable to the Bank which shall include, inter alia: (1) adescription of all the findings and results; (2) a list of proposed measures and actions to be taken to resolve the issuesidentified under (1) above; and (3) a proposed timeline for the implementation of said measures and actions; (b) afford the Bank areasonable opportunity to exchange views on such Technical Audit; and (c) thereafter implement such recommended measures, takinginto account the Bank's view's on the matter.
PDO Indicator
An integrated financial management (FM) information system in the ABC detailed, designed, installed, and used.
PDO Indicator
Development of an ABC strategy for primary highway network rehabilitation planning by the purchase and installation of a Pavement Management System and populating it with pertinent data.
PDO Indicator
Average International Roughness Index (IRI) of target roads at contract closings is less than 3 m per km.
Intermediate Results Indicator
Conceptual design of integrated financial management system
Intermediate Results Indicator
Direct project beneficiaries
Intermediate Results Indicator
ABC's Socio-environmental Manual updated and approved
Intermediate Results Indicator
Female beneficiaries
Intermediate Results Indicator
Pavement Management System installed and populated with information related to the primary paved network
Intermediate Results Indicator
Citizen Engagement
Intermediate Results Indicator
Road Safety Capacity Assessment
Intermediate Results Indicator
Roads rehabilitated, Non-rural
44000-P165861
World Bank
Bolivia Urban Resilience
International Development Association
International Development Association
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Ayah Mahgoub
+1-202-473-1000amahgoub@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
Departamento de La Paz
-15.5000 -68.0000
Rio Orcajahuira
-16.5170 -68.1330
Viacha
-16.6500 -68.3000
Montero
-17.6330 -62.8000
Santa Cruz de la Sierra
-17.7860 -63.1810
Irpavi
-16.5330 -68.1000
Sub-National GovernmentUrban TransportOther Water Supply, Sanitation and Waste ManagementFlood and Drought Risk ManagementUrban DevelopmentMitigationUrban Infrastructure and Service DeliveryRoad SafetyServices and Housing for the PoorDisaster PreparednessAdaptationDisaster Risk ManagementClimate changeDisaster Risk Reduction
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
156590.00
219940.00
261380.00
300720.00
337050.00
374640.00
426090.00
470260.00
498960.00
517580.00
538860.00
563290.00
584780.00
593810.00
595560.00
622020.00
674520.00
729190.00
756700.00
801990.00
872550.00
936320.00
990920.00
1050910.00
1113210.00
1172780.00
1230880.00
1278620.00
1325590.00
1384670.00
1435210.00
2226840.00
1547910.00
1604260.00
1637510.00
1651020.00
1699180.00
1735230.00
1736840.00
1724100.00
1747760.00
1756440.00
1738940.00
1727880.00
1737820.00
1733830.00
1719270.00
1695750.00
1681190.00
1676570.00
1672930.00
1668520.00
1664180.00
1658650.00
1653330.00
1648640.00
1643740.00
2796080.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
156590.00
219940.00
261380.00
300720.00
337050.00
374640.00
426090.00
470260.00
498960.00
517580.00
538860.00
563290.00
584780.00
593810.00
595560.00
622020.00
674520.00
729190.00
756700.00
801990.00
872550.00
936320.00
990920.00
1050910.00
1113210.00
1172780.00
1230880.00
1278620.00
1325590.00
1384670.00
1435210.00
2226840.00
1547910.00
1604260.00
1637510.00
1651020.00
1699180.00
1735230.00
1736840.00
1724100.00
1747760.00
1756440.00
1738940.00
1727880.00
1737820.00
1733830.00
1719270.00
1695750.00
1681190.00
1676570.00
1672930.00
1668520.00
1664180.00
1658650.00
1653330.00
1648640.00
1643740.00
2796080.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
20000000Total Commitment in First Quarter of 2020
International Development Association50000000Total Commitment in First Quarter of 2020
International Development Association0Total Disbursement in First Quarter of 2020
International Development AssociationProject Appraisal Document Implementation Status and Results ReportContract AwardsProject URLProcurement Notices
PDO Indicator
Number of households benefiting from infrastructure to protect from flood events of a 10 year return period in Project areas
PDO Indicator
People provided with improved urban living conditions
PDO Indicator
People provided with improved urban living conditions - Female (RMS requirement)
PDO Indicator
M2 of public space improved per inhabitant in Project areas
Intermediate Results Indicator
Number of households benefitting from urban upgrading measures
Intermediate Results Indicator
Km length of drainage canal improved or constructed
Intermediate Results Indicator
Grievances recorded in the GAMLP GRM system that are addressed according to the agreed service standards and communicated back to the concerned stakeholders (%)
Intermediate Results Indicator
M of river bank stabilization measures constructed
Intermediate Results Indicator
Km of bike lanes built
Intermediate Results Indicator
Grievances recorded in the GAMSC GRM system that are addressed according to the agreed service standards and communicated back to the concerned stakeholders (%)
Intermediate Results Indicator
Ha of resilient public space created
Intermediate Results Indicator
Ha of resilient public space built
Intermediate Results Indicator
Strategy for asset operation and maintenance adopted
Intermediate Results Indicator
Strategy for asset operation and maintenance adopted
Intermediate Results Indicator
Women's needs reflected in project design
Intermediate Results Indicator
Early warning system for flood events functional
Intermediate Results Indicator
Women's needs reflected in project design
44000-P083051
World Bank
BO Rural Alliances
International Development Association
GOVERNMENT
International Development Association
GOVERNMENTPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
David Tuchschneider
+1-202-473-1000dtuchschneider@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
Departamento de Santa Cruz
-17.5000 -61.5000
Departamento de Potosi
-20.6670 -67.0000
Departamento de Oruro
-18.6670 -67.5000
Departamento de Cochabamba
-17.5000 -65.6670
Provincia Nuflo de Chavez
-15.9170 -62.5000
Provincia Nuflo de Chavez
-15.9170 -62.5000
Provincia Carrasco
-17.5000 -65.0000
Tiwanacu
-16.5520 -68.6810
Huacareta
-20.3670 -64.0040
Machareti
-20.7550 -63.2330
Monteagudo
-19.9490 -64.0620
Villa de Huacaya
-20.4850 -63.8280
Villa Vaca Guzman (Muyupampa)
-19.9660 -63.7810
Copacabana
-16.1500 -69.0830
Salar de Uyuni
-20.3330 -67.7000
San Rafael
-18.4330 -59.6500
Vinto
-17.2170 -66.0830
Villa Yapacani
-17.4000 -63.8330
Villa Rivero
-17.6170 -65.8000
Villamontes
-21.2620 -63.4690
Villa Martin Colchak
-20.7410 -67.6610
Vallegrande
-18.4890 -64.1060
Vacas
-17.5750 -65.5800
Uyuni
-20.4600 -66.8250
Urubicha
-15.3930 -62.9470
Totora
-17.7270 -65.1930
Tomave
-20.1000 -66.5830
Toco
-17.6170 -65.9000
Tito Yupamqui
-16.1770 -68.9550
Tipuani
-15.5500 -68.0000
Tinquipaya
-17.3380 -66.2160
Teoponte
-15.4670 -67.8170
Tarata
-17.6090 -66.0210
Taraco
-16.4570 -68.8580
Tahua
-19.8900 -67.6950
Sipe Sipe
-17.4500 -66.3830
Santa Rosa del Sara
-17.1090 -63.5950
San Ramon
-16.7330 -62.6830
San Pedro de Quemez
-20.7470 -68.0500
San Pedro
-16.8260 -63.4800
San Pedro
-16.2370 -68.8510
San Julian
-17.7830 -62.8670
San Juan del Surutu
-17.4830 -63.7000
San Javier
-16.2750 -62.5040
San Ignacio de Velasco
-16.3670 -60.9500
San Carlos
-17.9670 -63.3170
San Buena Ventura
-14.4670 -67.5830
San Buena Ventura
-14.4670 -67.5830
San Benito
-17.5170 -65.9170
San Andres de Machaca
-16.9500 -68.9670
San Agustin
-21.1560 -67.6800
Salinas de Garci Mendoza
-19.6370 -67.6750
Saipina
-18.0940 -64.5830
Sacaba
-17.3980 -66.0380
Rurrenabaque
-14.4410 -67.5280
Reyes
-14.2950 -67.3360
Quillacollo
-17.3920 -66.2780
Quillacas
-19.2330 -66.9420
Punata
-17.5420 -65.8350
Puesto Fernandez
-17.0000 -63.2330
Puerto Perez
-16.2670 -68.6330
Puerto Acosta
-15.5330 -69.2500
Pucarani
-16.4000 -68.4780
Portachuelo
-17.3520 -63.3930
Pojo
-17.7500 -64.8170
Pocona
-17.6500 -65.4000
Pampa Aullagas
-19.1960 -67.0610
Pailon
-17.6500 -62.7500
Okinawa Numero Uno
-17.2330 -62.8170
Montero
-17.3390 -63.2510
Mineros
-17.1190 -63.2310
Mapiri
-15.2500 -68.1670
Llica
-19.8510 -68.2480
Lagunillas
-19.6510 -63.6750
La Guardia
-17.8890 -63.3290
La Belgica
-17.5500 -63.2170
Jesus de Machaca
-16.7500 -68.8330
Ixiamas
-13.7500 -68.1500
Huari
-19.0130 -66.7770
Gutierrez
-19.4230 -63.5290
Guaqui
-16.5830 -68.8670
General Saavedra
-17.2260 -63.2120
Entre Rios
-21.5270 -64.1730
El Torno
-16.9670 -63.2670
El Puente
-16.3260 -62.9070
Desaguadero
-16.5670 -69.0330
Cuevo
-20.4530 -63.5180
Concepcion
-16.4330 -60.9000
Comarapa
-17.9150 -64.5320
Colomi
-17.3500 -65.8670
Cliza
-17.5880 -65.9330
Charagua
-19.7920 -63.1990
Challapata
-18.9020 -66.7700
Carapari
-21.6890 -65.2050
Caranavi
-15.8170 -67.5500
Carabuco
-15.7500 -69.0670
Camiri
-20.0380 -63.5180
Caiza
-20.0080 -65.6540
Cabezas
-18.7890 -63.3010
Buena Vista
-17.4580 -63.6710
Boyuibe
-20.4320 -63.2810
Batallas
-16.3330 -68.5000
Ayacucho
-17.8500 -63.3330
Arbieto
-17.5670 -66.0170
Arani
-17.5690 -65.7690
Apolo
-14.7190 -68.4120
Ancoraimes
-16.1700 -69.0790
Achacachi
-16.0500 -68.6830
Khushmuqam
34.8560 71.9440
Yacuiba
-22.0160 -63.6780
Andamarca
-18.7790 -67.5080
Guanay
-15.4980 -67.8830
Coroico
-16.1940 -67.7300
Ascencion De Guarayos
-15.9330 -63.1550
Other Agriculture, Fishing and ForestryAgricultural Extension, Research, and Other Support ActivitiesAgricultural markets, commercialization and agri-businessFinance for DevelopmentAgriculture FinanceRural Infrastructure and service deliveryRural MarketsRural Development
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
66666.67
66666.67
66666.66
83333.33
83333.33
83333.34
193333.33
193333.33
193333.34
193333.33
193333.33
193333.34
193333.33
193333.33
193333.34
193333.33
193333.33
193333.34
193333.33
193333.33
193333.34
283333.33
283333.33
283333.34
283333.33
283333.33
283333.34
283333.33
283333.33
283333.34
366666.67
366666.67
366666.66
600000.00
600000.00
600000.00
700000.00
700000.00
700000.00
700000.00
700000.00
700000.00
700000.00
700000.00
700000.00
700000.00
700000.00
700000.00
933333.33
933333.33
933333.34
933333.33
933333.33
933333.34
700000.00
700000.00
700000.00
700000.00
700000.00
700000.00
466666.67
466666.67
466666.66
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
66666.66
66666.67
66666.67
83333.33
83333.33
83333.34
193333.33
193333.33
193333.34
193333.33
193333.33
193333.34
193333.33
193333.33
193333.34
193333.33
193333.33
193333.34
193333.33
193333.33
193333.34
283333.33
283333.33
283333.34
283333.33
283333.33
283333.34
283333.33
283333.33
283333.34
366666.66
366666.67
366666.67
600000.00
600000.00
600000.00
883333.33
883333.33
883333.34
883333.33
883333.33
883333.34
883333.33
883333.33
883333.34
883333.33
883333.33
883333.34
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1266666.66
1266666.67
1266666.67
1266666.66
1266666.67
1266666.67
1258333.33
1258333.33
1258333.34
791666.66
791666.67
791666.67
791666.66
791666.67
791666.67
791666.66
791666.67
791666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
166666.66
166666.67
166666.67
0.00
0.00
0.00
0.00
0.00
0.00
0.00
28400000Total Commitment in Second Quarter of 2005
International Development Association500000Total Disbursement in Second Quarter of 2006
International Development Association-64810Total Interest Repayment in Third Quarter of 2006
International Development Association118321Total Disbursement in Fourth Quarter of 2006
International Development Association312158Total Disbursement in First Quarter of 2007
International Development Association-30495Total Interest Repayment in First Quarter of 2007
International Development Association84703Total Disbursement in Second Quarter of 2007
International Development Association313603Total Disbursement in Third Quarter of 2007
International Development Association-31135Total Interest Repayment in Third Quarter of 2007
International Development Association152311Total Disbursement in Fourth Quarter of 2007
International Development Association903188Total Disbursement in Fourth Quarter of 2007
International Development Association466246Total Disbursement in First Quarter of 2008
International Development Association525468Total Disbursement in First Quarter of 2008
International Development Association-20970Total Interest Repayment in First Quarter of 2008
International Development Association383548Total Disbursement in Second Quarter of 2008
International Development Association838559Total Disbursement in Second Quarter of 2008
International Development Association503350Total Disbursement in Third Quarter of 2008
International Development Association656054Total Disbursement in Third Quarter of 2008
International Development Association-27893Total Interest Repayment in Third Quarter of 2008
International Development Association849562Total Disbursement in Fourth Quarter of 2008
International Development Association1290867Total Disbursement in Fourth Quarter of 2008
International Development Association1648692Total Disbursement in Fourth Quarter of 2008
International Development Association1629336Total Disbursement in First Quarter of 2009
International Development Association-26284Total Interest Repayment in First Quarter of 2009
International Development Association650551Total Disbursement in Second Quarter of 2009
International Development Association794896Total Disbursement in Second Quarter of 2009
International Development Association30000000Total Commitment in Second Quarter of 2009
International Development Association1057231Total Disbursement in Third Quarter of 2009
International Development Association-45154Total Interest Repayment in Third Quarter of 2009
International Development Association743166Total Disbursement in Fourth Quarter of 2009
International Development Association1690609Total Disbursement in Fourth Quarter of 2009
International Development Association1692403Total Disbursement in Fourth Quarter of 2009
International Development Association503250Total Disbursement in First Quarter of 2010
International Development Association1228381Total Disbursement in First Quarter of 2010
International Development Association-60270Total Interest Repayment in First Quarter of 2010
International Development Association628310Total Disbursement in Second Quarter of 2010
International Development Association445998Total Disbursement in Third Quarter of 2010
International Development Association885175Total Disbursement in Third Quarter of 2010
International Development Association-70329Total Interest Repayment in Third Quarter of 2010
International Development Association1000000Total Disbursement in Third Quarter of 2010
International Development Association842801Total Disbursement in Fourth Quarter of 2010
International Development Association1074971Total Disbursement in Fourth Quarter of 2010
International Development Association1862473Total Disbursement in Fourth Quarter of 2010
International Development Association2853185Total Disbursement in Fourth Quarter of 2010
International Development Association72145Total Disbursement in First Quarter of 2011
International Development Association1781663Total Disbursement in First Quarter of 2011
International Development Association-89085Total Interest Repayment in First Quarter of 2011
International Development Association7699Total Disbursement in First Quarter of 2011
International Development Association629643Total Disbursement in First Quarter of 2011
International Development Association-3908Total Interest Repayment in First Quarter of 2011
International Development Association1200712Total Disbursement in Second Quarter of 2011
International Development Association648626Total Disbursement in Second Quarter of 2011
International Development Association895464Total Disbursement in Second Quarter of 2011
International Development Association-108598Total Interest Repayment in Third Quarter of 2011
International Development Association1111253Total Disbursement in Third Quarter of 2011
International Development Association1226084Total Disbursement in Third Quarter of 2011
International Development Association2129360Total Disbursement in Third Quarter of 2011
International Development Association-22341Total Interest Repayment in Third Quarter of 2011
International Development Association228781Total Disbursement in Fourth Quarter of 2011
International Development Association1212067Total Disbursement in Fourth Quarter of 2011
International Development Association1452908Total Disbursement in Fourth Quarter of 2011
International Development Association2268916Total Disbursement in Fourth Quarter of 2011
International Development Association338108Total Disbursement in First Quarter of 2012
International Development Association-106077Total Interest Repayment in First Quarter of 2012
International Development Association380474Total Disbursement in First Quarter of 2012
International Development Association570706Total Disbursement in First Quarter of 2012
International Development Association1367420Total Disbursement in First Quarter of 2012
International Development Association-47588Total Interest Repayment in First Quarter of 2012
International Development Association335378Total Disbursement in Second Quarter of 2012
International Development Association790082Total Disbursement in Second Quarter of 2012
International Development Association997883Total Disbursement in Second Quarter of 2012
International Development Association1646204Total Disbursement in Second Quarter of 2012
International Development Association-106972Total Interest Repayment in Third Quarter of 2012
International Development Association898284Total Disbursement in Third Quarter of 2012
International Development Association1185915Total Disbursement in Third Quarter of 2012
International Development Association1663105Total Disbursement in Third Quarter of 2012
International Development Association-71862Total Interest Repayment in Third Quarter of 2012
International Development Association1033017Total Disbursement in Fourth Quarter of 2012
International Development Association1598832Total Disbursement in Fourth Quarter of 2012
International Development Association-108188Total Interest Repayment in First Quarter of 2013
International Development Association456412Total Disbursement in First Quarter of 2013
International Development Association-97415Total Interest Repayment in First Quarter of 2013
International Development Association450242Total Disbursement in Second Quarter of 2013
International Development Association1110634Total Disbursement in Second Quarter of 2013
International Development Association-107599Total Interest Repayment in Third Quarter of 2013
International Development Association1022990Total Disbursement in Third Quarter of 2013
International Development Association-106119Total Interest Repayment in Third Quarter of 2013
International Development Association134716Total Disbursement in Fourth Quarter of 2013
International Development Association-108997Total Interest Repayment in First Quarter of 2014
International Development Association-113801Total Interest Repayment in First Quarter of 2014
International Development Association-638Total Disbursement in Third Quarter of 2014
International Development Association-108809Total Interest Repayment in Third Quarter of 2014
International Development Association-31006Total Disbursement in Third Quarter of 2014
International Development Association-114716Total Interest Repayment in Third Quarter of 2014
International Development Association-638Total Commitment Cancellations in Fourth Quarter of 2014
International Development Association-31006Total Commitment Cancellations in Fourth Quarter of 2014
International Development Association-100322Total Interest Repayment in First Quarter of 2015
International Development Association-105546Total Interest Repayment in First Quarter of 2015
International Development Association-99481Total Interest Repayment in Third Quarter of 2015
International Development Association-331602Total Loan Repayment in Third Quarter of 2015
International Development Association-104637Total Interest Repayment in Third Quarter of 2015
International Development Association-94718Total Interest Repayment in First Quarter of 2016
International Development Association-332117Total Loan Repayment in First Quarter of 2016
International Development Association-103906Total Interest Repayment in First Quarter of 2016
International Development Association-100081Total Interest Repayment in Third Quarter of 2016
International Development Association-329696Total Loan Repayment in Third Quarter of 2016
International Development Association-104923Total Interest Repayment in Third Quarter of 2016
International Development Association-89001Total Interest Repayment in First Quarter of 2017
International Development Association-318909Total Loan Repayment in First Quarter of 2017
International Development Association-99877Total Interest Repayment in First Quarter of 2017
International Development Association-90277Total Interest Repayment in Third Quarter of 2017
International Development Association-332481Total Loan Repayment in Third Quarter of 2017
International Development Association-103812Total Interest Repayment in Third Quarter of 2017
International Development Association-91168Total Interest Repayment in First Quarter of 2018
International Development Association-344584Total Loan Repayment in First Quarter of 2018
International Development Association-107313Total Interest Repayment in First Quarter of 2018
International Development Association-103706Total Interest Repayment in Third Quarter of 2018
International Development Association-326816Total Loan Repayment in Third Quarter of 2018
International Development Association-106332Total Interest Repayment in Third Quarter of 2018
International Development Association-87391Total Interest Repayment in First Quarter of 2019
International Development Association-327570Total Loan Repayment in First Quarter of 2019
International Development Association-102800Total Interest Repayment in First Quarter of 2019
International Development Association-89928Total Interest Repayment in Third Quarter of 2019
International Development Association-324692Total Loan Repayment in Third Quarter of 2019
International Development Association-103017Total Interest Repayment in Third Quarter of 2019
International Development Association-341522Total Loan Repayment in Third Quarter of 2019
International Development Association-86017Total Interest Repayment in First Quarter of 2020
International Development Association-323067Total Loan Repayment in First Quarter of 2020
International Development Association-100669Total Interest Repayment in First Quarter of 2020
International Development Association-339812Total Loan Repayment in First Quarter of 2020
International Development AssociationProject Information DocumentProject Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportCredit AgreementFinancing AgreementProject Performance Assessment ReportContract AwardsProject URLProcurement Notices
Completing the staffing of the UCN and UORs
Consultants that carry out feasibility studies have been selected
Financial evaluation experts hired
Prefectura agreements
FPS agreement
FONDESIF agreement
By November 15 of each year, Annual Operating Plan furnished to IDA
By April 15 and October 15 of each year, Progress Report furnished to IDA
Complete the staffing of the UORs
Intermediate Results Indicator
Number of alliances supported in their organization
Final number, exceeding EOP target by 28%
Intermediate Results Indicator
Number of alliances financed
Final number, exceeding EOP target by 14%.
PDO Indicator
Growth (%) in income of rural productive units (gross income per household per year)
This indicator will be measured at the end of the project through a survey.
PDO Indicator
Number of financed alliances with IRR>12.5%
Study of all alliances under preparation.
PDO Indicator
Percentage of new wage earning jobs generated (man-day)
Study of all alliances under preparation.
PDO Indicator
Percentage increase in the volume marketed per rural productive unit
From preliminary analysis of data on 761 concluded alliances.
PDO Indicator
Alliance model implemented
Follow up Rural Alliances II project under implementation. Flagship project in Bolivia portfolio.
Intermediate Results Indicator
Number of alliances identified with a viable plan
Final number, exceeding EOP target by 50%.
Intermediate Results Indicator
Number of alliance members who received training in institutional strengtheningfor alliance operation
Final number, exceeding EOP target by 64%
Intermediate Results Indicator
Percentage of alliances with positive financial results
Final number will be reported in the next ISR.
Intermediate Results Indicator
Number of families receiving direct benefits from producer subprojects
Final number of beneficiaries in 770 financed producer subprojects.
Intermediate Results Indicator
Number of families receiving indirect benefits through municipal subprojects
The baseline is established as zero for municipal subprojects associated with approved alliances.
Final number to be reported in next ISR, once portfolio is closed
44000-P083979
World Bank
Bolivia Urban Infrastructure Project
International Development Association
MUNI LA PAZ, MUNI EL ALTO, SAGUAPAC
International Development Association
MUNI LA PAZ, MUNI EL ALTO, SAGUAPACPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Zoe Elena Trohanis
+1-202-473-1000ztrohanis@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
El Alto
-16.4830 -68.1830
Copacabana
-16.1500 -69.0830
Viacha
-16.6500 -68.3000
Desaguadero
-16.5670 -69.0330
Santa Cruz de la Sierra
-17.7860 -63.1810
Oruro
-17.9830 -67.1500
Cochabamba
-17.3900 -66.1570
La Paz
-16.5000 -68.1500
Other TransportationSocial ProtectionOther Water Supply, Sanitation and Waste ManagementSanitationSub-National GovernmentOther Public AdministrationUrban TransportUrban DevelopmentUrban Infrastructure and Service DeliveryMunicipal Institution BuildingRule of LawPublic Private PartnershipsEnvironmental Health and Pollution ManagementServices and Housing for the PoorAir quality managementAdministrative and Civil Service ReformSoil PollutionPublic AdministrationPersonal and Property RightsWater Pollution
4878.04
4878.04
4878.06
170731.71
170731.71
170731.70
248780.49
248780.49
248780.49
336585.37
336585.37
336585.37
365853.66
365853.66
365853.66
429268.29
429268.29
429268.30
517073.17
517073.17
517073.18
565853.66
565853.66
565853.65
643902.44
643902.44
643902.44
717073.17
717073.17
717073.17
780487.80
780487.80
780487.82
804878.05
804878.05
804878.05
824390.24
824390.24
824390.25
863414.63
863414.63
863414.63
917073.18
917073.18
917073.16
936585.37
936585.37
936585.37
995121.95
995121.95
995121.95
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
537208.87
369637.36
369637.36
369637.38
891941.24
891941.25
891941.25
226018.33
226018.33
226018.35
666666.66
666666.67
666666.67
512195.12
512195.12
512195.11
833333.33
833333.33
833333.34
512195.12
512195.12
512195.11
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
833333.33
833333.33
833333.34
666666.66
666666.67
666666.67
833333.33
833333.33
833333.34
623333.33
623333.33
623333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
194887.80
194887.80
194887.81
133948.79
133948.79
133948.77
246277.57
246277.57
246277.55
466511.22
466511.22
466511.21
1333333.17
1333333.17
1333333.17
566666.34
566666.34
566666.34
1319105.37
1319105.37
1319105.36
1475609.75
1475609.75
1475609.77
1775609.75
1775609.75
1775609.77
1145219.02
1145219.02
1145219.03
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
30000000Total Commitment in Fourth Quarter of 2006
International Development Association537209Total Disbursement in Third Quarter of 2007
International Development Association10412Total Disbursement in Fourth Quarter of 2007
International Development Association10412Total Disbursement in Fourth Quarter of 2007
International Development Association1088088Total Disbursement in Fourth Quarter of 2007
International Development Association719452Total Disbursement in First Quarter of 2008
International Development Association861335Total Disbursement in First Quarter of 2008
International Development Association1095037Total Disbursement in First Quarter of 2008
International Development Association-36350Total Interest Repayment in First Quarter of 2008
International Development Association30270Total Disbursement in Second Quarter of 2008
International Development Association132053Total Disbursement in Second Quarter of 2008
International Development Association253830Total Disbursement in Second Quarter of 2008
International Development Association112114Total Disbursement in Third Quarter of 2008
International Development Association408554Total Disbursement in Third Quarter of 2008
International Development Association1089652Total Disbursement in Third Quarter of 2008
International Development Association-30995Total Interest Repayment in Third Quarter of 2008
International Development Association494681Total Disbursement in Fourth Quarter of 2008
International Development Association571542Total Disbursement in Fourth Quarter of 2008
International Development Association2428030Total Disbursement in Fourth Quarter of 2008
International Development Association232832Total Disbursement in First Quarter of 2009
International Development Association1180473Total Disbursement in First Quarter of 2009
International Development Association1340455Total Disbursement in First Quarter of 2009
International Development Association-25860Total Interest Repayment in First Quarter of 2009
International Development Association440541Total Disbursement in Second Quarter of 2009
International Development Association778154Total Disbursement in Second Quarter of 2009
International Development Association1019654Total Disbursement in Second Quarter of 2009
International Development Association184165Total Disbursement in Third Quarter of 2009
International Development Association866186Total Disbursement in Third Quarter of 2009
International Development Association1366225Total Disbursement in Third Quarter of 2009
International Development Association-51668Total Interest Repayment in Third Quarter of 2009
International Development Association426188Total Disbursement in Fourth Quarter of 2009
International Development Association557000Total Disbursement in Fourth Quarter of 2009
International Development Association1052717Total Disbursement in Fourth Quarter of 2009
International Development Association912738Total Disbursement in First Quarter of 2010
International Development Association1191361Total Disbursement in First Quarter of 2010
International Development Association-69779Total Interest Repayment in First Quarter of 2010
International Development Association86182Total Disbursement in Second Quarter of 2010
International Development Association150318Total Disbursement in Second Quarter of 2010
International Development Association154500Total Disbursement in Second Quarter of 2010
International Development Association275355Total Disbursement in Third Quarter of 2010
International Development Association622603Total Disbursement in Third Quarter of 2010
International Development Association813564Total Disbursement in Third Quarter of 2010
International Development Association-76249Total Interest Repayment in Third Quarter of 2010
International Development Association288702Total Disbursement in Fourth Quarter of 2010
International Development Association315070Total Disbursement in Fourth Quarter of 2010
International Development Association1230812Total Disbursement in Fourth Quarter of 2010
International Development Association241440Total Disbursement in First Quarter of 2011
International Development Association572570Total Disbursement in First Quarter of 2011
International Development Association596635Total Disbursement in First Quarter of 2011
International Development Association-92451Total Interest Repayment in First Quarter of 2011
International Development Association402771Total Disbursement in Second Quarter of 2011
International Development Association801046Total Disbursement in Second Quarter of 2011
International Development Association806791Total Disbursement in Second Quarter of 2011
International Development Association422097Total Disbursement in Third Quarter of 2011
International Development Association-108744Total Interest Repayment in Third Quarter of 2011
International Development Association258Total Disbursement in Fourth Quarter of 2011
International Development Association115108Total Disbursement in Fourth Quarter of 2011
International Development Association423191Total Disbursement in Fourth Quarter of 2011
International Development Association-110634Total Interest Repayment in First Quarter of 2012
International Development Association337735Total Disbursement in Second Quarter of 2012
International Development Association157853Total Disbursement in Third Quarter of 2012
International Development Association416068Total Disbursement in Third Quarter of 2012
International Development Association-109490Total Interest Repayment in Third Quarter of 2012
International Development Association279299Total Disbursement in Fourth Quarter of 2012
International Development Association317865Total Disbursement in Fourth Quarter of 2012
International Development Association24000000Total Commitment in Fourth Quarter of 2012
International Development Association35823Total Disbursement in First Quarter of 2013
International Development Association-114069Total Interest Repayment in First Quarter of 2013
International Development Association-114858Total Interest Repayment in Third Quarter of 2013
International Development Association-116350Total Interest Repayment in First Quarter of 2014
International Development Association-116150Total Interest Repayment in Third Quarter of 2014
International Development Association600000Total Disbursement in Third Quarter of 2014
International Development Association400000Total Disbursement in Fourth Quarter of 2014
International Development Association-107092Total Interest Repayment in First Quarter of 2015
International Development Association712380Total Disbursement in First Quarter of 2015
International Development Association-4801Total Interest Repayment in First Quarter of 2015
International Development Association687183Total Disbursement in Second Quarter of 2015
International Development Association907898Total Disbursement in Second Quarter of 2015
International Development Association452992Total Disbursement in Third Quarter of 2015
International Development Association-106252Total Interest Repayment in Third Quarter of 2015
International Development Association376683Total Disbursement in Third Quarter of 2015
International Development Association473693Total Disbursement in Third Quarter of 2015
International Development Association540350Total Disbursement in Third Quarter of 2015
International Development Association-24539Total Interest Repayment in Third Quarter of 2015
International Development Association397228Total Disbursement in Fourth Quarter of 2015
International Development Association542476Total Disbursement in Fourth Quarter of 2015
International Development Association2424877Total Disbursement in Fourth Quarter of 2015
International Development Association-5970Total Disbursement in First Quarter of 2016
International Development Association-107207Total Interest Repayment in First Quarter of 2016
International Development Association1712412Total Disbursement in First Quarter of 2016
International Development Association-56109Total Interest Repayment in First Quarter of 2016
International Development Association-57902Total Commitment Cancellations in Second Quarter of 2016
International Development Association-51785Total Disbursement in Second Quarter of 2016
International Development Association733663Total Disbursement in Second Quarter of 2016
International Development Association-108058Total Interest Repayment in Third Quarter of 2016
International Development Association413258Total Disbursement in Third Quarter of 2016
International Development Association552521Total Disbursement in Third Quarter of 2016
International Development Association904143Total Disbursement in Third Quarter of 2016
International Development Association-106590Total Interest Repayment in Third Quarter of 2016
International Development Association780250Total Disbursement in Fourth Quarter of 2016
International Development Association1503082Total Disbursement in Fourth Quarter of 2016
International Development Association-100199Total Interest Repayment in First Quarter of 2017
International Development Association-345223Total Loan Repayment in First Quarter of 2017
International Development Association182832Total Disbursement in First Quarter of 2017
International Development Association941852Total Disbursement in First Quarter of 2017
International Development Association-123321Total Interest Repayment in First Quarter of 2017
International Development Association61463Total Disbursement in Second Quarter of 2017
International Development Association-101733Total Interest Repayment in Third Quarter of 2017
International Development Association-359915Total Loan Repayment in Third Quarter of 2017
International Development Association45016Total Disbursement in Third Quarter of 2017
International Development Association789555Total Disbursement in Third Quarter of 2017
International Development Association-159734Total Interest Repayment in Third Quarter of 2017
International Development Association227949Total Disbursement in Fourth Quarter of 2017
International Development Association439773Total Disbursement in Fourth Quarter of 2017
International Development Association-767931Total Commitment Cancellations in First Quarter of 2018
International Development Association-767931Total Disbursement in First Quarter of 2018
International Development Association-102832Total Interest Repayment in First Quarter of 2018
International Development Association-373017Total Loan Repayment in First Quarter of 2018
International Development Association-2013931Total Disbursement in First Quarter of 2018
International Development Association-163806Total Interest Repayment in First Quarter of 2018
International Development Association-385068Total Loan Repayment in First Quarter of 2018
International Development Association-50682Total Disbursement in Second Quarter of 2018
International Development Association-113031Total Interest Repayment in Third Quarter of 2018
International Development Association-344110Total Loan Repayment in Third Quarter of 2018
International Development Association-161332Total Interest Repayment in Third Quarter of 2018
International Development Association-365212Total Loan Repayment in Third Quarter of 2018
International Development Association-45649Total Disbursement in Fourth Quarter of 2018
International Development Association-95875Total Interest Repayment in First Quarter of 2019
International Development Association-344904Total Loan Repayment in First Quarter of 2019
International Development Association-6929502Total Commitment Cancellations in First Quarter of 2019
International Development Association-142363Total Interest Repayment in First Quarter of 2019
International Development Association-366054Total Loan Repayment in First Quarter of 2019
International Development Association-98554Total Interest Repayment in Third Quarter of 2019
International Development Association-341874Total Loan Repayment in Third Quarter of 2019
International Development Association-142800Total Interest Repayment in Third Quarter of 2019
International Development Association-243082Total Loan Repayment in Third Quarter of 2019
International Development Association-94395Total Interest Repayment in First Quarter of 2020
International Development Association-340163Total Loan Repayment in First Quarter of 2020
International Development Association-136910Total Interest Repayment in First Quarter of 2020
International Development Association-241865Total Loan Repayment in First Quarter of 2020
International Development AssociationProject Information DocumentProject Information DocumentProject Information DocumentProject Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementFinancing AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Intermediate Results Indicator
Percent increase of cadastre housing value - La Paz
Intermediate Results Indicator
Walking time to nearest transport stop - La Paz
Intermediate Results Indicator
Number of temporary employments - La Paz
Intermediate Results Indicator
Percent of crimes reported by female household heads in the last three months - La Paz
Intermediate Results Indicator
Square meters of improved constructed or improved vehicle roads and pedestrian pathways - La Paz
Intermediate Results Indicator
Cubic meters of stabilization works - La Paz
Intermediate Results Indicator
Square meters of forested green space - La Paz
Intermediate Results Indicator
Meters of restored or constructed linear canals - La Paz
Intermediate Results Indicator
Square meters of recreational space built - La Paz
Intermediate Results Indicator
Strategy to improve the efficiency of the public transport system designed - El Alto
Intermediate Results Indicator
Non-motorized strategy design - El Alto
Intermediate Results Indicator
Number of bicycles in the main arteries (J. Arzabe street) - El Alto
Intermediate Results Indicator
Kilometers of paved bicycle paths (J. Arzabe street) - El Alto
Intermediate Results Indicator
Linear meters of sidewalk border - El Alto
Intermediate Results Indicator
Average increase in n# of vehicles/day in the 1st and 2nd rings
Intermediate Results Indicator
Minutes between the north and south zones of the city (from intersection Viacha High Road and Litoral to the intersection of Costanera II Avenue and Juan Pablo II Avenue) - El Alto
Intermediate Results Indicator
Construction of Secondary collector UV 105(P) and 114: - Santa Cruz
Intermediate Results Indicator
Construction of Secondary collector UV 115 and 140 - Santa Cruz
Intermediate Results Indicator
Construction of Secondary collector UV 119 and 118(A): - Santa Cruz
Intermediate Results Indicator
No. of UV 105(P) and 114 Household Connections - Santa Cruz
Intermediate Results Indicator
No. of UV 115 and 140 Household Connections - Santa Cruz
Intermediate Results Indicator
No. of UV 119 and 118(A) Household Connections - Santa Cruz
Intermediate Results Indicator
Average Concentration of nitrate (NO3) - Santa Cruz
PDO Indicator
Increased property values in participating poor neighborhoods in La Paz as a result of improved access to basic urban services (measured according to monthly rent in US dollars)
PDO Indicator
Improved urban mobility in El Alto, especially for the urban poor, as a result of access to improved roads and non-motorized transport alternatives (minutes)
PDO Indicator
Increased coverage of Santa Cruz's sewerage networks in poor neighborhoods. (Number of new inhabitants with connections. 4 people/connection)
PDO Indicator
Reduced rate of groundwater contamination (mg/L) - Santa Cruz
Intermediate Results Indicator
km of rain drainage built - La Paz
Intermediate Results Indicator
Volume of earth moved for works - El Alto
Intermediate Results Indicator
Km of rain drainage - Santa Cruz
PDO Indicator
Direct project beneficiaries - La Paz
Intermediate Results Indicator
Percentage of people that report that the neighborhood is a safer place to live - La Paz
Intermediate Results Indicator
Number of families with access to recreational spaces constructed by the Project - La Paz
Intermediate Results Indicator
Number of families with access to communal houses/ spaces built by the Project - La Paz
Intermediate Results Indicator
Perception of risk related to weather events in housing unit and neighborhood as a consequence of project intervention - La Paz.
Intermediate Results Indicator
Number of houses with new sanitary connections - La Paz.
Intermediate Results Indicator
Number of groups created for sustainability after project's intervention - La Paz.
Intermediate Results Indicator
Number of families that have obtained property registration as a consequence of the Project - La Paz.
Intermediate Results Indicator
Roads constructed, non-rural - El Alto
PDO Indicator
Direct project beneficiaries - La Paz
Intermediate Results Indicator
Number of people in urban areas provided with access to all-season roads within a 500 meter range under the project - La Paz
Intermediate Results Indicator
Number of people in urban areas provided with access to Improved Sanitation under the project - La Paz
PDO Indicator
Female beneficiaries - La Paz
PDO Indicator
Female beneficiaries - La Paz
44000-P106700
World Bank
Agricultural Innovation and Services
International Development Association
GOVERNMENT OF BOLIVIA
International Development Association
GOVERNMENT OF BOLIVIAPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Francisco Javier Obreque Arqueros
+1-202-473-1000fobreque@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
Departamento de La Paz
-15.5000 -68.0000
CropsPublic Administration - Agriculture, Fishing & ForestryAgricultural Extension, Research, and Other Support ActivitiesBiodiversityLandscape ManagementRural Infrastructure and service deliveryAgriculture FinanceLand Administration and ManagementAdaptationJobsFinance for DevelopmentMitigationRural DevelopmentRural MarketsClimate changeRenewable Natural Resources Asset Management
0.00
0.00
0.00
0.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
333333.33
333333.33
333333.34
333333.33
333333.33
333333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
333333.33
333333.33
333333.34
333333.33
333333.33
333333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
39000000Total Commitment in Third Quarter of 2011
International Development Association698997Total Disbursement in First Quarter of 2012
International Development Association693540Total Disbursement in Second Quarter of 2012
International Development Association700000Total Disbursement in Second Quarter of 2012
International Development Association-6348Total Interest Repayment in Third Quarter of 2012
International Development Association270629Total Disbursement in First Quarter of 2013
International Development Association800000Total Disbursement in First Quarter of 2013
International Development Association-23289Total Interest Repayment in First Quarter of 2013
International Development Association3187798Total Disbursement in Second Quarter of 2013
International Development Association846900Total Disbursement in Third Quarter of 2013
International Development Association-30148Total Interest Repayment in Third Quarter of 2013
International Development Association677789Total Disbursement in Fourth Quarter of 2013
International Development Association687323Total Disbursement in Fourth Quarter of 2013
International Development Association872345Total Disbursement in Fourth Quarter of 2013
International Development Association1851576Total Disbursement in First Quarter of 2014
International Development Association-77924Total Interest Repayment in First Quarter of 2014
International Development Association142961Total Disbursement in Second Quarter of 2014
International Development Association1080877Total Disbursement in Second Quarter of 2014
International Development Association734376Total Disbursement in Third Quarter of 2014
International Development Association1169594Total Disbursement in Third Quarter of 2014
International Development Association-115244Total Interest Repayment in Third Quarter of 2014
International Development Association298962Total Disbursement in Fourth Quarter of 2014
International Development Association765591Total Disbursement in Fourth Quarter of 2014
International Development Association1734092Total Disbursement in Fourth Quarter of 2014
International Development Association833823Total Disbursement in First Quarter of 2015
International Development Association1261847Total Disbursement in First Quarter of 2015
International Development Association-139670Total Interest Repayment in First Quarter of 2015
International Development Association1370372Total Disbursement in Second Quarter of 2015
International Development Association888864Total Disbursement in Third Quarter of 2015
International Development Association1132317Total Disbursement in Third Quarter of 2015
International Development Association-181447Total Interest Repayment in Third Quarter of 2015
International Development Association759055Total Disbursement in Fourth Quarter of 2015
International Development Association1326461Total Disbursement in Fourth Quarter of 2015
International Development Association1838990Total Disbursement in Fourth Quarter of 2015
International Development Association466369Total Disbursement in First Quarter of 2016
International Development Association2083183Total Disbursement in First Quarter of 2016
International Development Association-212241Total Interest Repayment in First Quarter of 2016
International Development Association272970Total Disbursement in Second Quarter of 2016
International Development Association1375187Total Disbursement in Second Quarter of 2016
International Development Association926501Total Disbursement in Third Quarter of 2016
International Development Association1079304Total Disbursement in Third Quarter of 2016
International Development Association-286884Total Interest Repayment in Third Quarter of 2016
International Development Association516274Total Disbursement in Fourth Quarter of 2016
International Development Association763989Total Disbursement in Fourth Quarter of 2016
International Development Association767261Total Disbursement in Fourth Quarter of 2016
International Development Association-307352Total Interest Repayment in First Quarter of 2017
International Development Association-544013Total Loan Repayment in First Quarter of 2017
International Development Association-802688Total Commitment Cancellations in Third Quarter of 2017
International Development Association-185430Total Disbursement in Third Quarter of 2017
International Development Association-45809Total Disbursement in Third Quarter of 2017
International Development Association-2036Total Disbursement in Third Quarter of 2017
International Development Association-315221Total Interest Repayment in Third Quarter of 2017
International Development Association-559803Total Loan Repayment in Third Quarter of 2017
International Development Association-330900Total Interest Repayment in First Quarter of 2018
International Development Association-562974Total Loan Repayment in First Quarter of 2018
International Development Association-329685Total Interest Repayment in Third Quarter of 2018
International Development Association-550810Total Loan Repayment in Third Quarter of 2018
International Development Association-301910Total Interest Repayment in First Quarter of 2019
International Development Association-548190Total Loan Repayment in First Quarter of 2019
International Development Association-309362Total Interest Repayment in Third Quarter of 2019
International Development Association-544033Total Loan Repayment in Third Quarter of 2019
International Development Association-293627Total Interest Repayment in First Quarter of 2020
International Development Association-542744Total Loan Repayment in First Quarter of 2020
International Development AssociationProject Information DocumentProject Information DocumentProject Appraisal DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Finance Agreement :Article IV; 4.01 of the FA. | Description :Maintenance of INIAFs Legal Framework and the Normas Basicas delSistema de Administracin de Bienes y Servicios (Procurement Regulations) throughout the implementation of the Project | Frequency:Yearly
Finance Agreement :Article IV; 4.02 of the FA. | Description :Co-financing Deadline on June 1, 2012 | Due Date :01-Jun-2012
Finance Agreement :Article V; 5.01(a) & 5.02; Section I.B of Schedule 2 | Description :Subsidiary Agreement between INIAF and theRecipient signed and Legal Opinion issued | Due Date :20-Jan-2012
Finance Agreement :Article V; 5.01 (b); Schedule 2, Section I.C | Description :Operational Manual approved/adopted | Due Date:29-Jun-2011
Finance Agreement :Schedule 2; Section I.A.1(b) & (c) | Description :Maintenance of a Technical Coordination Team and Board ofDirectors throughout the Project | Frequency :Yearly
Finance Agreement :Schedule 2; Section I.A.1(d) | Description :Competitive selection of staff for Project Management | Frequency:Yearly
Finance Agreement :Schedule 2; Section I.A.2 | Description :Establishment of Research Fund Management Unit | Frequency :Yearly
Finance Agreement :Schedule 2, Section I.A.3 | Description :Establishment of Evaluation Committee for the Research Fund | Due Date:01-Nov-2011
Finance Agreement :Schedule 2, Section I.E | Description :INIAF to enter into Sub-Financing Agreements for the financing ofResearch Subprojects Sub& Strategic Alliance Subprojects under terms and conditions set forth in the Operational Manual. |Frequency :Yearly
Finance Agreement :Schedule 2, Section I.F | Description :INIAF to enter into Pilot Subproject Agreement with two Departments ofthe Recipient for the financing of Pilot Subprojects, under terms and conditions set forth in the Operational Manual | Frequency:Yearly
Finance Agreement :Schedule 2, Section G.1 & 2 | Description :INIAF shall comply with the provision of the ESMF and PAMP, andensure that no Category A activities are carried out under the Project, nor does the Project give rise to Displaced Persons or are| Frequency :Yearly
Finance Agreement :Schedule 2, Section G.3 | Description :Consultants designing policy frameworks shall abide by the Associationssafeguard policies. | Frequency :Yearly
Finance Agreement :Schedule 2, Section D.2 | Description :Procurement audits to be carried out by independent auditors | Frequency:Yearly
PDO Indicator
Participation of R&E organizations in SNIAF meetings at national and subnational level
PDO Indicator
INIAF led agricultural innovations adopted by producers
PDO Indicator
Agricultural organizations that see INIAF as an effective leader of the agricultural innovation system
Intermediate Results Indicator
Subprojects supported by the research fund that have received the final payment (number)
Intermediate Results Indicator
Themes prioritized by the Departmental Innovation Councils that are covered by subprojects supported by the Research Fund (percentage)
Intermediate Results Indicator
Innovation policies (including those affecting official norms and standards) developed through the SNIAF and approved by the competent authority (number)
Intermediate Results Indicator
Consolidated Departmental and Regional Innovation Councils contributing to the accomplishment of SNIAF objectives (number)
Intermediate Results Indicator
Departmental technical assistance strategies defined with support of INIAF (number)
Intermediate Results Indicator
Targeted farmers satisfied with INIAF supported technical assistance (percentage)
Intermediate Results Indicator
Volume of seed certified by INIAF
Intermediate Results Indicator
Seed producers satisfied with INIAF certification procedures (percentage)
Intermediate Results Indicator
Targeted clients satisfied with agricultural services (percentage)
Intermediate Results Indicator
Accessions characterized in INIAF's germplasm banks (percentage)
Intermediate Results Indicator
Agricultural innovations developed using participatory methods (number)
Intermediate Results Indicator
Management Systems screened and approved by the INIAF's internal audit (number)
Intermediate Results Indicator
INIAF's Management Information System is fully effective
Intermediate Results Indicator
INIAF national and departmental offices that are performing their basic functions (number)
Intermediate Results Indicator
Formal collaborations with national and international counterparts under implementation (number)
Intermediate Results Indicator
INIAF management positions held by women and/or indigenous people (percentage)
Intermediate Results Indicator
INIAF internal users (staff) satisfied with the administrative support (percentage)
Intermediate Results Indicator
Targeted farmers satisfied with INIAF supported technical assistance - female (percentage)
Intermediate Results Indicator
Targeted farmers satisfied with INIAF supported technical assistance - male (percentage)
Intermediate Results Indicator
Seed producers satisfied with INIAF certification procedures - female (percentage)
Intermediate Results Indicator
Seed producers satisfied with INIAF certification procedures - male (percentage)
Intermediate Results Indicator
Targeted clients satisfied with agricultural services - male (number)
Intermediate Results Indicator
Targeted clients satisfied with agricultural services - female (number)
Intermediate Results Indicator
Targeted clients- male (number)
Intermediate Results Indicator
Targeted clients – female (number)
44000-P101426
World Bank
Lake Titicaca Local Sustainable Development
International Development Association
VICE MINISTRY OF TOURISM
International Development Association
VICE MINISTRY OF TOURISMPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
John Morton
+1-202-473-1000jmorton@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
Copacabana
-16.1500 -69.0830
Viacha
-16.6500 -68.3000
Tito Yupamqui
-16.1770 -68.9550
Tiahuanaco
-16.5520 -68.6800
Taraco
-16.4570 -68.8580
Tacanoca
-16.3500 -68.6170
San Pedro
-16.2370 -68.8510
Puerto Perez
-16.2670 -68.6330
Puerto Acosta
-15.5330 -69.2500
Pucarani
-16.4000 -68.4780
Nina Chiri
-16.5500 -68.3000
Masaya
-16.5330 -68.5500
Lacaya
-16.4330 -68.6670
Kallutaca
-16.5170 -68.3170
Huarina
-16.2000 -68.6330
Guaqui
-16.5830 -68.8670
Desaguadero
-16.5670 -69.0330
Catavi
-16.4670 -68.6000
Carabuco
-15.7500 -69.0670
Batallas
-16.3330 -68.5000
Aygachi
-16.3670 -68.6170
Avicaya
-16.4830 -68.4500
Ancoraimes
-16.1700 -69.0790
Achacachi
-16.0500 -68.6830
Isla del Sol
-16.0170 -69.1670
Isla Pariti
-16.3500 -68.7330
Isla de la Luna
-16.0420 -69.0710
Central Government (Central Agencies)Other Industry, Trade and ServicesSanitationWater SupplyAir quality managementEnvironmental Health and Pollution ManagementRural Non-farm Income GenerationUrban DevelopmentWater PollutionRural DevelopmentCultural HeritageServices and Housing for the PoorSoil Pollution
1319365.63
439788.53
439788.55
439788.55
439788.53
439788.55
439788.55
520833.33
520833.33
520833.34
520833.33
520833.33
520833.34
520833.33
520833.33
520833.34
520833.33
520833.33
520833.34
327481.11
327481.13
327481.13
327481.11
327481.13
327481.13
327481.11
327481.13
327481.13
327481.11
327481.13
327481.13
237434.89
237434.89
237434.91
237434.89
237434.89
237434.91
237434.89
237434.89
237434.91
237434.89
237434.89
237434.91
251075.91
251075.91
251075.92
251075.91
251075.91
251075.92
251075.91
251075.91
251075.92
251075.91
251075.91
251075.92
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
90000.00
162506.76
162506.76
162506.76
0.00
0.00
0.00
51739.31
51739.31
51739.31
34681.17
34681.17
34681.18
61306.18
61306.18
61306.19
66666.66
66666.67
66666.67
211397.41
211397.41
211397.41
53737.04
53737.04
53737.04
38641.94
38641.95
38641.95
23522.73
23522.73
23522.73
30589.87
30589.87
30589.88
25623.80
25623.81
25623.81
0.00
0.00
0.00
30918.65
30918.65
30918.65
33333.33
33333.33
33333.34
33333.33
33333.33
33333.34
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
1000000.00
1000000.00
1000000.00
1278668.45
1278668.45
1278668.45
0.00
0.00
0.00
20000000Total Commitment in Fourth Quarter of 2007
International Development Association90000Total Disbursement in Fourth Quarter of 2008
International Development Association487520Total Disbursement in First Quarter of 2009
International Development Association-6647Total Interest Repayment in First Quarter of 2009
International Development Association155218Total Disbursement in Third Quarter of 2009
International Development Association-3024Total Interest Repayment in Third Quarter of 2009
International Development Association104044Total Disbursement in Fourth Quarter of 2009
International Development Association183919Total Disbursement in First Quarter of 2010
International Development Association-3081Total Interest Repayment in First Quarter of 2010
International Development Association200000Total Disbursement in Second Quarter of 2010
International Development Association73155Total Disbursement in Third Quarter of 2010
International Development Association561037Total Disbursement in Third Quarter of 2010
International Development Association-4109Total Interest Repayment in Third Quarter of 2010
International Development Association161211Total Disbursement in Fourth Quarter of 2010
International Development Association115926Total Disbursement in First Quarter of 2011
International Development Association-7361Total Interest Repayment in First Quarter of 2011
International Development Association70568Total Disbursement in Second Quarter of 2011
International Development Association38250Total Disbursement in Third Quarter of 2011
International Development Association53520Total Disbursement in Third Quarter of 2011
International Development Association-8677Total Interest Repayment in Third Quarter of 2011
International Development Association76871Total Disbursement in Fourth Quarter of 2011
International Development Association-8803Total Interest Repayment in First Quarter of 2012
International Development Association92756Total Disbursement in Second Quarter of 2012
International Development Association195105Total Disbursement in Third Quarter of 2012
International Development Association207280Total Disbursement in Third Quarter of 2012
International Development Association-8984Total Interest Repayment in Third Quarter of 2012
International Development Association229935Total Disbursement in Fourth Quarter of 2012
International Development Association-10903Total Interest Repayment in First Quarter of 2013
International Development Association239628Total Disbursement in Second Quarter of 2013
International Development Association-11864Total Interest Repayment in Third Quarter of 2013
International Development Association-61198Total Disbursement in Fourth Quarter of 2013
International Development Association103799Total Disbursement in Fourth Quarter of 2013
International Development Association131284Total Disbursement in First Quarter of 2014
International Development Association-12744Total Interest Repayment in First Quarter of 2014
International Development Association214320Total Disbursement in Second Quarter of 2014
International Development Association1525763Total Disbursement in Third Quarter of 2014
International Development Association-13240Total Interest Repayment in Third Quarter of 2014
International Development Association1846316Total Disbursement in Fourth Quarter of 2014
International Development Association-9047607Total Commitment Cancellations in First Quarter of 2015
International Development Association-966329Total Disbursement in First Quarter of 2015
International Development Association3249916Total Disbursement in First Quarter of 2015
International Development Association-18771Total Interest Repayment in First Quarter of 2015
International Development Association-27383Total Commitment Cancellations in Second Quarter of 2015
International Development Association-35345Total Interest Repayment in Third Quarter of 2015
International Development Association-33072Total Interest Repayment in First Quarter of 2016
International Development Association-33396Total Interest Repayment in Third Quarter of 2016
International Development Association-31789Total Interest Repayment in First Quarter of 2017
International Development Association-33042Total Interest Repayment in Third Quarter of 2017
International Development Association-30634Total Interest Repayment in First Quarter of 2018
International Development Association-115362Total Loan Repayment in First Quarter of 2018
International Development Association-36774Total Interest Repayment in Third Quarter of 2018
International Development Association-109413Total Loan Repayment in Third Quarter of 2018
International Development Association-31302Total Interest Repayment in First Quarter of 2019
International Development Association-109666Total Loan Repayment in First Quarter of 2019
International Development Association-32156Total Interest Repayment in Third Quarter of 2019
International Development Association-108702Total Loan Repayment in Third Quarter of 2019
International Development Association-30825Total Interest Repayment in First Quarter of 2020
International Development Association-108158Total Loan Repayment in First Quarter of 2020
International Development AssociationProject Information DocumentProject Information DocumentProject Appraisal Document Implementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Agency OM needed
Oversight of FPS
Intermediate Results Indicator
Number of rural towns provided woth improved water and sanitation services
20 completed (Laja and Puerto Perez). An additional 5 are scheduled to be completed under the project.
Intermediate Results Indicator
Number of Tourism Studies - COMPLETED
Intermediate Results Indicator
New piped household water connections that are resulting from the project intervention
Target not able to be determined as the designs were not finalized for the household water supply in urban areas.
Restructuring updates the water and urban core indicators in the context of the Project's revised scope (not yet measured)
Intermediate Results Indicator
Number of other water service providers that the project is supporting
Puerto Perez, Laja, Tiwanacu, Copacabana, Achacachi and Tiquina.
Restructuring updates the water and urban core indicators in the context of the Project's revised scope (not yet measured)
Intermediate Results Indicator
Number of people in rural areas provided with access to Improved Water Sources under the project
Populations of Puerto Perez and Laja were targeted.
Population estimates will be confirmed for Laja and Puerto Perez as part of project closure.
Completed- (both Puerto Perez and Laja)
Intermediate Results Indicator
Number of people in urban areas provided with access to Improved Sanitation under the project
Population target will be confirmed as part of project closure.
Restructuring updates the water and urban core indicators in the context of the Project's revised scope (not yet measured)
Intermediate Results Indicator
Number of people in urban areas provided with access to regular solid waste collection under the project
All projects are under construction.
PDO Indicator
Urban Environmental Sustainability Index for key communities
Intermediate Results Indicator
Number of cities with adequate solid waste services
Bidding expected before december
Intermediate Results Indicator
Number of urban communities provided with adequate wastewater services
3 cities in design
Intermediate Results Indicator
Direct project beneficiaries
Numbers will be updated and confirmed before project closure based on projected projects accounting for design changes.
Not yet measured
Intermediate Results Indicator
Communities with improved tourism infrastructure
Note that many communities have benefited from improved signage but they have not been counted here.
Intermediate Results Indicator
Female beneficiaries
44000-P152281
World Bank
Santa Cruz Road Corridor Connector Project (San Ignacio - San Jose)
International Bank for Reconstruction and Development
ADMINISTRADORA BOLIVIANA DE CARRETERAS
International Bank for Reconstruction and Development
International Development Association
International Development Association
ADMINISTRADORA BOLIVIANA DE CARRETERASPlanned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Felipe Targa Rodriguez
+1-202-473-1000ftarga@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
Departamento de Santa Cruz
-17.5000 -61.5000
San Rafael
-18.4330 -59.6500
San Matias
-16.3670 -58.4000
Puerto Suarez
-18.9500 -57.8000
San Miguel
-19.2670 -60.6330
San JosE de Chiquitos
-17.8500 -60.7500
San Ignacio de Velasco
-16.3670 -60.9500
La Fortuna
-16.4670 -61.2170
San Jose
-17.8280 -63.1690
Rural and Inter-Urban RoadsPublic Administration - TransportationJob CreationRural Infrastructure and service deliveryJobsRoad SafetyRural DevelopmentClimate changeAdaptation
0.00
0.00
0.00
0.00
0.00
0.00
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
6916666.67
6916666.67
6916666.67
6916666.67
6916666.67
6916666.67
6916666.67
6916666.67
6916666.67
6916666.67
6916666.67
6916666.67
5416666.67
5416666.67
5416666.67
5416666.67
5416666.67
5416666.67
5416666.67
5416666.67
5416666.67
5416666.67
5416666.67
5416666.67
2083333.33
2083333.33
2083333.33
2083333.33
2083333.33
2083333.33
2083333.33
2083333.33
2083333.33
2083333.33
2083333.33
2083333.33
583333.33
583333.33
583333.33
583333.33
583333.33
583333.33
583333.33
583333.33
583333.33
583333.33
583333.33
583333.33
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
4128014.77
4128014.77
4128014.78
0.00
0.00
0.00
0.00
0.00
0.00
666666.67
666666.67
666666.66
0.00
0.00
0.00
928000.47
928000.47
928000.46
2721336.28
2721336.28
2721336.29
3089618.98
3089618.98
3089618.97
2388836.20
2388836.20
2388836.20
1491342.46
1491342.46
1491342.47
3036343.09
3036343.09
3036343.10
3962523.84
3962523.84
3962523.85
10857374.65
10857374.65
10857374.64
1239028.54
1239028.54
1239028.54
4386403.83
4386403.83
4386403.83
4640488.82
4640488.82
4640488.81
1739002.22
1739002.22
1739002.21
259108.98
259108.98
259108.98
0.00
0.00
0.00
0.00
0.00
30000000Total Commitment in First Quarter of 2017
International Development Association
200000000Total Commitment in First Quarter of 2017
International Bank for Reconstruction and Development
75000Total Disbursement in Fourth Quarter of 2017
International Development Association
-75000Total Interest Repayment in Fourth Quarter of 2017
International Development Association
500000Total Disbursement in Fourth Quarter of 2017
International Bank for Reconstruction and Development
-500000Total Interest Repayment in Fourth Quarter of 2017
International Bank for Reconstruction and Development
-78316Total Interest Repayment in Second Quarter of 2018
International Development Association
-520565Total Interest Repayment in Second Quarter of 2018
International Bank for Reconstruction and Development
-38945Total Interest Repayment in Fourth Quarter of 2018
International Development Association
-259666Total Interest Repayment in Fourth Quarter of 2018
International Bank for Reconstruction and Development
12384044Total Disbursement in First Quarter of 2019
International Development Association
-145985Total Interest Repayment in Second Quarter of 2019
International Development Association
-258651Total Interest Repayment in Second Quarter of 2019
International Bank for Reconstruction and Development
-260577Total Interest Repayment in Fourth Quarter of 2019
International Development Association
2000000Total Disbursement in Fourth Quarter of 2019
International Bank for Reconstruction and Development
-260047Total Interest Repayment in Fourth Quarter of 2019
International Bank for Reconstruction and Development
-260542Total Interest Repayment in Second Quarter of 2020
International Development Association
-279409Total Interest Repayment in Second Quarter of 2020
International Bank for Reconstruction and Development
Project Information DocumentProject Information DocumentProject Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportLoan AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Finance Agreement :Institutional Arrangements: Schedule 2, Section I, A, 4 | Description :Operate and maintain, throughout Projectimplementation, an accessible grievance redress mechanism, acceptable to the Bank, to address grievances relating to the carryingout of the civil works under Part A of the Project. | Frequency :CONTINUOUS
Finance Agreement :Safeguard: Schedule 2, Section I, D, 1--5 | Description :1. The Borrower shall cause ABC to carry out theProject in accordance with the Environmental Impact Assessment/Environmental Management Plan (EIA/EMP), the Resettlement PolicyFramework (RPF), the Resettlement Action Plan (RAP) and the Indigenous Peoples Plan (IPP). Except as the Bank shall otherwiseagree, the Borrower shall cause ABC to not assign, amend, abrogate or waive the EIA/EMP, the RPF, the RAP and/or the IPP, or any oftheir provisions. 2. Without limitation to the provisions set forth in paragraph 1 above, for the purposes of carrying out anyworks under Part A (except for the construction works of the bypass of San Ignacio de Velasco) of the Project, the Borrower shallcause ABC to carry out the works in accordance with the provisions of the Resettlement Action Plan, including full payment ofcompensation and/or the provision of relocation assistance to all affected persons, prior to any displacement.3. Withoutlimitation to the provisions set forth in paragraph 1 and 2 above, and after the final detailed designs of works regarding thebypass of San Ignacio de Velasco have been completed, the Borrower shall cause ABC to, if Involuntary Resettlement is involved: (i)prepare and disclose, prior to commencement of any works, a site-specific resettlement action plan acceptable to the Bank, inaccordance with the RPF; and (ii) immediately thereafter, carry out said works in accordance with the provisions of saidsite-specific resettlement action plan and in a manner acceptable to the Bank, including full payment of compensation and/or theprovision of relocation to all affected persons, prior to any displacement.4. The Borrower shall cause ABC to ensure that theproceeds of the Loan are not used for the acquisition of land without the prior written concurrence of the Bank.5. The Borrowershall cause ABC to ensure that the terms of reference for any technical assistance provided under the Project, shall besatisfactory to the Bank, and to that end, such terms of reference shall require that the advice conveyed through such technicalassistance be consistent with the requirements of the Bankâs Safeguards Policies and Procedures. | Frequency :CONTINUOUS
Finance Agreement :Technical Audits: Schedule 2, Section II, C | Description :In implementing Part A of the Project, as applicable,as determined by the Bank, the Borrower shall cause ABC to: (a) prepare and furnish to the Bank, an independent technical audit(Technical Audit) in form and substance acceptable to the Bank which shall include, inter alia: (1) a description of all thefindings and results; (2) a list of proposed measures and actions to be taken to resolve the issues identified under (1) above; and(3) a proposed timeline for the implementation of said measures and actions; (b) afford the Bank a reasonable opportunity toexchange views on such Technical Audit; and (c) thereafter implement such recommended measures, taking into account the Bankâsviews on the matter. | Frequency :CONTINUOUS
PDO Indicator
Travel time along the project area
PDO Indicator
Vehicle Operating Cost - Cars
PDO Indicator
Vehicle Operating Cost - Trucks
Intermediate Results Indicator
Roads constructed, non-rural
Intermediate Results Indicator
DBMOT bid documents prepared for San Matias - San Ignacio de Velasco road
Intermediate Results Indicator
Direct project beneficiaries
Intermediate Results Indicator
Female beneficiaries
Intermediate Results Indicator
Road users satisfied with quality of roads disaggregated by gender and user mode
Intermediate Results Indicator
Road Users Satisfaction - Male Passengers
Intermediate Results Indicator
Road Users Satisfaction - Female Passengers
Intermediate Results Indicator
Road Users Satisfaction - Male Drivers
Intermediate Results Indicator
Social Inclusion and Gender
Intermediate Results Indicator
Improvement of access to water in indigenous communities
Intermediate Results Indicator
Training of construction workers on gender, gender based violence prevention and HIV/AIDS/STD
Intermediate Results Indicator
Ayoreo women and men trained on HIV/AIDS/STD and Tuberculosis prevention, working in their communities.
Intermediate Results Indicator
iRAP surveys completed showing any trends/improvements in road safety along the corridor
Intermediate Results Indicator
Traffic accidents on the San Ignacio de Velasco - San Jose de Chiquitos road corridor reported
44000-P101298
World Bank
Second Participatory Rural Investment
International Development Association
FONDO DE INVERSION PRODUCTIVA Y SOCIAL AND OTHERS TBD
International Development Association
FONDO DE INVERSION PRODUCTIVA Y SOCIAL AND OTHERS TBDPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
David Tuchschneider
+1-202-473-1000dtuchschneider@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
Provincia Sajama
-18.2000 -68.5500
Provincia Nuflo de Chavez
-15.9170 -62.5000
Provincia Litoral
-18.5000 -68.2500
Provincia Inquisivi
-17.0000 -67.0830
Camargo
-20.6150 -65.1920
Camataqui (Villa Abecia)
-20.9930 -65.3210
Culpina
-20.7700 -64.6800
El Villar
-19.7150 -64.3230
Huacareta
-20.3670 -64.0040
Icla
-19.4580 -64.7840
Incahuasi
-20.5940 -65.0200
Las Carreras
-21.2840 -65.2720
Machareti
-20.7550 -63.2330
Mojocoya
-18.8220 -64.6270
Monteagudo
-19.9490 -64.0620
Padilla
-19.7220 -64.3530
San Lucas
-20.1600 -64.9310
Sopachuy
-19.4510 -64.5290
Tarabuco
-19.1510 -64.9030
Tarvita (Villa Orias)
-19.7600 -64.5900
Tomina
-19.2030 -64.5230
Villa Alcala
-19.4330 -64.3750
Villa Azurduy
-20.1000 -64.4730
Villa de Huacaya
-20.4850 -63.8280
Villa Serrano
-19.0270 -64.3050
Villa Vaca Guzman (Muyupampa)
-19.9660 -63.7810
Villa Zudanez (Tacopaya)
-19.1660 -64.6890
Yamparaez
-19.2510 -65.0780
Bermejo
-22.7330 -64.3430
Vacas
-17.5630 -65.5810
Vila Vila
-17.9500 -65.6050
Curahuara De Carnagas Sajama
-17.7130 -68.4180
"Colcha ""K""
-20.6990 -67.3180
San Lorenzo
-11.3750 -66.8160
Sena
-11.7760 -67.2790
Santiago de Huari
-19.2800 -66.8570
San Lucas
-20.2000 -64.9840
Santos Mercado
-9.9500 -66.6170
Porvenir
-9.9830 -66.7330
Yunguyo
-18.4000 -67.8830
Yunchara
-21.8240 -65.2280
Yaco
-17.1500 -67.4000
Vitichi
-20.2070 -65.4950
Villazon
-22.0870 -65.5940
Villa Viscarra
-17.9830 -65.6000
Vaca Guzman
-19.8950 -63.7510
Villa Orias
-19.9200 -64.4820
Villamontes
-21.2620 -63.4690
Vallegrande
-18.4890 -64.1060
Vacas
-17.5750 -65.5800
Uyuni
-20.4600 -66.8250
Urubicha
-15.3930 -62.9470
Uriondo
-21.6970 -64.6550
Uncia
-18.4670 -66.5700
Turco
-18.1820 -68.1920
Tupiza
-21.4430 -65.7190
Totoral
-18.4960 -66.8740
Totora
-17.8170 -68.1170
Totora
-17.7270 -65.1930
Torotoro
-18.1350 -65.7620
Tomayapo
-21.2170 -65.0330
Todos Santos
-19.0140 -68.7190
Tipuani
-15.5500 -68.0000
Tinquipaya
-17.3380 -66.2160
Teoponte
-15.4670 -67.8170
Tapacari
-17.5160 -66.6210
Tahua
-19.8900 -67.6950
Tacopaya
-17.8380 -66.5370
Sorata
-15.7670 -68.6330
Sipe Sipe
-17.4500 -66.3830
Sicaya
-17.8000 -66.3340
Sapahaqui
-16.8890 -67.9490
Santivanez
-17.5460 -66.2460
Santa Rosa del Abuna
-10.6070 -67.4520
Santa Rosa
-14.1670 -66.8830
Santa Ana de Yacuma
-13.7500 -65.4330
San Ramon
-14.4830 -63.1500
San Pedro de Quemez
-20.7470 -68.0500
San Pedro de Buena Vista
-18.2690 -65.9820
San Pablo de Lipez
-21.6880 -66.6200
San Lorenzo
-21.4180 -64.7500
San Lorenzo
-11.8970 -66.8780
San Javier
-17.3500 -63.5830
San Javier
-14.5670 -64.8330
San Ignacio de Moxo
-15.0000 -65.6500
San Buena Ventura
-14.4670 -67.5830
San Andres
-15.6000 -64.2670
San Agustin
-21.7500 -66.3500
San Agustin
-21.1560 -67.6800
Salinas de Garci Mendoza
-19.6370 -67.6750
Saipina
-18.0940 -64.5830
Sacaca
-18.0700 -66.3850
Sabaya
-19.0160 -68.3720
Rurrenabaque
-14.4410 -67.5280
Riberalta
-11.0070 -66.0630
Reyes
-14.2950 -67.3360
Ravelo
-18.8070 -65.5120
Quirusillas
-18.3360 -63.9470
Quime
-17.0330 -67.2500
Quime
-16.9830 -67.2170
Quiabaya
-15.6170 -68.7670
Puerto Gonzalo Moreno
-11.0830 -66.1740
Pucarani
-16.4000 -68.4780
Pucara
-18.7160 -64.1840
Postrervalle
-18.4910 -63.8340
Porco
-21.0630 -66.4300
Porco
-19.7990 -65.9890
Pocoata
-18.7000 -66.1630
Pampa Grande
-18.0900 -64.1120
Padcaya
-21.8870 -64.7130
Omereque
-18.1060 -64.9080
Ocuri
-18.8420 -65.7960
Moro Moro
-18.3670 -64.3230
Morochata
-17.8670 -65.8170
Morochata
-17.2350 -66.5320
Monteagudo
-19.8000 -63.9550
Mojinete
-21.8140 -66.3880
Mapiri
-15.2500 -68.1670
Malla
-17.0830 -67.4830
Mairana
-18.1190 -63.9600
Magdalena
-13.2330 -64.2000
Machareti
-20.8150 -63.3630
Luribay
-17.0500 -67.6670
Loreto
-15.1930 -64.7590
Llica
-19.8510 -68.2480
Llallagua
-18.4240 -66.5840
La Rivera
-19.0050 -68.6400
Lagunillas
-19.6510 -63.6750
Ixiamas
-13.7500 -68.1500
Inquisivi
-16.9200 -67.1730
Ingavi
-11.7000 -68.9710
Incahuasi
-20.7790 -64.8670
Ichoca
-17.2170 -69.3330
Huayllamarca
-17.8340 -67.9410
Huacaya
-20.7450 -63.6650
Huacaraje
-13.5500 -63.7500
Gutierrez
-19.4330 -62.4830
Guayaramerin
-10.8370 -65.3610
General Saavedra
-17.2260 -63.2120
Filadelfia
-11.3460 -68.7580
Exaltacion
-13.2790 -65.2400
Esmeralda
-18.8460 -68.2840
Escara
-18.8600 -68.1700
Entre Rios
-21.5270 -64.1730
El Trigal
-18.3060 -64.1490
El Puente
-21.2370 -65.2060
Cuevo
-20.4530 -63.5180
Santiago de Cotagaita
-20.8170 -65.6610
Corque
-18.3500 -67.6820
Concepcion
-16.4330 -60.9000
Combaya
-15.7830 -68.7670
Colquiri
-17.3890 -67.1270
Colquechaca
-18.7000 -66.0040
Colcha
-19.8660 -67.1370
Coipasa
-19.2770 -68.2780
Cliza
-17.5880 -65.9330
Chuma
-15.4830 -68.9000
Choquecota
-18.2500 -67.9500
Chipaya
-19.0420 -68.0900
Chayanta
-18.4490 -66.4610
Charagua
-19.7920 -63.1990
Challapata
-18.9020 -66.7700
Challapata
-15.8830 -68.1170
Caripuyo
-18.2330 -66.4740
Carapari
-21.8280 -63.7430
Carangas
-18.9330 -68.6170
Caranavi
-15.8170 -67.5500
Capinota
-17.7110 -66.2610
Camiri
-20.0380 -63.5180
Cajuata
-16.8170 -67.2500
Caiza
-20.0080 -65.6540
Cairoma
-16.9000 -67.5500
Cabezas
-18.7890 -63.3010
Boyuibe
-20.4320 -63.2810
Bolpebra
-10.9490 -69.5640
Bolivar
-17.9690 -66.5380
Bella Flor
-11.1420 -67.8210
Belen de Anamarca
-18.8190 -67.6410
Baures
-13.5830 -63.5830
Batallas
-16.3330 -68.5000
Ayata
-15.3410 -68.7530
Ayacucho
-17.8500 -63.3330
Aucapata
-15.5000 -68.7670
Atocha
-20.9350 -66.2210
Arque
-17.8220 -66.4040
Arbieto
-17.5670 -66.0170
Arampampa
-17.9590 -66.0940
Apolo
-14.7190 -68.4120
Ancoraimes
-16.1700 -69.0790
Alalay
-17.6830 -65.6830
Acacio
-18.0240 -66.0580
La Santisima Trinidad
-14.8330 -64.9000
Cobija
-11.0270 -68.7690
Yacuiba
-22.0160 -63.6780
Independencia
-17.0840 -66.8180
Huachacalla
-18.7930 -68.2620
Andamarca
-18.7790 -67.5080
Guanay
-15.4980 -67.8830
Las Carreras
-21.2500 -65.2830
Culpina
-20.8240 -64.9450
Camargo
-20.6410 -65.2090
Azurduy
-20.1060 -64.4140
Ascencion De Guarayos
-15.9330 -63.1550
Central Government (Central Agencies)Sub-National GovernmentOther Agriculture, Fishing and ForestryIrrigation and DrainageRural and Inter-Urban RoadsAir quality managementRural Infrastructure and service deliveryEnvironmental Health and Pollution ManagementPublic AdministrationAdministrative and Civil Service ReformSocial InclusionMunicipal Institution BuildingSoil PollutionWater PollutionParticipation and Civic EngagementIndigenous People and Ethnic MinoritiesRural Development
680000.00
680000.00
680000.00
680000.00
680000.00
680000.00
680000.00
680000.00
680000.00
449166.67
449166.67
449166.66
449166.67
449166.67
449166.66
449166.67
449166.67
449166.66
449166.67
449166.67
449166.66
395000.00
395000.00
395000.00
395000.00
395000.00
395000.00
395000.00
395000.00
395000.00
395000.00
395000.00
395000.00
312500.00
312500.00
312500.00
312500.00
312500.00
312500.00
312500.00
312500.00
312500.00
312500.00
312500.00
312500.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
123121.09
123121.09
123121.09
461000.00
461000.00
461000.00
0.00
0.00
0.00
87013.00
87013.01
87013.01
152168.58
152168.59
152168.59
379382.59
379382.60
379382.60
686642.66
686642.66
686642.67
398269.77
398269.77
398269.78
569132.16
569132.17
569132.17
569132.16
569132.17
569132.17
735798.83
735798.83
735798.84
735798.83
735798.83
735798.84
442301.74
442301.74
442301.74
442301.74
442301.74
442301.74
442301.73
442301.74
442301.74
442301.73
442301.74
442301.74
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
20000000Total Commitment in Fourth Quarter of 2007
International Development Association369363Total Disbursement in First Quarter of 2009
International Development Association1383000Total Disbursement in Second Quarter of 2009
International Development Association-9466Total Interest Repayment in Third Quarter of 2009
International Development Association261039Total Disbursement in Fourth Quarter of 2009
International Development Association456506Total Disbursement in First Quarter of 2010
International Development Association-7779Total Interest Repayment in First Quarter of 2010
International Development Association474994Total Disbursement in Second Quarter of 2010
International Development Association663154Total Disbursement in Second Quarter of 2010
International Development Association373065Total Disbursement in Third Quarter of 2010
International Development Association783070Total Disbursement in Third Quarter of 2010
International Development Association903793Total Disbursement in Third Quarter of 2010
International Development Association-10456Total Interest Repayment in Third Quarter of 2010
International Development Association535078Total Disbursement in Fourth Quarter of 2010
International Development Association659731Total Disbursement in Fourth Quarter of 2010
International Development Association-22422Total Interest Repayment in First Quarter of 2011
International Development Association596020Total Disbursement in Second Quarter of 2011
International Development Association1144418Total Disbursement in Second Quarter of 2011
International Development Association300000Total Disbursement in Third Quarter of 2011
International Development Association1004694Total Disbursement in Third Quarter of 2011
International Development Association1129507Total Disbursement in Third Quarter of 2011
International Development Association-29876Total Interest Repayment in Third Quarter of 2011
International Development Association542859Total Disbursement in Fourth Quarter of 2011
International Development Association363832Total Disbursement in First Quarter of 2012
International Development Association540124Total Disbursement in First Quarter of 2012
International Development Association-41328Total Interest Repayment in First Quarter of 2012
International Development Association817080Total Disbursement in Second Quarter of 2012
International Development Association593904Total Disbursement in Third Quarter of 2012
International Development Association-47808Total Interest Repayment in Third Quarter of 2012
International Development Association450000Total Disbursement in Fourth Quarter of 2012
International Development Association1536628Total Disbursement in Fourth Quarter of 2012
International Development Association359361Total Disbursement in First Quarter of 2013
International Development Association669952Total Disbursement in First Quarter of 2013
International Development Association-54027Total Interest Repayment in First Quarter of 2013
International Development Association59923Total Disbursement in Second Quarter of 2013
International Development Association7000Total Disbursement in Third Quarter of 2013
International Development Association665952Total Disbursement in Third Quarter of 2013
International Development Association-62960Total Interest Repayment in Third Quarter of 2013
International Development Association578770Total Disbursement in Fourth Quarter of 2013
International Development Association693913Total Disbursement in Fourth Quarter of 2013
International Development Association-67206Total Interest Repayment in First Quarter of 2014
International Development Association-928751Total Commitment Cancellations in Second Quarter of 2014
International Development Association-115654Total Disbursement in Second Quarter of 2014
International Development Association-71107Total Interest Repayment in Third Quarter of 2014
International Development Association-64753Total Interest Repayment in First Quarter of 2015
International Development Association-64210Total Interest Repayment in Third Quarter of 2015
International Development Association-63761Total Interest Repayment in First Quarter of 2016
International Development Association-64385Total Interest Repayment in Third Quarter of 2016
International Development Association-61289Total Interest Repayment in First Quarter of 2017
International Development Association-63704Total Interest Repayment in Third Quarter of 2017
International Development Association-59062Total Interest Repayment in First Quarter of 2018
International Development Association-222413Total Loan Repayment in First Quarter of 2018
International Development Association-70899Total Interest Repayment in Third Quarter of 2018
International Development Association-210944Total Loan Repayment in Third Quarter of 2018
International Development Association-60350Total Interest Repayment in First Quarter of 2019
International Development Association-211431Total Loan Repayment in First Quarter of 2019
International Development Association-61995Total Interest Repayment in Third Quarter of 2019
International Development Association-209573Total Loan Repayment in Third Quarter of 2019
International Development Association-59429Total Interest Repayment in First Quarter of 2020
International Development Association-208524Total Loan Repayment in First Quarter of 2020
International Development AssociationProject Information DocumentProject Information DocumentProject Appraisal Document Implementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
FPS shall have completed the modifications of the first phase of SAP, agreed with the Association pursuant to the FPS Action Plan.
FPS shall have completed all SAP modifications agreed with the Association, pursuant to the FPS Action Plan.
FPS shall have established its public web page with the register of companies, supervisors, and contracts awarded by FPS and theMunicipalities since January 31, 2008.
The Recipient shall cause FPS to carry out the FPS Action Plan.
The Recipient and the Association shall assess semiannually, FPS institutional performance to confirm compliance with the FPSAction Plan.
The Recipient shall maintain throughout the implementation of the Project: the control and monitoring unit under FPS€™s executiveoffice;the environmental unit; and the procurement monitoring unit
Intermediate Results Indicator
54 sectoral, multi-municipal and 18 territorial development programs &/or plans mutually agreed upon by the Prefecture, Municipal Governments, their associations, civil society actors, & other actors
Substantially achieved. Diverse sources have financed the plan implementation
Intermediate Results Indicator
Reduction of at least 30% in average travel time on roads assisted under the project.
Achieved, but measurement uncertainties. Based on the final survey.
PDO Indicator
100% of productive investments executed by the project have been cofinanced by prefectures and/or municipalities, under the framework of their competencies.
Achieved. 71 subprojects co-financed by the central government and both departmental and municipal governments; 173 subprojectsco-financed by the central Government and Municipalities
PDO Indicator
30% increase in the benefits of public investments co-financed by the project.
An estimate for a sample of 10 irrigation subprojects is 477%. Sample size was small and incomplete. Subproject baselines had to bereconstructed and comparability with Project baseline not achieved. No control group.
PDO Indicator
70% of the public investments cofinanced and coordinated by the project are properly maintained and operated
Substantially achieved. Based on a sample of 81 subprojects (final survey). The Economic Evaluation revealed similar results for asample of 38 subprojects
PDO Indicator
18 inter-municipal plans with a territorial focus have been consolidated as a mechanism for local development.
Substantially achieved. Out of the 24 plans formulated for both territorial development and infrastructure improvement, 17 planshave been used as instruments to lead joint efforts among diverse actors such as Municipalities and Departmental Governments
PDO Indicator
Validated models for ordering subnational public investment have been tested for replication in other sectors and territories.
Achieved. 2 co-financing models were used and validated for the collaboration between sub-national governments (Cochabamba andOruro Departments). Relevance in new policy context to be seen,
Intermediate Results Indicator
24,000 members of 180 subnational entities and civil society organizations have been trained and participate in the formulation, management, and evaluation of development plans, programs, and projects
Exceeded. Based on the PDCR final report
Intermediate Results Indicator
81 subnational public entities have generated, agreed upon, and applied local and/or sectoral regulatory systems that regulate the implementation of instruments developed and applied by the project (r
Exceeded. Based on a PDCR final report
Intermediate Results Indicator
15% increase in the executed budget of municipal governments and prefecture for productive investments in the project area.
Not achieved. Reduction of the budget disbursed for productive investments from 29% to 23.2%, among the Municipalities within theproject area. Indicator beyond Project control.
Intermediate Results Indicator
Increase of 30% in the value of production of families participating in micro-irrigation, promotion of economic activities, productive promotion subprojects.
Exceeded. But sample incomplete. Only includes a sample of 12 micro irrigation subprojects. The increase was (375%)
Intermediate Results Indicator
20% increase in the sales value of products and services of project participants who benefit from economic promotion activities.
Not measured.
Intermediate Results Indicator
The PDCR#s technical and administrative staff is stable in terms of periodic performance assessments.
The project executed regular performance evaluations and based stffing decisions on them.
Intermediate Results Indicator
Timely and valid information is available for timely decision making and the adaptive management of the project.
Intermediate Results Indicator
Technical and annual budget execution of the projectin accordance with the implementation plan, the operational manual, the resultsframework, and the donation and credit agreements
44000-P087925
World Bank
Bolivia Land for Agricultural Development Project.
International Development Association
MINISTRY OF SUSTAINABLE DEVELOPMENT
International Development Association
MINISTRY OF SUSTAINABLE DEVELOPMENTPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Enrique Pantoja
+1-202-473-1000epantoja@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
Departamento de Santa Cruz
-17.5000 -61.5000
San Ignacio de Velasco
-16.3670 -60.9500
Pailon
-17.6500 -62.7500
Mineros
-17.1190 -63.2310
Concepcion
-16.4330 -60.9000
Charagua
-19.7920 -63.1990
Sub-National GovernmentOther Agriculture, Fishing and ForestrySocial Safety NetsRural MarketsSocial InclusionJobsSocial ProtectionRural DevelopmentLand Administration and ManagementIndigenous People and Ethnic Minorities
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
208333.33
208333.33
208333.34
208333.33
208333.33
208333.34
208333.33
208333.33
208333.34
208333.33
208333.33
208333.34
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
291666.67
291666.67
291666.66
291666.67
291666.67
291666.66
291666.67
291666.67
291666.66
291666.67
291666.67
291666.66
291666.67
291666.67
291666.66
291666.67
291666.67
291666.66
291666.67
291666.67
291666.66
291666.67
291666.67
291666.66
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
240871.68
240871.68
240871.68
0.00
0.00
0.00
807491.37
807491.37
807491.37
0.00
0.00
0.00
171524.91
171524.92
171524.92
0.00
0.00
0.00
97631.14
97631.14
97631.14
0.00
0.00
0.00
308115.98
308115.98
308115.98
186300.70
186300.72
186300.72
151995.83
151995.83
151995.83
323523.81
323523.81
323523.83
189106.38
189106.38
189106.39
96544.71
96544.71
96544.72
553911.77
553911.78
553911.78
321069.28
321069.28
321069.29
119839.83
119839.83
119839.84
280489.00
280489.00
280489.01
426481.32
426481.32
426481.32
0.00
0.00
0.00
290571.65
290571.65
290571.66
258237.66
258237.67
258237.67
176292.92
176292.92
176292.93
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
15000000Total Commitment in Fourth Quarter of 2007
International Development Association700000Total Disbursement in Second Quarter of 2009
International Development Association-6859Total Interest Repayment in Third Quarter of 2009
International Development Association260041Total Disbursement in Fourth Quarter of 2009
International Development Association636110Total Disbursement in Fourth Quarter of 2009
International Development Association1490526Total Disbursement in Fourth Quarter of 2009
International Development Association-15645Total Interest Repayment in First Quarter of 2010
International Development Association512019Total Disbursement in Second Quarter of 2010
International Development Association-12501Total Interest Repayment in Third Quarter of 2010
International Development Association300000Total Disbursement in Fourth Quarter of 2010
International Development Association-14953Total Interest Repayment in First Quarter of 2011
International Development Association298164Total Disbursement in Second Quarter of 2011
International Development Association663668Total Disbursement in Second Quarter of 2011
International Development Association587533Total Disbursement in Third Quarter of 2011
International Development Association-17250Total Interest Repayment in Third Quarter of 2011
International Development Association464754Total Disbursement in Fourth Quarter of 2011
International Development Association396806Total Disbursement in First Quarter of 2012
International Development Association578654Total Disbursement in First Quarter of 2012
International Development Association-21599Total Interest Repayment in First Quarter of 2012
International Development Association219772Total Disbursement in Second Quarter of 2012
International Development Association347547Total Disbursement in Second Quarter of 2012
International Development Association289634Total Disbursement in Third Quarter of 2012
International Development Association-26306Total Interest Repayment in Third Quarter of 2012
International Development Association195604Total Disbursement in Fourth Quarter of 2012
International Development Association592123Total Disbursement in Fourth Quarter of 2012
International Development Association874009Total Disbursement in Fourth Quarter of 2012
International Development Association442191Total Disbursement in First Quarter of 2013
International Development Association521017Total Disbursement in First Quarter of 2013
International Development Association-32570Total Interest Repayment in First Quarter of 2013
International Development Association359520Total Disbursement in Second Quarter of 2013
International Development Association841467Total Disbursement in Third Quarter of 2013
International Development Association-39255Total Interest Repayment in Third Quarter of 2013
International Development Association496574Total Disbursement in Fourth Quarter of 2013
International Development Association782870Total Disbursement in Fourth Quarter of 2013
International Development Association-43722Total Interest Repayment in First Quarter of 2014
International Development Association871715Total Disbursement in Second Quarter of 2014
International Development Association774713Total Disbursement in Third Quarter of 2014
International Development Association-51188Total Interest Repayment in Third Quarter of 2014
International Development Association148536Total Disbursement in Fourth Quarter of 2014
International Development Association-50306Total Interest Repayment in First Quarter of 2015
International Development Association-50303Total Interest Repayment in Third Quarter of 2015
International Development Association-49952Total Interest Repayment in First Quarter of 2016
International Development Association-128571Total Disbursement in Second Quarter of 2016
International Development Association-50103Total Interest Repayment in Third Quarter of 2016
International Development Association-686103Total Commitment Cancellations in Fourth Quarter of 2016
International Development Association-218007Total Disbursement in Fourth Quarter of 2016
International Development Association-46960Total Interest Repayment in First Quarter of 2017
International Development Association-48618Total Interest Repayment in Third Quarter of 2017
International Development Association-45074Total Interest Repayment in First Quarter of 2018
International Development Association-169736Total Loan Repayment in First Quarter of 2018
International Development Association-54107Total Interest Repayment in Third Quarter of 2018
International Development Association-160984Total Loan Repayment in Third Quarter of 2018
International Development Association-46056Total Interest Repayment in First Quarter of 2019
International Development Association-161355Total Loan Repayment in First Quarter of 2019
International Development Association-47312Total Interest Repayment in Third Quarter of 2019
International Development Association-159938Total Loan Repayment in Third Quarter of 2019
International Development Association-45354Total Interest Repayment in First Quarter of 2020
International Development Association-159137Total Loan Repayment in First Quarter of 2020
International Development AssociationProject Information DocumentProject Information DocumentProject Appraisal DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportCredit AgreementAgreementAgreementContract AwardsProject URLProcurement Notices
An Operational Manual satisfactory to IDA, adopted by effectiveness date
Enter into participating agreements with participating FIs
Enter in partnership agreement with each municipality
Carry out an assessment of the impact of the project on BAs (mid-term and closing)
Prepare on March 30 if each year a report integrating information from Project M&E
Ensure that lands acquired under the project are not siubject to reversion
Intermediate Results Indicator
At least 2,200 beneficiary families select and acquire their farms
Original target surpassed. These families are organized under Productive Associations.
PDO Indicator
Direct project beneficiaries
Estimate based on original assumption of 10 HHs per Productive Association, and an average of 5 people per HH.
Final figure to be confirmed at the end of the Project evaluation.
PDO Indicator
At least 50% increase in beneficiary familiy income
Final figure to be confirmed at the end of Project evaluation.
Intermediate Results Indicator
At least 115,000 hectares of land are accessed by Productive Associations (PAs)
Target surpassed.
PDO Indicator
Local level decision-making and monitoring entities established and functioning in 3 selected municipalities
The number of Local Development Committees (CODALs) was increased to reflect the addition of two municipalities as part of theProject area.
Intermediate Results Indicator
At least 70% of the productive sub-projects comply satisfactorily with agreed implementation plans
Final figure to be confirmed at the end of Project evaluation. Preliminary findings show that target has been surpassed.
PDO Indicator
At least 15% increase in value of productive assets of beneficiary families
Final figures to be confirmed at the end of the Project Evaluation.
Intermediate Results Indicator
At least 70% of land accessed by PAs are put under productive use
Indicator is based on average area put under productive use by year of project implementation.
PDO Indicator
At least 10% of Productive Associations (PAs) have women in their Boards
Target surpassed.
Intermediate Results Indicator
At least 80% of PAs are satisfied with the technical assistance provided by the Project
Intermediate Results Indicator
At least 20% of participants in training sessions are women
Target surpassed.
Intermediate Results Indicator
Project M&E system established and updated periodically, and Mid-term and final evaluation completed
M&E system established. MTR evaluation completed. Project evaluation is well underway.
Intermediate Results Indicator
At least 190 Productive Associations (PAs) established under the Project
PDO Indicator
Female beneficiaries
44000-P101336
World Bank
Strengthening Statistical Capacity and Informational Base for Evidence-Based Planning
International Development Association
MINISTRY OF PLANNING AND DEVELOPMENT
International Development Association
MINISTRY OF PLANNING AND DEVELOPMENTPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Alejandro Medina Giopp
+1-202-473-1000amedinagiopp@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
Departamento de Tarija
-21.5000 -64.0000
Departamento de Santa Cruz
-17.5000 -61.5000
Departamento de Potosi
-20.6670 -67.0000
Departamento de Pando
-11.3330 -67.6670
Departamento de Oruro
-18.6670 -67.5000
Departamento de La Paz
-15.5000 -68.0000
Departamento de Chuquisaca
-20.0000 -64.3330
El Beni
-14.0000 -65.5000
Cochabamba
-17.3900 -66.1570
Public Administration - Agriculture, Fishing & ForestrySub-National GovernmentCentral Government (Central Agencies)Enterprise DevelopmentTransparency, Accountability and Good GovernancePublic AdministrationMSME DevelopmentData production, accessibility and useData Development and Capacity Building
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
200000.00
200000.00
0.00
0.00
0.00
166666.66
166666.67
166666.67
1333333.33
1333333.33
1333333.34
666666.66
666666.67
666666.67
4333333.33
4333333.33
4333333.34
1333333.33
1333333.33
1333333.34
433333.33
433333.33
433333.34
3333333.33
3333333.33
3333333.34
2666666.66
2666666.67
2666666.67
666666.66
666666.67
666666.67
333333.33
333333.33
333333.34
300000.00
300000.00
300000.00
816666.66
816666.67
816666.67
150000.00
150000.00
150000.00
333333.33
333333.33
333333.34
250000.00
250000.00
250000.00
700000.00
700000.00
700000.00
833333.33
833333.33
833333.34
516666.66
516666.67
516666.67
1116666.66
1116666.67
1116666.67
1066666.66
1066666.67
1066666.67
100000.00
100000.00
100000.00
116666.66
116666.67
116666.67
216666.66
216666.67
216666.67
116666.66
116666.67
116666.67
13333.33
13333.33
13333.34
33333.33
33333.33
33333.34
0.00
0.00
0.00
500000.00
500000.00
500000.00
200000.00
200000.00
200000.00
500000.00
500000.00
500000.00
366666.66
366666.67
366666.67
333333.33
333333.33
333333.34
453333.33
453333.33
453333.34
0.00
0.00
0.00
50000000Total Commitment in First Quarter of 2011
International Development Association357988Total Disbursement in Third Quarter of 2011
International Development Association-954Total Interest Repayment in Fourth Quarter of 2011
International Development Association500000Total Disbursement in First Quarter of 2012
International Development Association3500000Total Disbursement in Second Quarter of 2012
International Development Association-2357Total Interest Repayment in Second Quarter of 2012
International Development Association2088000Total Disbursement in Third Quarter of 2012
International Development Association2556880Total Disbursement in Fourth Quarter of 2012
International Development Association4756422Total Disbursement in Fourth Quarter of 2012
International Development Association5695338Total Disbursement in Fourth Quarter of 2012
International Development Association-23120Total Interest Repayment in Fourth Quarter of 2012
International Development Association2000000Total Disbursement in First Quarter of 2013
International Development Association2000000Total Disbursement in First Quarter of 2013
International Development Association1401388Total Disbursement in Second Quarter of 2013
International Development Association-86795Total Interest Repayment in Second Quarter of 2013
International Development Association778282Total Disbursement in Third Quarter of 2013
International Development Association9123630Total Disbursement in Third Quarter of 2013
International Development Association3056942Total Disbursement in Fourth Quarter of 2013
International Development Association3640098Total Disbursement in Fourth Quarter of 2013
International Development Association-115603Total Interest Repayment in Fourth Quarter of 2013
International Development Association162797Total Disbursement in First Quarter of 2014
International Development Association1188001Total Disbursement in First Quarter of 2014
International Development Association364431Total Disbursement in Second Quarter of 2014
International Development Association653721Total Disbursement in Second Quarter of 2014
International Development Association-163418Total Interest Repayment in Second Quarter of 2014
International Development Association9700000Total Commitment in Second Quarter of 2014
International Development Association13600000Total Commitment in Second Quarter of 2014
International Development Association410877Total Disbursement in Third Quarter of 2014
International Development Association530000Total Disbursement in Third Quarter of 2014
International Development Association544245Total Disbursement in Fourth Quarter of 2014
International Development Association655977Total Disbursement in Fourth Quarter of 2014
International Development Association1082000Total Disbursement in Fourth Quarter of 2014
International Development Association-160448Total Interest Repayment in Fourth Quarter of 2014
International Development Association493604Total Disbursement in First Quarter of 2015
International Development Association-159669Total Interest Repayment in Second Quarter of 2015
International Development Association1044000Total Disbursement in Second Quarter of 2015
International Development Association138008Total Disbursement in Third Quarter of 2015
International Development Association533664Total Disbursement in Third Quarter of 2015
International Development Association180000Total Disbursement in Fourth Quarter of 2015
International Development Association-167211Total Interest Repayment in Fourth Quarter of 2015
International Development Association600000Total Disbursement in Fourth Quarter of 2015
International Development Association1537318Total Disbursement in Fourth Quarter of 2015
International Development Association-7179Total Interest Repayment in Fourth Quarter of 2015
International Development Association400000Total Disbursement in First Quarter of 2016
International Development Association750000Total Disbursement in First Quarter of 2016
International Development Association1202437Total Disbursement in First Quarter of 2016
International Development Association-165762Total Interest Repayment in Second Quarter of 2016
International Development Association200000Total Disbursement in Second Quarter of 2016
International Development Association300000Total Disbursement in Second Quarter of 2016
International Development Association400000Total Disbursement in Second Quarter of 2016
International Development Association-3325Total Interest Repayment in Second Quarter of 2016
International Development Association193342Total Disbursement in Second Quarter of 2016
International Development Association470391Total Disbursement in Second Quarter of 2016
International Development Association-33100Total Interest Repayment in Second Quarter of 2016
International Development Association166322Total Disbursement in Third Quarter of 2016
International Development Association795000Total Disbursement in Third Quarter of 2016
International Development Association680000Total Disbursement in Third Quarter of 2016
International Development Association800000Total Disbursement in Third Quarter of 2016
International Development Association1000000Total Disbursement in Third Quarter of 2016
International Development Association87464Total Disbursement in Fourth Quarter of 2016
International Development Association-158478Total Interest Repayment in Fourth Quarter of 2016
International Development Association1620000Total Disbursement in Fourth Quarter of 2016
International Development Association-21670Total Interest Repayment in Fourth Quarter of 2016
International Development Association1457726Total Disbursement in Fourth Quarter of 2016
International Development Association-64796Total Interest Repayment in Fourth Quarter of 2016
International Development Association267000Total Disbursement in First Quarter of 2017
International Development Association12297Total Disbursement in Second Quarter of 2017
International Development Association-161151Total Interest Repayment in Second Quarter of 2017
International Development Association-45498Total Interest Repayment in Second Quarter of 2017
International Development Association350000Total Disbursement in Second Quarter of 2017
International Development Association-89938Total Interest Repayment in Second Quarter of 2017
International Development Association-491Total Disbursement in Third Quarter of 2017
International Development Association650000Total Disbursement in Third Quarter of 2017
International Development Association340420Total Disbursement in Fourth Quarter of 2017
International Development Association-170649Total Interest Repayment in Fourth Quarter of 2017
International Development Association-48921Total Interest Repayment in Fourth Quarter of 2017
International Development Association-106658Total Interest Repayment in Fourth Quarter of 2017
International Development Association-168723Total Interest Repayment in Second Quarter of 2018
International Development Association-50508Total Interest Repayment in Second Quarter of 2018
International Development Association105000Total Disbursement in Second Quarter of 2018
International Development Association-113654Total Interest Repayment in Second Quarter of 2018
International Development Association-44887Total Commitment Cancellations in Third Quarter of 2018
International Development Association-17594Total Disbursement in Third Quarter of 2018
International Development Association-164797Total Interest Repayment in Fourth Quarter of 2018
International Development Association650000Total Disbursement in Fourth Quarter of 2018
International Development Association690000Total Disbursement in Fourth Quarter of 2018
International Development Association-47789Total Interest Repayment in Fourth Quarter of 2018
International Development Association62000Total Disbursement in Fourth Quarter of 2018
International Development Association100000Total Disbursement in Fourth Quarter of 2018
International Development Association123118Total Disbursement in Fourth Quarter of 2018
International Development Association-108299Total Interest Repayment in Fourth Quarter of 2018
International Development Association1400000Total Disbursement in First Quarter of 2019
International Development Association400000Total Disbursement in First Quarter of 2019
International Development Association-165316Total Interest Repayment in Second Quarter of 2019
International Development Association758000Total Disbursement in Second Quarter of 2019
International Development Association-60100Total Interest Repayment in Second Quarter of 2019
International Development Association110000Total Disbursement in Second Quarter of 2019
International Development Association-112477Total Interest Repayment in Second Quarter of 2019
International Development Association82852Total Disbursement in Third Quarter of 2019
International Development Association100137Total Disbursement in Third Quarter of 2019
International Development Association-163810Total Interest Repayment in Fourth Quarter of 2019
International Development Association-667353Total Commitment Cancellations in Fourth Quarter of 2019
International Development Association-85363Total Interest Repayment in Fourth Quarter of 2019
International Development Association-142107Total Loan Repayment in Fourth Quarter of 2019
International Development Association-417793Total Commitment Cancellations in Fourth Quarter of 2019
International Development Association-116583Total Interest Repayment in Fourth Quarter of 2019
International Development Association-199030Total Loan Repayment in Fourth Quarter of 2019
International Development Association-83630Total Interest Repayment in Second Quarter of 2020
International Development Association-130516Total Loan Repayment in Second Quarter of 2020
International Development Association-114112Total Interest Repayment in Second Quarter of 2020
International Development Association-191444Total Loan Repayment in Second Quarter of 2020
International Development AssociationProject Information DocumentProject Information DocumentProject Information DocumentProject Information DocumentProject Information DocumentProject Appraisal DocumentProject Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementAgreementFinancing AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Finance Agreement: Section I.A of Schedule 2 to the Financing Agreement Description :The Recipient shall cause INE to: (a) operateand maintain throughout Project implementation within INE, its technical units responsible for statistical operations and anadministrative unit; and (b) assign responsibility internally for the management, implementation, monitoring and reporting of theProject | Frequency: Continuous
Finance Agreement: Section I. D of Schedule 2 to the Financing Agreement | Description: The Recipient shall cause INE to: (a)submit annual Project work plans and budget to the Association for their respective review and approval; and (b) thereafter, carryout such annual Project work plan referred to in (a) herein in accordance with its terms and in a manner acceptable to theAssociation. | Frequency: Yearly
Finance Agreement: Section I. F of Schedule 2 to the Financing Agreement | Description: The Recipient shall cause INE to, prior tothe carrying out of any activity under Parts 2.2, 2.3, 2.4, 3.3 and 3.4 of the Project: (a) prepare and furnish to the Associationan engagement strategy, acceptable to the Association; and (b) thereafter, carry out said activities in accordance with saidstrategy, and in a manner acceptable to the Association. Frequency: Continuous
Finance Agreement: Section III. D. 2 of Schedule 2 to the Financing Agreement | Description: The Recipient shall cause INE to carryout procurement audits, under the terms and conditions established in the Financing Agreement. | Frequency: Yearly
Finance Agreement: Section I.A of Schedule 2 to the Financing Agreement | Description: The Recipient shall cause INE to: (a)operate and maintain throughout Project implementation within INE, its technical units responsible for statistical operations andan administrative unit; and (b) assign responsibility internally for the management, implementation, monitoring and reporting ofthe Project | Frequency: Continuous
Finance Agreement: Section I. D of Schedule 2 to the Financing Agreement | Description: The Recipient shall cause INE to: (a)submit annual Project work plans and budget to the Association for their respective review and approval; and (b) thereafter, carryout such annual Project work plan referred to in (a) herein in accordance with its terms and in a manner acceptable to theAssociation. | Frequency: Yearly
Finance Agreement: Section I. F of Schedule 2 to the Financing Agreement | Description: The Recipient shall cause INE to, prior tothe carrying out of any activity under Parts 2.2, 2.3, 2.4, 3.3 and 3.4 of the Project: (a) prepare and furnish to the Associationan engagement strategy, acceptable to the Association; and (b) thereafter, carry out said activities in accordance with saidstrategy, and in a manner acceptable to the Association. | Frequency: Continuous
Finance Agreement: Section III. D. 2 of Schedule 2 to the Financing Agreement | Description: The Recipient shall cause INE to carryout procurement audits, under the terms and conditions established in the Financing Agreement. | Frequency: Yearly
PDO Indicator
GOB has updated quality statistical information that has been disseminated widely within the Government and among the public
Intermediate Results Indicator
List of Agricultural Production Units at the municipal level
Intermediate Results Indicator
90% of dwellings accounted for in the National Population and Housing Census
Intermediate Results Indicator
90% of departments have representative data on living standards
Intermediate Results Indicator
100% of physically demarcated and non-demarcated areas have updated cartographic information used in the preparation of the National Agricultural Census and the National Housing and Population Census
Intermediate Results Indicator
100% of departments have updated economic information (Agriculture, Industry, Trade & Services)
Intermediate Results Indicator
100% of departments have updated information on agricultural production and its destination.
Intermediate Results Indicator
95% of localities with population over 10,000 inhabitants have information on economic establishments.
Intermediate Results Indicator
The country has a Consumer Price Index Calculated based on an updated basket with a new base year
Intermediate Results Indicator
100% of the departments have updated socio-demographic information.
Intermediate Results Indicator
100% of the departments have updated demographic and health information.
Intermediate Results Indicator
Nine capital cities, El Alto and rural areas have updated information on household incomes and structure of expenditures.
Intermediate Results Indicator
At least 30 public statistical units and enterprises, at the national and subnational level, of the country's Statistical System apply standardized methods of production of data developed by INE.
44000-P083965
World Bank
BO-Secondary Education Transformation
International Development Association
MINISTRY OF EDUCATION
International Development Association
MINISTRY OF EDUCATIONPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Patricia Alvarez
+1-202-473-1000palvarez@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
La Paz
-16.5000 -68.1500
Sub-National GovernmentPrimary EducationSecondary EducationAdministrative and Civil Service ReformEducation FinancingAccess to EducationPublic AdministrationMunicipal Institution BuildingEducation
0.00
0.00
0.00
0.00
0.00
0.00
733333.34
733333.34
733333.32
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
700000.00
700000.00
700000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1200000.00
1200000.00
1200000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
700000.00
700000.00
700000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
441548.11
441548.11
441548.11
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1093202.20
1093202.21
1093202.21
0.00
0.00
0.00
389125.52
389125.52
389125.53
0.00
0.00
0.00
579457.49
579457.49
579457.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
71794.86
71794.88
71794.88
143589.74
143589.74
143589.75
379487.17
379487.18
379487.18
234871.78
234871.80
234871.80
0.00
0.00
0.00
0.00
0.00
10000000Total Commitment in Fourth Quarter of 2007
International Development Association306318Total Disbursement in First Quarter of 2009
International Development Association650000Total Disbursement in First Quarter of 2009
International Development Association150000Total Disbursement in Second Quarter of 2009
International Development Association218326Total Disbursement in Second Quarter of 2009
International Development Association312945Total Disbursement in Third Quarter of 2009
International Development Association401726Total Disbursement in Third Quarter of 2009
International Development Association-8092Total Interest Repayment in Third Quarter of 2009
International Development Association140506Total Disbursement in Fourth Quarter of 2009
International Development Association349419Total Disbursement in Fourth Quarter of 2009
International Development Association725843Total Disbursement in Fourth Quarter of 2009
International Development Association428614Total Disbursement in First Quarter of 2010
International Development Association445352Total Disbursement in First Quarter of 2010
International Development Association-9429Total Interest Repayment in First Quarter of 2010
International Development Association475203Total Disbursement in Second Quarter of 2010
International Development Association-15181Total Interest Repayment in Third Quarter of 2010
International Development Association176611Total Disbursement in Fourth Quarter of 2010
International Development Association267232Total Disbursement in Fourth Quarter of 2010
International Development Association723534Total Disbursement in Fourth Quarter of 2010
International Development Association-19654Total Interest Repayment in First Quarter of 2011
International Development Association59761Total Disbursement in Second Quarter of 2011
International Development Association378394Total Disbursement in Second Quarter of 2011
International Development Association-23705Total Interest Repayment in Third Quarter of 2011
International Development Association783879Total Disbursement in Fourth Quarter of 2011
International Development Association368405Total Disbursement in First Quarter of 2012
International Development Association-23256Total Interest Repayment in First Quarter of 2012
International Development Association387692Total Disbursement in Second Quarter of 2012
International Development Association479745Total Disbursement in Third Quarter of 2012
International Development Association-27950Total Interest Repayment in Third Quarter of 2012
International Development Association263700Total Disbursement in Fourth Quarter of 2012
International Development Association31431Total Disbursement in First Quarter of 2013
International Development Association312527Total Disbursement in First Quarter of 2013
International Development Association744077Total Disbursement in First Quarter of 2013
International Development Association-30610Total Interest Repayment in First Quarter of 2013
International Development Association302388Total Disbursement in Second Quarter of 2013
International Development Association-92072Total Commitment Cancellations in Third Quarter of 2013
International Development Association37621Total Disbursement in Third Quarter of 2013
International Development Association-36535Total Interest Repayment in Third Quarter of 2013
International Development Association-37136Total Interest Repayment in First Quarter of 2014
International Development Association-37072Total Interest Repayment in Third Quarter of 2014
International Development Association-34181Total Interest Repayment in First Quarter of 2015
International Development Association-33895Total Interest Repayment in Third Quarter of 2015
International Development Association-33658Total Interest Repayment in First Quarter of 2016
International Development Association-33987Total Interest Repayment in Third Quarter of 2016
International Development Association-32352Total Interest Repayment in First Quarter of 2017
International Development Association-33627Total Interest Repayment in Third Quarter of 2017
International Development Association-31177Total Interest Repayment in First Quarter of 2018
International Development Association-117405Total Loan Repayment in First Quarter of 2018
International Development Association-37425Total Interest Repayment in Third Quarter of 2018
International Development Association-111351Total Loan Repayment in Third Quarter of 2018
International Development Association-31857Total Interest Repayment in First Quarter of 2019
International Development Association-111608Total Loan Repayment in First Quarter of 2019
International Development Association-32725Total Interest Repayment in Third Quarter of 2019
International Development Association-110627Total Loan Repayment in Third Quarter of 2019
International Development Association-31371Total Interest Repayment in First Quarter of 2020
International Development Association-110074Total Loan Repayment in First Quarter of 2020
International Development AssociationProject Information DocumentProject Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementContract AwardsProject URLProcurement Notices
Maintain a qualified team responsible for project implementation
Submit Project Reports covering semester periods
Intermediate Results Indicator
Students from grades 1, 2, 3 and 4 at secondary level enrolled in the Program for At-Risk Students
This is the cumulative number of students that participated in the program in 2009, 2010 and 2011.
Intermediate Results Indicator
Classrooms built, and furnished in 7 completely reconstructed and expanded school buildings
Intermediate Results Indicator
Classrooms built and equipped with audiovisual or computer equipment
Intermediate Results Indicator
Sanitary facilities constructed
Intermediate Results Indicator
Administrative offices constructed with furniture and equipment
Intermediate Results Indicator
Study on roles and responsibilities in school maintenance
As a result of the study, there is a formal regulation (Reglamento) for the education infrastructure maintainance, which is beingvalidated with the community (Juntas Escolares)
Intermediate Results Indicator
Teachers, principals and municipal staff who have received diplomas in civic values and active citizenship
Intermediate Results Indicator
Teachers, administrators, members of Juntas Escolares who have received training in civic values from those that have received a diploma in civic values and active citizenship
Intermediate Results Indicator
Secondary school students between grades 3 and 6 who become involved in dialogues, classroom projects and movements related to civic values
Intermediate Results Indicator
Establishment and operation of Center for High Performance functioning
Intermediate Results Indicator
School Improvement Plans prepared by trained school management committees and financed by the Project
Intermediate Results Indicator
OMDH equipped and strengthened
PDO Indicator
Strengthen the capacity for decentralized education management: School buildings with functioning management teams in La Paz
PDO Indicator
Increase quality: Diminish the repetition rate in secondary education from 8.3% to 5.7%
The MoE made adjustments to their data base last year, which had influence in the project indicators and revised this progressdataupward.
PDO Indicator
Increase quality: Increase the promotion rate in secondary education from 86.2% to 90.9%
The MoE made adjustments to their data base last year, which had influence in the project indicators and revised this progressdatadownward.
Intermediate Results Indicator
New, rehabilitated or reconstructed classrooms with furniture in about 12 improved school buildings
11 additional classrooms will be completed by March 31, 2013 (closing date of the Project). Making a total of 97 classrooms.
PDO Indicator
Increase access: Increase in enrollment in secondary education in the 7 completely reconstructed school buildings financed by the Project
Current data is as of March 8, 2013 and provided by the Municipality of La Paz system information.
Intermediate Results Indicator
Information management and monitoring system in place
Intermediate Results Indicator
Direct project beneficiaries
Intermediate Results Indicator
Female beneficiaries
44000-P150751
World Bank
Bolivia Disaster Risk Managment DPC and DPL
International Bank for Reconstruction and Development
MINISTRY OF ECONOMY AND PUBLIC FINANCE
International Bank for Reconstruction and Development
International Development Association
International Development Association
MINISTRY OF ECONOMY AND PUBLIC FINANCEPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Oscar Anil Ishizawa Escudero
+1-202-473-1000oishizawa@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
Sucre
-19.0333 -65.2627
Other Non-bank Financial InstitutionsOther Water Supply, Sanitation and Waste ManagementOther Public AdministrationOther TransportationSub-National GovernmentDisaster Risk ReductionAdaptationDisaster Risk ManagementDisaster Risk FinanceDisaster PreparednessClimate changeFinance for DevelopmentDisaster Response and Recovery
0.00
0.00
4630970Total Commitment in First Quarter of 2015
International Development Association
95369030Total Commitment in First Quarter of 2015
International Development Association
100000000Total Commitment in First Quarter of 2015
International Bank for Reconstruction and Development
4500416Total Disbursement in Second Quarter of 2015
International Development Association
92680442Total Disbursement in Second Quarter of 2015
International Development Association
250000Total Disbursement in Second Quarter of 2015
International Bank for Reconstruction and Development
99750000Total Disbursement in Second Quarter of 2015
International Bank for Reconstruction and Development
-250000Total Interest Repayment in Second Quarter of 2015
International Bank for Reconstruction and Development
-63776Total Interest Repayment in First Quarter of 2016
International Development Association
-1018131Total Interest Repayment in First Quarter of 2016
International Development Association
-1056443Total Interest Repayment in First Quarter of 2016
International Bank for Reconstruction and Development
-57541Total Interest Repayment in Third Quarter of 2016
International Development Association
-918593Total Interest Repayment in Third Quarter of 2016
International Development Association
-1117278Total Interest Repayment in Third Quarter of 2016
International Bank for Reconstruction and Development
-55780Total Interest Repayment in First Quarter of 2017
International Development Association
-890474Total Interest Repayment in First Quarter of 2017
International Development Association
-1190889Total Interest Repayment in First Quarter of 2017
International Bank for Reconstruction and Development
-56568Total Interest Repayment in Third Quarter of 2017
International Development Association
-903067Total Interest Repayment in Third Quarter of 2017
International Development Association
-1347444Total Interest Repayment in Third Quarter of 2017
International Bank for Reconstruction and Development
-59170Total Interest Repayment in First Quarter of 2018
International Development Association
-944594Total Interest Repayment in First Quarter of 2018
International Development Association
-1436222Total Interest Repayment in First Quarter of 2018
International Bank for Reconstruction and Development
-58694Total Interest Repayment in Third Quarter of 2018
International Development Association
-937000Total Interest Repayment in Third Quarter of 2018
International Development Association
-1623972Total Interest Repayment in Third Quarter of 2018
International Bank for Reconstruction and Development
-57035Total Interest Repayment in First Quarter of 2019
International Development Association
-910521Total Interest Repayment in First Quarter of 2019
International Development Association
-1978000Total Interest Repayment in First Quarter of 2019
International Bank for Reconstruction and Development
-57621Total Interest Repayment in Third Quarter of 2019
International Development Association
-919867Total Interest Repayment in Third Quarter of 2019
International Development Association
-2116694Total Interest Repayment in Third Quarter of 2019
International Bank for Reconstruction and Development
-56840Total Interest Repayment in First Quarter of 2020
International Development Association
-907394Total Interest Repayment in First Quarter of 2020
International Development Association
-1819556Total Interest Repayment in First Quarter of 2020
International Bank for Reconstruction and Development
Project Information DocumentProject Information DocumentImplementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportLoan AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Intermediate Results Indicator
Number of departmental development plans that incorporate disaster risk management
Intermediate Results Indicator
Issuance of Ministerial Regulation to incorporate risk analysis in public investment projects
Intermediate Results Indicator
Approval of organizational design and operating standards for the operation of the Trust Fund Plurinational Mother Earth
Intermediate Results Indicator
Adoption of the Plurinational Climate Change Plan articulating policies, financing and coordination mechanisms at the national and subnational levels for climate change adaptation activities
Intermediate Results Indicator
Adoption of guidelines defining roles and coordination mechanisms for emergency and disaster response at all levels of government.
Intermediate Results Indicator
Number of Departmental Emergency Operation Committees (COED) established and operating.
Intermediate Results Indicator
Number of Municipal Emergency Operation Committees (COEM) established and operating.
Intermediate Results Indicator
Adoption of emergency operations procedures integrating the role of Firefighters at national level
Intermediate Results Indicator
Number of departmental emergency management protocols integrating the role of Firefighters
Intermediate Results Indicator
Issuance of guidelines to acquire, design and implement risk transfer instruments for the national and subnational governmental levels
Intermediate Results Indicator
National Budget 2016 includes a specific budget allocation for FORADE
44000-P143995
World Bank
Bolivia: Improving Employability and Labor Income of Youth Project
International Development Association
MINISTRY OF LABOR
International Development Association
MINISTRY OF LABORPlanned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Patricia Alvarez
+1-202-473-1000palvarez@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
Departamento de Tarija
-21.5000 -64.0000
Departamento de Santa Cruz
-17.5000 -61.5000
Departamento de Potosi
-20.6670 -67.0000
Departamento de Pando
-11.3330 -67.6670
Departamento de Oruro
-18.6670 -67.5000
Departamento de La Paz
-15.5000 -68.0000
Departamento de Cochabamba
-17.5000 -65.6670
Departamento de Chuquisaca
-20.0000 -64.3330
Departamento del Beni
-14.0000 -65.5000
Secondary EducationPublic Administration - Social ProtectionSocial ProtectionStandards, Curriculum and TextbooksJobsLabor Market InstitutionsScience and TechnologyAccess to EducationLabor Market Policy and ProgramsActive Labor Market ProgramsTeachersEducation
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
200000.00
200000.00
200000.00
200000.00
200000.00
200000.00
225000.00
225000.00
225000.00
225000.00
225000.00
225000.00
225000.00
225000.00
225000.00
225000.00
225000.00
225000.00
266666.67
266666.67
266666.66
266666.67
266666.67
266666.66
266666.67
266666.67
266666.66
266666.67
266666.67
266666.66
291666.67
291666.67
291666.66
291666.67
291666.67
291666.66
291666.67
291666.67
291666.66
291666.67
291666.67
291666.66
300000.00
300000.00
300000.00
300000.00
300000.00
300000.00
300000.00
300000.00
300000.00
300000.00
300000.00
300000.00
316666.67
316666.67
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.37
24677.10
24677.10
24677.10
24677.10
24677.10
24677.10
24677.10
24677.10
24677.10
24677.10
24677.10
24677.15
33333.33
33333.33
33333.33
33333.33
33333.33
33333.33
33333.33
33333.33
33333.33
33333.33
33333.33
33333.37
31002.23
31002.23
31002.23
31002.23
31002.23
31002.23
31002.23
31002.23
31002.23
31002.23
31002.23
31002.18
1031301.38
1031301.38
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
20000000Total Commitment in Second Quarter of 2014
International Development Association1000000Total Disbursement in First Quarter of 2016
International Development Association-4243Total Interest Repayment in Second Quarter of 2016
International Development Association38810Total Disbursement in Third Quarter of 2016
International Development Association227312Total Disbursement in Fourth Quarter of 2016
International Development Association-9806Total Interest Repayment in Fourth Quarter of 2016
International Development Association30003Total Disbursement in Second Quarter of 2017
International Development Association-12304Total Interest Repayment in Second Quarter of 2017
International Development Association-13499Total Interest Repayment in Fourth Quarter of 2017
International Development Association400000Total Disbursement in Second Quarter of 2018
International Development Association-13270Total Interest Repayment in Second Quarter of 2018
International Development Association-16766Total Interest Repayment in Fourth Quarter of 2018
International Development Association372027Total Disbursement in Second Quarter of 2019
International Development Association-17854Total Interest Repayment in Second Quarter of 2019
International Development Association-296724Total Loan Repayment in Second Quarter of 2019
International Development Association454712Total Disbursement in Third Quarter of 2019
International Development Association566497Total Disbursement in Third Quarter of 2019
International Development Association-21437Total Interest Repayment in Fourth Quarter of 2019
International Development Association-296887Total Loan Repayment in Fourth Quarter of 2019
International Development Association1041394Total Disbursement in First Quarter of 2020
International Development AssociationProject Information DocumentProject Information DocumentProject Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Finance Agreement: For purposes of carrying out Parts A and B of the Project, the Recipient shall establish and maintain theProject Implementation Unit (PIU) in the Ministry of Development Planning with staff in place and responsibilities satisfactory tothe Association
Finance Agreement :Beneficiary Registry | Description :Schedule 2. Section I.A.2 Prior to the carrying out of any activity underPart A of the Project, the Recipient shall establish a registry of beneficiaries on terms and in a manner, acceptable to theAssociation.
Finance Agreement, Section I.A.4. Schedule 2, Project Execution. No later that ninety (90) days from the effective Date of therestated FA, the Recipient shall contract a PIU core team as defined in the Operational Manual
Finance Agreement: Prior to carrying out any activity under the Project, the Recipient shall adopt an Operational Manual Acceptableto the Association
Institutional agreement: Prior to carrying out any activity under Part A, the Recipient shall furnish to the Bank a model of laborcontract to be used by project participating firms to hire beneficiaries for the duration of the program and relieving them fromtheobligation to retain beneficiaries after the program.
Intermediate Results Indicator
Direct Project beneficiaries
PDO Indicator
Increase in the average labor income of PMEIL beneficiaries one year after completing the on-job training.
Intermediate Results Indicator
Beneficiaries of labor market programs
PDO Indicator
Increase in the placement rate of PMEIL beneficiaries in a job with at least minimum salary one year after completing the on-the-job training.
PDO Indicator
Percentage of vacancies registered during the project that are filled with a project beneficiary
Intermediate Results Indicator
Beneficiaries that have received on-the-job training
PDO Indicator
Expansion of geographical coverage of the PMEIL
Intermediate Results Indicator
Beneficiaries of internships
Intermediate Results Indicator
Beneficiaries that have completed the employability training course.
Intermediate Results Indicator
Beneficiaries that have completed the on-the-job training and/or internship
Intermediate Results Indicator
Employers who registered vacancies in PMEIL over total employers who registered vacancies in the Labor Insertion Program
Intermediate Results Indicator
Percentage of female beneficiaries
Intermediate Results Indicator
Beneficiaries of labor market programs - Female
44000-P173984
World Bank
COVID-19 Crisis Emergency Social Safety Nets Project
International Bank for Reconstruction and Development
International Bank for Reconstruction and Development
International Development Association
International Development Association
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Gaston Mariano Blanco
+1-202-473-1000gblanco@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OFSocial ProtectionDisease ControlPandemic ResponseSocial ProtectionSocial Safety Nets
0.00
0.00
710000.00
1270000.00
2550000.00
1290000.00
1290000.00
2600000.00
1310000.00
2640000.00
1330000.00
1340000.00
2690000.00
1360000.00
2730000.00
1370000.00
1380000.00
2770000.00
1390000.00
2800000.00
1400000.00
1400000.00
2810000.00
1440000.00
3180000.00
2020000.00
4860000.00
2670000.00
2830000.00
6030000.00
3140000.00
6070000.00
2940000.00
3010000.00
6230000.00
3210000.00
6590000.00
3370000.00
3400000.00
6870000.00
3220000.00
6620000.00
3380000.00
3420000.00
6930000.00
3480000.00
7020000.00
3320000.00
6670000.00
3390000.00
3420000.00
6890000.00
3460000.00
6950000.00
3480000.00
3480000.00
6970000.00
3490000.00
6970000.00
3490000.00
3490000.00
6970000.00
3480000.00
6950000.00
3470000.00
10390000.00
3460000.00
6900000.00
3440000.00
3420000.00
0.00
0.00
0.00
710000.00
1270000.00
2550000.00
1290000.00
1290000.00
2600000.00
1310000.00
2640000.00
1330000.00
1340000.00
2690000.00
1360000.00
2730000.00
1370000.00
1380000.00
2770000.00
1390000.00
2800000.00
1400000.00
1400000.00
2810000.00
1440000.00
3180000.00
2020000.00
4860000.00
2670000.00
2830000.00
6030000.00
3140000.00
6070000.00
2940000.00
3010000.00
6230000.00
3210000.00
6590000.00
3370000.00
3400000.00
6870000.00
3220000.00
6620000.00
3380000.00
3420000.00
6930000.00
3480000.00
7020000.00
3320000.00
6670000.00
3390000.00
3420000.00
6890000.00
3460000.00
6950000.00
3480000.00
3480000.00
6970000.00
3490000.00
6970000.00
3490000.00
3490000.00
6970000.00
3480000.00
6950000.00
3470000.00
10390000.00
3460000.00
6900000.00
3440000.00
3420000.00
0.00
0Total Disbursement in First Quarter of 2020
International Bank for Reconstruction and Development
0Total Disbursement in First Quarter of 2020
International Development Association
21000000Total Commitment in Second Quarter of 2020
International Development Association
33300000Total Commitment in Second Quarter of 2020
International Development Association
200000000Total Commitment in Second Quarter of 2020
International Bank for Reconstruction and Development
Project Information DocumentContract AwardsProject URLProcurement Notices 44000-P101206
World Bank
Expanding Access to Reduce Health Inequities Project (APL III)--Former Health Sector Reform - Third Phase (APL III)
International Development Association
MINISTRY OF HEALTH AND SPORTS
International Development Association
MINISTRY OF HEALTH AND SPORTSPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Andre C. Medici
+1-202-473-1000amedici@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
El Alto
-16.4830 -68.1830
Yaco
-17.1500 -67.4000
Waldo Ballivian
-17.5330 -67.9830
Villa Viscarra
-17.9830 -65.6000
Villa General Perez
-15.2000 -69.0500
Sicasica
-17.3330 -67.7390
Umala
-17.3740 -68.0230
Turco
-18.1820 -68.1920
Toledo
-18.1810 -67.4070
Sicaya
-17.8000 -66.3340
Sapahaqui
-16.8890 -67.9490
Santivanez
-17.5460 -66.2460
Santa Ana de Yacuma
-13.7500 -65.4330
San Pedro
-16.2370 -68.8510
Pelechuco
-14.8000 -69.0830
Patacamaya
-17.2360 -67.9220
Pasorapa
-18.3210 -64.6770
Papel Pampa
-17.7830 -67.8500
Omereque
-18.1060 -64.9080
Morochata
-17.8670 -65.8170
Mizque
-17.9410 -65.3400
Malla
-17.0830 -67.4830
Luribay
-17.0500 -67.6670
Exaltacion
-19.0170 -67.6670
Estancia Toco Vilaque
-17.3000 -67.1000
El Choro
-18.3570 -67.1150
Curva
-15.1380 -69.0530
Corque
-18.3500 -67.6820
Colquencha
-16.9330 -68.2500
Collana
-17.4330 -68.5500
Chuma
-15.4830 -68.9000
Chacarilla
-17.5670 -68.2170
Capinota
-17.7110 -66.2610
Callapa
-17.4830 -68.4000
Calamarca
-16.6330 -68.6000
Cairoma
-16.9000 -67.5500
Bolivar
-17.9690 -66.5380
Belen de Anamarca
-18.8190 -67.6410
Ayo Ayo
-17.0940 -68.0060
Ayata
-15.3410 -68.7530
Aucapata
-15.5000 -68.7670
Arque
-17.8220 -66.4040
Apolo
-14.7190 -68.4120
Cochabamba
-17.3900 -66.1570
Independencia
-17.0840 -66.8180
Sub-National GovernmentCentral Government (Central Agencies)HealthPublic Administration - HealthNutritionHealth System StrengtheningChild HealthFood SecurityReproductive and Maternal HealthNutrition and Food SecurityHealth Systems and Policies
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
693333.15
693333.15
693333.15
0.00
0.00
0.00
666666.49
666666.49
666666.49
0.00
0.00
0.00
693333.15
693333.15
693333.15
0.00
0.00
0.00
666666.49
666666.49
666666.49
0.00
0.00
0.00
693333.15
693333.15
693333.15
0.00
0.00
0.00
499999.86
499999.86
499999.86
0.00
0.00
0.00
526666.52
526666.52
526666.52
0.00
0.00
0.00
499999.86
499999.86
499999.86
0.00
0.00
0.00
533333.20
533333.20
533333.18
0.00
0.00
0.00
333333.24
333333.24
333333.25
0.00
0.00
0.00
360001.56
360001.56
360001.56
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
25933.51
25933.51
25933.51
25933.51
25933.51
25933.51
25933.51
25933.51
25933.51
25933.51
25933.51
25933.43
84751.25
84751.25
84751.25
84751.25
84751.25
84751.25
84751.25
84751.25
84751.25
84751.25
84751.25
84751.25
112047.32
112047.32
112047.32
112047.32
112047.32
112047.32
112047.32
112047.32
112047.32
112047.32
112047.32
112047.35
56845.01
56845.01
56845.01
56845.01
56845.01
56845.01
56845.01
56845.01
56845.01
56845.01
56845.01
56845.00
269398.57
269398.57
269398.57
269398.57
269398.57
269398.57
269398.57
269398.57
269398.57
269398.57
269398.57
269398.57
162599.71
162599.71
162599.71
162599.71
162599.71
162599.71
162599.71
162599.71
162599.71
162599.71
162599.71
162599.77
191024.34
191024.34
191024.34
191024.34
191024.34
191024.34
191024.34
191024.34
191024.34
191024.34
191024.34
191024.41
0.00
18500000Total Commitment in First Quarter of 2008
International Development Association300000Total Disbursement in First Quarter of 2010
International Development Association200000Total Disbursement in Third Quarter of 2010
International Development Association-861Total Interest Repayment in Third Quarter of 2010
International Development Association151816Total Disbursement in Fourth Quarter of 2010
International Development Association400000Total Disbursement in Fourth Quarter of 2010
International Development Association253240Total Disbursement in First Quarter of 2011
International Development Association-3268Total Interest Repayment in First Quarter of 2011
International Development Association469079Total Disbursement in Third Quarter of 2011
International Development Association-4907Total Interest Repayment in Third Quarter of 2011
International Development Association168181Total Disbursement in Fourth Quarter of 2011
International Development Association302007Total Disbursement in First Quarter of 2012
International Development Association-7216Total Interest Repayment in First Quarter of 2012
International Development Association379774Total Disbursement in Second Quarter of 2012
International Development Association186383Total Disbursement in Third Quarter of 2012
International Development Association-8461Total Interest Repayment in Third Quarter of 2012
International Development Association184854Total Disbursement in Fourth Quarter of 2012
International Development Association220981Total Disbursement in First Quarter of 2013
International Development Association-10585Total Interest Repayment in First Quarter of 2013
International Development Association-7325925Total Commitment Cancellations in Second Quarter of 2013
International Development Association70471Total Disbursement in Second Quarter of 2013
International Development Association245788Total Disbursement in Third Quarter of 2013
International Development Association328814Total Disbursement in Third Quarter of 2013
International Development Association699542Total Disbursement in Third Quarter of 2013
International Development Association-12221Total Interest Repayment in Third Quarter of 2013
International Development Association344765Total Disbursement in Fourth Quarter of 2013
International Development Association368976Total Disbursement in Fourth Quarter of 2013
International Development Association439115Total Disbursement in First Quarter of 2014
International Development Association-17833Total Interest Repayment in First Quarter of 2014
International Development Association174861Total Disbursement in Second Quarter of 2014
International Development Association526819Total Disbursement in Second Quarter of 2014
International Development Association297494Total Disbursement in Third Quarter of 2014
International Development Association702409Total Disbursement in Third Quarter of 2014
International Development Association-22983Total Interest Repayment in Third Quarter of 2014
International Development Association573165Total Disbursement in Fourth Quarter of 2014
International Development Association756930Total Disbursement in Fourth Quarter of 2014
International Development Association795866Total Disbursement in First Quarter of 2015
International Development Association-27352Total Interest Repayment in First Quarter of 2015
International Development Association128313Total Disbursement in Second Quarter of 2015
International Development Association-116034Total Disbursement in Third Quarter of 2015
International Development Association151875Total Disbursement in Third Quarter of 2015
International Development Association-33569Total Interest Repayment in Third Quarter of 2015
International Development Association14663Total Disbursement in Fourth Quarter of 2015
International Development Association176908Total Disbursement in Fourth Quarter of 2015
International Development Association307110Total Disbursement in Fourth Quarter of 2015
International Development Association18490Total Disbursement in First Quarter of 2016
International Development Association21995Total Disbursement in First Quarter of 2016
International Development Association-34437Total Interest Repayment in First Quarter of 2016
International Development Association40394Total Disbursement in Second Quarter of 2016
International Development Association-26295Total Commitment Cancellations in Third Quarter of 2016
International Development Association-2123Total Disbursement in Third Quarter of 2016
International Development Association-36168Total Interest Repayment in Third Quarter of 2016
International Development Association-34321Total Interest Repayment in First Quarter of 2017
International Development Association-35673Total Interest Repayment in Third Quarter of 2017
International Development Association-33074Total Interest Repayment in First Quarter of 2018
International Development Association-124548Total Loan Repayment in First Quarter of 2018
International Development Association-39702Total Interest Repayment in Third Quarter of 2018
International Development Association-118125Total Loan Repayment in Third Quarter of 2018
International Development Association-33795Total Interest Repayment in First Quarter of 2019
International Development Association-118398Total Loan Repayment in First Quarter of 2019
International Development Association-34716Total Interest Repayment in Third Quarter of 2019
International Development Association-117358Total Loan Repayment in Third Quarter of 2019
International Development Association-33280Total Interest Repayment in First Quarter of 2020
International Development Association-116770Total Loan Repayment in First Quarter of 2020
International Development AssociationProject Information DocumentProject Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementFinancing AgreementProject Performance Assessment ReportContract AwardsProject URLProcurement Notices
Finance Agreement :MS shall maintain UCOFI fully staffed and productive | Description :Section I.B. 2 and 3 of Schedule 2 |Frequency :Yearly
PDO Indicator
Ratio between the percentage of pregnant women accessing four prenatal care visits in the areas of project intervention and the rest of the country.
PDO Indicator
Ratio between the percentage of institutional deliveries in the areas of project intervention and the rest of the country.
Intermediate Results Indicator
Percentage of the health units applying the sector regulations norms and the PRONACS norms.
PDO Indicator
Porcentage of Target Population Enrolled in the Family Register Forms (Carpeta Familiar) in the Project Target Areas.
Intermediate Results Indicator
Percentage of health units in the target areas following approved normative to characterize health units at first and second level.
Intermediate Results Indicator
Percentage of civil works concluded in the health facilities in the areas of intervention
Intermediate Results Indicator
Percentage of equipment installed in health facilities in the areas of intervention.
PDO Indicator
Porcentage of 2 year old children covered with height growth control (CRED) in the intervention areas of the project.
PDO Indicator
The modules included in the SNIS are fully implemented in the SEDES, and all the heads of the referral networks in the interventionareas.
Intermediate Results Indicator
Percentage of user's population receiving services satisfied with the quality of the services received in the project areas.
44000-P101084
World Bank
BO: Investing in Children and Youth
International Development Association
MINISTRY OF HEALTH AND SPORTS
International Development Association
MINISTRY OF HEALTH AND SPORTSPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Gaston Mariano Blanco
+1-202-473-1000gblanco@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
Culpina
-20.7700 -64.6800
Icla
-19.4580 -64.7840
Incahuasi
-20.5940 -65.0200
Mojocoya
-18.8220 -64.6270
Poroma
-18.8610 -65.3570
Presto
-18.8930 -64.9510
San Lucas
-20.1600 -64.9310
Sopachuy
-19.4510 -64.5290
Tarabuco
-19.1510 -64.9030
Tomina
-19.2030 -64.5230
Yamparáez
-19.2510 -65.0780
Santiago de Callapa
-17.2360 -68.3370
Azurduy
-20.0960 -64.4110
Tarvita
-19.8400 -64.4930
Rio Ayopaya
-17.0170 -67.0170
Zudáñez
-19.1190 -64.7010
Yunchara
-21.8240 -65.2280
Vila Vila
-17.3500 -67.7670
Urmiri
-18.5780 -66.8770
Uncia
-18.4670 -66.5700
Torotoro
-18.1350 -65.7620
Tacopa
-17.3000 -69.1500
Tacobamba
-19.2010 -65.5520
Sicaya
-17.8000 -66.3340
Sapahaqui
-16.8890 -67.9490
Santa Rosa del Abuná
-10.6070 -67.4520
San Pedro de Buena Vista
-18.2690 -65.9820
Sacaca
-18.0700 -66.3850
Ravelo
-18.8070 -65.5120
Puerto Siles
-12.8110 -65.1150
Pucará
-18.7160 -64.1840
Pocoata
-18.7000 -66.1630
Ocuri
-18.8420 -65.7960
Moro Moro
-18.3670 -64.3230
Morochata
-17.2350 -66.5320
Loreto
-15.1930 -64.7590
GutiErrez
-19.4230 -63.5290
Tinguipaya
-19.2200 -65.8230
Exaltación
-13.2790 -65.2400
El Choro
-18.3570 -67.1150
Curva
-15.1380 -69.0530
Colquechaca
-18.7000 -66.0040
Chayanta
-18.4490 -66.4610
Chacarilla
-17.5670 -68.2170
Caripuyo
-18.2330 -66.4740
Bolivar
-12.2670 -67.4330
Betanzos
-19.5530 -65.4540
Ayata
-15.3410 -68.7530
Arque
-17.8220 -66.4040
Arampampa
-17.9590 -66.0940
Acacio
-18.0240 -66.0580
Central Government (Central Agencies)Social ProtectionSocial Safety NetsNutrition and Food SecurityFood SecurityLabor Market InstitutionsActive Labor Market ProgramsNutritionJobsSocial ProtectionLabor Market Policy and Programs
0.00
0.00
0.00
0.00
145833.33
145833.33
145833.34
145833.33
145833.33
145833.34
145833.33
145833.33
145833.34
145833.33
145833.33
145833.34
445833.33
445833.33
445833.34
445833.33
445833.33
445833.34
445833.33
445833.33
445833.34
445833.33
445833.33
445833.34
433333.33
433333.33
433333.34
433333.33
433333.33
433333.34
433333.33
433333.33
433333.34
433333.33
433333.33
433333.34
247500.00
247500.00
247500.00
247500.00
247500.00
247500.00
247500.00
247500.00
247500.00
247500.00
247500.00
247500.00
288333.33
288333.33
288333.34
288333.33
288333.33
288333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
183333.33
183333.33
183333.34
0.00
0.00
0.00
73333.33
73333.33
73333.34
0.00
0.00
0.00
31118.23
31118.23
31118.23
275095.90
275095.90
275095.89
0.00
0.00
0.00
117971.44
117971.44
117971.43
84135.81
84135.81
84135.81
293333.33
293333.33
293333.34
227169.14
227169.14
227169.13
230324.62
230324.62
230324.63
258944.12
258944.12
258944.11
84501.74
84501.74
84501.74
73835.07
73835.07
73835.08
231981.10
231981.10
231981.11
0.00
0.00
0.00
156049.32
156049.32
156049.31
533333.33
533333.33
533333.34
533333.33
533333.33
533333.34
504355.67
504355.67
504355.67
476675.96
476675.96
476675.96
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
17000000Total Commitment in First Quarter of 2008
International Development Association550000Total Disbursement in Third Quarter of 2009
International Development Association220000Total Disbursement in First Quarter of 2010
International Development Association-1496Total Interest Repayment in First Quarter of 2010
International Development Association93355Total Disbursement in Third Quarter of 2010
International Development Association-2547Total Interest Repayment in Third Quarter of 2010
International Development Association325288Total Disbursement in Fourth Quarter of 2010
International Development Association500000Total Disbursement in Fourth Quarter of 2010
International Development Association-4373Total Interest Repayment in First Quarter of 2011
International Development Association96048Total Disbursement in Second Quarter of 2011
International Development Association257866Total Disbursement in Second Quarter of 2011
International Development Association252407Total Disbursement in Third Quarter of 2011
International Development Association-7026Total Interest Repayment in Third Quarter of 2011
International Development Association880000Total Disbursement in Fourth Quarter of 2011
International Development Association681507Total Disbursement in First Quarter of 2012
International Development Association-10058Total Interest Repayment in First Quarter of 2012
International Development Association690974Total Disbursement in Second Quarter of 2012
International Development Association315988Total Disbursement in Third Quarter of 2012
International Development Association460845Total Disbursement in Third Quarter of 2012
International Development Association-15501Total Interest Repayment in Third Quarter of 2012
International Development Association32000Total Disbursement in Fourth Quarter of 2012
International Development Association221505Total Disbursement in Fourth Quarter of 2012
International Development Association221505Total Disbursement in First Quarter of 2013
International Development Association-20335Total Interest Repayment in First Quarter of 2013
International Development Association345340Total Disbursement in Second Quarter of 2013
International Development Association350603Total Disbursement in Second Quarter of 2013
International Development Association-22043Total Interest Repayment in Third Quarter of 2013
International Development Association-3810487Total Commitment Cancellations in Fourth Quarter of 2013
International Development Association193319Total Disbursement in Fourth Quarter of 2013
International Development Association274829Total Disbursement in Fourth Quarter of 2013
International Development Association-25329Total Interest Repayment in First Quarter of 2014
International Development Association101854Total Disbursement in Second Quarter of 2014
International Development Association366575Total Disbursement in Second Quarter of 2014
International Development Association70615Total Disbursement in Third Quarter of 2014
International Development Association285229Total Disbursement in Third Quarter of 2014
International Development Association-27006Total Interest Repayment in Third Quarter of 2014
International Development Association147091Total Disbursement in Fourth Quarter of 2014
International Development Association420310Total Disbursement in Fourth Quarter of 2014
International Development Association116761Total Disbursement in First Quarter of 2015
International Development Association-27612Total Interest Repayment in First Quarter of 2015
International Development Association170004Total Disbursement in Second Quarter of 2015
International Development Association245920Total Disbursement in Second Quarter of 2015
International Development Association3024512Total Disbursement in Second Quarter of 2015
International Development Association-30065Total Interest Repayment in Third Quarter of 2015
International Development Association-66913Total Disbursement in Fourth Quarter of 2015
International Development Association-1767Total Disbursement in Fourth Quarter of 2015
International Development Association-18909Total Disbursement in First Quarter of 2016
International Development Association-44267Total Interest Repayment in First Quarter of 2016
International Development Association-700188Total Commitment Cancellations in Second Quarter of 2016
International Development Association-289Total Commitment Cancellations in Second Quarter of 2016
International Development Association-1220Total Disbursement in Second Quarter of 2016
International Development Association-41741Total Interest Repayment in Third Quarter of 2016
International Development Association-39699Total Interest Repayment in First Quarter of 2017
International Development Association-41263Total Interest Repayment in Third Quarter of 2017
International Development Association-42655Total Interest Repayment in First Quarter of 2018
International Development Association-42265Total Interest Repayment in Third Quarter of 2018
International Development Association-136637Total Loan Repayment in Third Quarter of 2018
International Development Association-39601Total Interest Repayment in First Quarter of 2019
International Development Association-136952Total Loan Repayment in First Quarter of 2019
International Development Association-40668Total Interest Repayment in Third Quarter of 2019
International Development Association-135749Total Loan Repayment in Third Quarter of 2019
International Development Association-39001Total Interest Repayment in First Quarter of 2020
International Development Association-135069Total Loan Repayment in First Quarter of 2020
International Development AssociationProject Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Finance Agreement :43960 | Description :B.2.(i) establish and implemented to the satisfaction of the Association the conditionalmanagement information system to administer and monitor the Cash Transfers | Frequency :Monthly
Finance Agreement :43960 | Description :B.2.(ii) contracted the financial agency or agencies to pay the Cash Transfers tobeneficiary mothers following the Procurement methods in Schedule 2 and Annex to Schedule 2. | Frequency :Monthly
Finance Agreement :43960 | Description :B.3. The Ministry of Labor (MOL) has established and operated to the satisfaction of theAssociation a financial management system for the implementation of the project | Frequency :Monthly
Intermediate Results Indicator
Component 1: 1. Number of municipalities which signed agreements to enter the program
Intermediate Results Indicator
Component 1: 5. Proportion of pregnant women living in the targeted areas with complete pre-natal controls
Intermediate Results Indicator
Component 1: 4. Proportion of children under 2 years old who participate in the growth monitoring sessions in the areas of intervention.
Intermediate Results Indicator
Component 2: 1. Number of low income youth enrolled in the program during expansion
Intermediate Results Indicator
Component 2: 3. Number of departmental offices for the First Employment Program (DOFEP) with adequate staffing, operating and connected to the MIS (as described in the operational manual)
Intermediate Results Indicator
Component 3: 1. Registry of Beneficiaries and Monitoring System designed
PDO Indicator
Component 1: 1. Percent of 2-year old children participating in the program with a height for age below 2Z scores
PDO Indicator
Component 1: 2. Percentage of mothers with children younger than 2 living in the targeted areas receiving transfers
PDO Indicator
Component 2: 1. Proportion of beneficiaries enrolled during the expansion of the program that are poor
PDO Indicator
Component 2: 2. Percentage of beneficiaries with an employment contract four months after the end of the internship
PDO Indicator
Component 3: 1. Annual reports on RPS-DIC programs# progress submitted to CONAPES
Intermediate Results Indicator
Component 3: 2. New Operational Manual of BJA in use based on results of impact and process evaluation
PDO Indicator
Component 1: 3. Proportion of children participating in the program with anemia
PDO Indicator
Component 1: 4. Percentage of beneficiary women who know their rights to access services and co-responsabilities to participate in the program
Intermediate Results Indicator
Component 1: 9. Proportion of payment agencies with enough funds to pay beneficiaries on time
Intermediate Results Indicator
Component 1: 2. MIS system completed and operational
Intermediate Results Indicator
Component 1: 3. Number of municipalities with adequate IT-related equipment and connected with the MIS
Intermediate Results Indicator
Component 1: 6. Proportion of women receiving post natal care within seven days of delivery
Intermediate Results Indicator
Component 1: 7. Proportion of women participating in the program with sufficient knowledge about child care, food consumption home hygiene.
Intermediate Results Indicator
Component 1: 8. Proportion of bi-monthly reports on compliance with co-with coresponsibilities systematized through the MIS
Intermediate Results Indicator
Component 1. 10. Proportion of complains resolved by the program
Intermediate Results Indicator
Component 1. 11. Proportion of indigenous beneficiaries satisfied with the program
Intermediate Results Indicator
Component 2: 4. The Monitoring Information System Designed and operational
Intermediate Results Indicator
Component 1: 12. Proportion of registered women participating in IEC activities
Intermediate Results Indicator
Component 2: 2. National Unit for the First Employment Program (NUFEP) fully staffed and operational (as described in the operational manual).
Intermediate Results Indicator
Component 2: 5. Targeting mechanism to select low-income youths designed and tested
Intermediate Results Indicator
Component 2: 6. Process evaluation designed and implemented
Intermediate Results Indicator
Component 2: 7. Proportion of youth enrolled in the program completing the in-class phase of the program
Intermediate Results Indicator
Component 2: 8. Proportion of youths completing the internship (as a share of those who completed the in-class phase)
Intermediate Results Indicator
Component 2: 9. Share of women amongst beneficiaries who complete the internship
Intermediate Results Indicator
Component 2: 10. System to certify providers tested and operational
44000-P164453
World Bank
Health Service Delivery Network Project
International Bank for Reconstruction and Development
International Bank for Reconstruction and Development
International Development Association
International Development Association
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Carlos Marcelo Bortman
+1-202-473-1000mbortman@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
Departamento de Santa Cruz
-17.5000 -61.5000
Departamento de Potosi
-20.6670 -67.0000
Departamento de La Paz
-15.5000 -68.0000
Departamento de Cochabamba
-17.5000 -65.6670
El Beni
-14.0000 -65.5000
San Julian
-16.8330 -62.8000
Warnes
-17.5010 -63.1630
Uncia Municipality
-18.6000 -66.4330
San Ramon Municipality
-13.3330 -64.7500
Caranavi Municipality
-15.6670 -67.4170
Quillacollo
-17.3980 -66.2770
La Guardia
-17.8920 -63.3250
Cochabamba
-17.3610 -66.1560
La Paz
-16.5080 -68.1360
Robore
-18.3350 -59.7610
Puerto Suarez
-18.9500 -57.8000
Las Petas
-16.3830 -59.1830
Ascension
-16.3170 -59.4500
Villazon
-22.0870 -65.5940
Villamontes
-21.2620 -63.4690
Viacha
-16.6500 -68.3000
Uyuni
-21.1210 -66.4900
Santa Ana
-18.5930 -64.1450
Santa Ana
-10.7000 -65.5330
San Jose de Chiquitos
-17.8500 -60.7500
San Ignacio
-17.8670 -61.0500
San Ignacio de Velasco
-16.3670 -60.9500
Riberalta
-11.0070 -66.0630
Reyes
-14.2950 -67.3360
Puerto Villarroel
-16.8470 -64.7820
Puerto Heath
-12.5030 -68.6500
Puerto Acosta
-15.5320 -69.2510
Montero
-17.6330 -62.8000
Magdalena
-13.2330 -64.2000
Guaqui
-16.5830 -68.8670
Concepcion
-16.1320 -62.0280
Caranavi
-15.8170 -67.5500
Camiri
-20.0970 -63.5220
Asuncion
-11.7470 -67.9130
Apolo
-14.7190 -68.4120
Aiquile
-18.2040 -65.1810
San Borja
-14.8520 -66.7500
Yacuiba
-22.0160 -63.6780
Tarabuco
-19.1820 -64.9150
HealthPublic Administration - HealthHealth Facilities and ConstructionHealth Systems and PoliciesHealth Service DeliveryAdaptationHealth System StrengtheningMitigationClimate change
0.00
0.00
1666666.67
1666666.67
1666666.67
1666666.67
1666666.67
1666666.67
1666666.67
1666666.67
1666666.67
1666666.67
1666666.67
1666666.63
3750000.00
3750000.00
3750000.00
3750000.00
3750000.00
3750000.00
3750000.00
3750000.00
3750000.00
3750000.00
3750000.00
3750000.00
5583333.33
5583333.33
5583333.33
5583333.33
5583333.33
5583333.33
5583333.33
5583333.33
5583333.33
5583333.33
5583333.33
5583333.37
5916666.67
5916666.67
5916666.67
5916666.67
5916666.67
5916666.67
5916666.67
5916666.67
5916666.67
5916666.67
5916666.67
5916666.63
5833333.33
5833333.33
5833333.33
5833333.33
5833333.33
5833333.33
5833333.33
5833333.33
5833333.33
5833333.33
5833333.33
5833333.37
27000000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
541666.67
541666.67
541666.67
541666.67
541666.67
541666.67
541666.67
541666.67
541666.67
541666.67
541666.67
541666.63
5000000.00
5000000.00
5000000.00
5000000.00
5000000.00
5000000.00
5000000.00
5000000.00
5000000.00
5000000.00
5000000.00
5000000.00
8333333.33
8333333.33
8333333.33
8333333.33
8333333.33
8333333.33
8333333.33
8333333.33
8333333.33
8333333.33
8333333.33
8333333.37
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.63
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.67
4166666.63
2791666.67
2791666.67
2791666.67
2791666.67
2791666.67
2791666.67
2791666.67
2791666.67
2791666.67
2791666.67
2791666.67
2791666.63
48000000Total Commitment in Second Quarter of 2018
International Development Association
252000000Total Commitment in Second Quarter of 2018
International Bank for Reconstruction and Development
120000Total Disbursement in First Quarter of 2019
International Development Association
-120000Total Interest Repayment in First Quarter of 2019
International Development Association
630000Total Disbursement in First Quarter of 2019
International Bank for Reconstruction and Development
-630000Total Interest Repayment in First Quarter of 2019
International Bank for Reconstruction and Development
2500000Total Disbursement in Second Quarter of 2019
International Development Association
500000Total Disbursement in Second Quarter of 2019
International Bank for Reconstruction and Development
3500000Total Disbursement in Second Quarter of 2019
International Bank for Reconstruction and Development
2500000Total Disbursement in Third Quarter of 2019
International Bank for Reconstruction and Development
-112224Total Interest Repayment in Fourth Quarter of 2019
International Development Association
-478233Total Interest Repayment in Fourth Quarter of 2019
International Bank for Reconstruction and Development
18796640Total Disbursement in First Quarter of 2020
International Bank for Reconstruction and Development
-101807Total Interest Repayment in Second Quarter of 2020
International Development Association
5809074Total Disbursement in Second Quarter of 2020
International Bank for Reconstruction and Development
11943652Total Disbursement in Second Quarter of 2020
International Bank for Reconstruction and Development
-433939Total Interest Repayment in Second Quarter of 2020
International Bank for Reconstruction and Development
Project Appraisal DocumentProject Appraisal Document Implementation Status and Results ReportLoan AgreementAgreementAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Schedule 2, Section I.A. The Borrower/Recipient shall cause AISEM to be headed by a General Director, and staffed with adequateprofessional, fiduciary, administrative and technical personnel (including social and environmental specialists), all withqualifications, experience and terms of employment acceptable to the Bank, as set forth in the AISEM Operational Manual.
Schedule 2, Section I.A. The Borrower/Recipient, through MOH, shall ensure that the UGESPRO PIU is staffed with adequateprofessional, fiduciary, administrative and technical personnel (including social and environmental specialists), all withqualifications, experience and terms of employment acceptable to the Bank, as set forth in the Operational Manual.
Schedule 2, Section I.A. The Borrower/Recipient, through MOH, shall not later than a hundred and twenty (120) days after EffectiveDate, ensure that a procurement specialist, financial management specialist and a disbursement specialist are hired to work fulltime within the UGESPRO PIU, all under terms of reference acceptable to the Bank/Association.
Not later than 15 days after the countersignature of the Amendment the Borrower/Recipient shall update and disclose the ESMF withnew chapter with an specific ESMF for Part 4 of the Project and update the Op. Manuals to include modifications under Part 4 of theProject. No civil works shall be carried out under Part 4 until the ESMF has been updated and disclosed acceptable to theBank/Association
Schedule 2, Section I.A. The Borrower/Recipient shall cause AISEM to maintain, throughout Project implementation, a structure, withfunctions and responsibilities acceptable to the Bank, as set forth in the AISEM Operational Manual, including inter alia, theresponsibility to implement, monitor and supervise the carrying out of Parts 1, 3 and 4.2 of the Project.
Schedule 2, Section I.A. The Borrower/Recipient, through MOH, shall establish, and thereafter operate and maintain, throughoutProject implementation, a unit within MOH (UGESPRO PIU), with structure and responsibilities acceptable to the Bank, as set forthin the Operational Manual, including inter alia, the responsibility to implement monitor and supervise the carrying out of Parts 2,3 and 4.1.
Schedule 2, Section II. MoH and AISEM shall furnish to the WBG the Project Reports not later than 45 days after the end of eachcalendar semester covering the calendar semester. Except as otherwise required or permitted or requested by the WBG, in sharingany information, report or document related to the activities, the Bank/Association shall ensure they do not include Personal Data.
PDO Indicator
Network referral centers operational with at least 60% of the required medical staff and providing health services
Intermediate Results Indicator
New hospitals equipped
Intermediate Results Indicator
Medical specialists enrolled in residency program supported by the project
Intermediate Results Indicator
Number of health facilities equiped to improve response to COVID-19 outbreak
PDO Indicator
Health facilities supported in the targeted networks fulfill the licensing standards
Intermediate Results Indicator
New hospitals that do not use incineration to treat hospital waste in the targeted networks
Intermediate Results Indicator
Health facility managers and administrators trained
Intermediate Results Indicator
Number of regional laboratories equiped to improve response to COVID-19 outbreak
PDO Indicator
Doctors checking the MoH clinical guidelines application at least once in the last 60 days
Intermediate Results Indicator
Grievance Redress Mechanism (GRM) designed and operational available to attend in indigenous languages of the region
Intermediate Results Indicator
Patients reporting being satisfied with health services provided in the targeted networks desagregated by gender (including LGBTI) and self- ethnic identification
PDO Indicator
Number of diagnosed cases treated per approved protocol
Intermediate Results Indicator
Facilities in the targeted networks using quality checklists
Intermediate Results Indicator
Number clinical guidelines updated or developed
Intermediate Results Indicator
Female patients reporting being satisfied with health services provided in the targeted networks
44000-P127743
World Bank
Rural Alliances Project II
International Development Association
MINISTRY OF RURAL DEVELOPMENT AND LAND
International Development Association
MINISTRY OF RURAL DEVELOPMENT AND LANDPlanned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Luz Berania Diaz Rios
+1-202-473-1000ldiazrios@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
Departamento de Tarija
-21.5000 -64.0000
Departamento de Santa Cruz
-17.5000 -61.5000
Departamento de Potosi
-20.6670 -67.0000
Departamento de Pando
-11.3330 -67.6670
Departamento de Oruro
-18.6670 -67.5000
Departamento de La Paz
-15.5000 -68.0000
Departamento de Cochabamba
-17.5000 -65.6670
Departamento de Chuquisaca
-20.0000 -64.3330
El Beni
-14.0000 -65.5000
Other Agriculture, Fishing and ForestryAgricultural markets, commercialization and agri-businessOther Energy and ExtractivesRural and Inter-Urban RoadsOther Water Supply, Sanitation and Waste ManagementAgriculture FinanceRural MarketsSocial InclusionFinance for DevelopmentRural Infrastructure and service deliveryJobsIndigenous People and Ethnic MinoritiesRural DevelopmentGender
0.00
0.00
0.00
0.00
0.00
0.00
266666.66
266666.67
266666.67
266666.66
266666.67
266666.67
266666.66
266666.67
266666.67
633333.33
633333.33
633333.34
633333.33
633333.33
633333.34
633333.33
633333.33
633333.34
633333.33
633333.33
633333.34
1266666.66
1266666.67
1266666.67
1266666.66
1266666.67
1266666.67
1266666.66
1266666.67
1266666.67
1266666.66
1266666.67
1266666.67
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1333333.33
1333333.33
1333333.34
933333.33
933333.33
933333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
180576.22
180576.22
180576.22
180576.22
180576.22
180576.22
180576.22
180576.22
180576.22
180576.22
180576.22
180576.22
1010547.28
1010547.28
1010547.28
1010547.28
1010547.28
1010547.28
1010547.28
1010547.28
1010547.28
1010547.28
1010547.28
1010547.29
1057490.86
1057490.86
1057490.86
1057490.86
1057490.86
1057490.86
1057490.86
1057490.86
1057490.86
1057490.86
1057490.86
1057490.86
1349611.80
1349611.80
1349611.80
1349611.80
1349611.80
1349611.80
1349611.80
1349611.80
1349611.80
1349611.80
1349611.80
1349611.75
661647.48
661647.48
661647.48
661647.48
661647.48
661647.48
661647.48
661647.48
661647.48
661647.48
661647.48
661647.52
2811283.58
2811283.58
2811283.58
2811283.58
2811283.58
2811283.58
2811283.58
2811283.58
2811283.58
2811283.58
2811283.58
2811283.62
2916666.67
2916666.67
2916666.67
2916666.67
2916666.67
2916666.67
2916666.67
2916666.67
2916666.67
2916666.67
2916666.67
2916666.63
1909903.33
1909903.33
1909903.33
1909903.33
1909903.33
1909903.33
1909903.33
1909903.33
1909903.33
1909903.33
1909903.33
1909903.37
619151.40
619151.40
619151.40
619151.40
619151.40
50000000Total Commitment in Fourth Quarter of 2012
International Development Association1000000Total Disbursement in Third Quarter of 2013
International Development Association467921Total Disbursement in Fourth Quarter of 2013
International Development Association-8739Total Interest Repayment in First Quarter of 2014
International Development Association698994Total Disbursement in Second Quarter of 2014
International Development Association1273675Total Disbursement in Third Quarter of 2014
International Development Association-20288Total Interest Repayment in Third Quarter of 2014
International Development Association1419369Total Disbursement in Fourth Quarter of 2014
International Development Association2342679Total Disbursement in Fourth Quarter of 2014
International Development Association1352959Total Disbursement in First Quarter of 2015
International Development Association1853036Total Disbursement in First Quarter of 2015
International Development Association-44010Total Interest Repayment in First Quarter of 2015
International Development Association1570033Total Disbursement in Second Quarter of 2015
International Development Association2314818Total Disbursement in Second Quarter of 2015
International Development Association1669428Total Disbursement in Third Quarter of 2015
International Development Association1673243Total Disbursement in Third Quarter of 2015
International Development Association-109803Total Interest Repayment in Third Quarter of 2015
International Development Association1282946Total Disbursement in Fourth Quarter of 2015
International Development Association4257124Total Disbursement in Fourth Quarter of 2015
International Development Association1709929Total Disbursement in First Quarter of 2016
International Development Association-192521Total Interest Repayment in First Quarter of 2016
International Development Association882775Total Disbursement in Second Quarter of 2016
International Development Association1214445Total Disbursement in Second Quarter of 2016
International Development Association783169Total Disbursement in Third Quarter of 2016
International Development Association1317886Total Disbursement in Third Quarter of 2016
International Development Association2468888Total Disbursement in Third Quarter of 2016
International Development Association-266391Total Interest Repayment in Third Quarter of 2016
International Development Association1119027Total Disbursement in Fourth Quarter of 2016
International Development Association2300000Total Disbursement in Fourth Quarter of 2016
International Development Association2619463Total Disbursement in Fourth Quarter of 2016
International Development Association2098981Total Disbursement in First Quarter of 2017
International Development Association-323660Total Interest Repayment in First Quarter of 2017
International Development Association1487464Total Disbursement in Second Quarter of 2017
International Development Association2000464Total Disbursement in Second Quarter of 2017
International Development Association100000000Total Commitment in Second Quarter of 2017
International Bank for Reconstruction and Development1739797Total Disbursement in Third Quarter of 2017
International Development Association-411626Total Interest Repayment in Third Quarter of 2017
International Development Association1200000Total Disbursement in Fourth Quarter of 2017
International Development Association-437493Total Interest Repayment in First Quarter of 2018
International Development Association-791796Total Loan Repayment in First Quarter of 2018
International Development Association250000Total Disbursement in First Quarter of 2018
International Bank for Reconstruction and Development-250000Total Interest Repayment in First Quarter of 2018
International Bank for Reconstruction and Development2000000Total Disbursement in Second Quarter of 2018
International Bank for Reconstruction and Development3000000Total Disbursement in Second Quarter of 2018
International Bank for Reconstruction and Development56713Total Disbursement in Third Quarter of 2018
International Development Association-487699Total Interest Repayment in Third Quarter of 2018
International Development Association-750968Total Loan Repayment in Third Quarter of 2018
International Development Association-238433Total Interest Repayment in Third Quarter of 2018
International Bank for Reconstruction and Development-33598Total Commitment Cancellations in Fourth Quarter of 2018
International Development Association228648Total Disbursement in Fourth Quarter of 2018
International Bank for Reconstruction and Development-434269Total Interest Repayment in First Quarter of 2019
International Development Association-752124Total Loan Repayment in First Quarter of 2019
International Development Association-239402Total Interest Repayment in First Quarter of 2019
International Bank for Reconstruction and Development2032608Total Disbursement in Second Quarter of 2019
International Bank for Reconstruction and Development-435927Total Interest Repayment in Third Quarter of 2019
International Development Association-745518Total Loan Repayment in Third Quarter of 2019
International Development Association2823925Total Disbursement in Third Quarter of 2019
International Bank for Reconstruction and Development-253410Total Interest Repayment in Third Quarter of 2019
International Bank for Reconstruction and Development1535172Total Disbursement in Fourth Quarter of 2019
International Bank for Reconstruction and Development1739892Total Disbursement in Fourth Quarter of 2019
International Bank for Reconstruction and Development2538826Total Disbursement in Fourth Quarter of 2019
International Bank for Reconstruction and Development-419896Total Interest Repayment in First Quarter of 2020
International Development Association-741786Total Loan Repayment in First Quarter of 2020
International Development Association839667Total Disbursement in First Quarter of 2020
International Bank for Reconstruction and Development2295485Total Disbursement in First Quarter of 2020
International Bank for Reconstruction and Development2976053Total Disbursement in First Quarter of 2020
International Bank for Reconstruction and Development-330707Total Interest Repayment in First Quarter of 2020
International Bank for Reconstruction and DevelopmentProject Information DocumentProject Information DocumentProject Information DocumentProject Appraisal DocumentProject Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportLoan AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Finance Agreement :Complete the staffing of the ROUs in a manner acceptable to the Association | Description :Complete selection ofkey personnel in Regional Operating units in accordance to procedures and requirements included in the Project Operational Manual.| Due Date :31-Oct-2013
Finance Agreement :Maintain EMPODERAR (NCU and ROUs) in a manner acceptable to the Association | Description :Maintain, throughoutProject implementation: (i) within MDRyT, a unit with operational autonomy (“Unidad Desconcentrada EMPODERAR” or “EMPODERAR”);and(ii) within EMPODERAR, a national coordination unit (NCU) and, in each of the Selected Areas, a regional operation unit (ROU),all with structure, functions and responsibilities acceptable to the Association and set forth in the OM | Frequency :Yearly
Finance Agreement :Staffing of EMPODERAR's NCU in a manner acceptable to the Association | Description :Ensure that the NCU is,throughout Project implementation, headed by a Project manager, and that each ROU is headed by a regional coordinator, all staffedwith adequate professional, fiduciary, administrative and technical personnel (including procurement and financial specialists),with qualifications, experience and terms of employment acceptable to the Association, as set forth in the OM | Frequency :Yearly
Finance Agreement :Land acquisition shall not be financed out of the proceeds of the Credit | Description :The Recipient undertakesthat the proceeds of the Financing shall not be used to finance land acquisition in any of the Selected Areas. If the Association,at any time, determines that an amount of the Financing was used to make a payment for such land acquisition, the Recipient shallpromptly, upon notice by the Association, refund an amount equal to the amount of such payment to the Association. | Frequency:Yearly
PDO Indicator
Increase in the average volume of sales of the product(s) involved in the alliances
PDO Indicator
Producer organizations that maintain or improve their commercial relations (alliances) for at least two productive cycles
PDO Indicator
Members of beneficiary SPOs that apply improved technologies/practices as defined in the business plans
PDO Indicator
Direct project beneficiaries
PDO Indicator
Female beneficiaries
PDO Indicator
Beneficiaries of public investment subprojects (there is no disaggregation) (households)
Intermediate Results Indicator
1.1 Producer organizations that receive assistance to be formalized
Intermediate Results Indicator
2.1 Business Plans of supported alliances that are dully implemented.
Intermediate Results Indicator
3.1. Management Geo-referencing Information System improved and operating
Intermediate Results Indicator
1.2 Alliances with signed financial agreement for project support
Intermediate Results Indicator
2.2 Supported alliances that fulfill their commercial aims in the framework of agreed arrangements
Intermediate Results Indicator
3.2. Project's Public Information System installed and operating
Intermediate Results Indicator
1.3 SPOs that receive training and support for organization strengthening
Intermediate Results Indicator
2.3 Producer organizations that obtain positive net incremental real income from Alliance product(s)
Intermediate Results Indicator
3.2.1. Grievances responded within the stipulated service standards for response times
Intermediate Results Indicator
1.4. Service providers to SPOs that benefit from capacity building to improve their knowledge
Intermediate Results Indicator
2.4 Producer organizations whose leaders are periodically accountable to their members
Intermediate Results Indicator
3.2.2. Members of beneficiary SPOs that expressed satisfaction with the support provided by the Project, via alliances
Intermediate Results Indicator
2.5 Executed public investment subprojects
Intermediate Results Indicator
3.3. Collaborative/strategic partnerships with public and private institutions established
Intermediate Results Indicator
Female Service Providers to SPOs that benefit from capacity building to improve their knowledge
Intermediate Results Indicator
2.6 Alliances that apply environmental measures satisfactorily
Intermediate Results Indicator
2.7 Area provided with improved irrigation investments
44000-P122007
World Bank
National Roads and Airport Infrastructure Project
International Development Association
ADMINISTRADORA BOLIVIANA DE CARRETERAS Y
International Development Association
ADMINISTRADORA BOLIVIANA DE CARRETERAS YPlanned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Felipe Targa Rodriguez
+1-202-473-1000ftarga@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
Departamento de La Paz
-15.5000 -68.0000
Tumupasa
-14.1500 -67.9170
Rurrenabaque
-14.4410 -67.5280
Ixiamas
-13.7500 -68.1500
San Buenaventura
-14.4350 -67.5410
Sadiri
-14.1670 -67.9330
Rural and Inter-Urban RoadsAviationRural Infrastructure and service deliveryRural Development
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
3333333.33
3333333.33
3333333.34
1333333.33
1333333.33
1333333.34
666666.67
666666.67
666666.66
1333333.33
1333333.33
1333333.34
4000000.00
4000000.00
4000000.00
2333333.33
2333333.33
2333333.34
2333333.33
2333333.33
2333333.34
2333333.33
2333333.33
2333333.34
3000000.00
3000000.00
3000000.00
2500000.00
2500000.00
2500000.00
2500000.00
2500000.00
2500000.00
1666666.67
1666666.67
1666666.66
1666666.67
1666666.67
1666666.66
1000000.00
1000000.00
1000000.00
2000000.00
2000000.00
2000000.00
1000000.00
1000000.00
1000000.00
666666.67
666666.67
666666.66
1500000.00
1500000.00
1500000.00
1333333.33
1333333.33
1333333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
366328.33
366328.33
366328.34
87963.05
87963.05
87963.06
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
164821.42
164821.42
164821.43
0.00
0.00
0.00
0.00
0.00
0.00
5823582.99
5823582.99
5823583.00
3308967.99
3308967.99
3308967.99
1101054.51
1101054.51
1101054.52
2187317.23
2187317.23
2187317.23
1145958.44
1145958.44
1145958.43
2230804.21
2230804.21
2230804.22
0.00
0.00
0.00
41666.67
41666.67
41666.66
25517.00
25517.00
25517.00
303486.44
303486.44
303486.45
0.00
0.00
0.00
309579.10
309579.10
309579.10
203167.95
203167.95
203167.94
20815.00
20815.00
20815.01
203118.88
203118.88
203118.89
0.00
0.00
0.00
173738.14
173738.14
173738.15
62120.37
62120.37
62120.37
376950.67
376950.67
376950.66
565426.33
565426.33
565426.34
1319328.00
1319328.00
1319328.00
1319328.00
1319328.00
1319328.00
282713.00
282713.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
109500000Total Commitment in Second Quarter of 2011
International Development Association1098985Total Disbursement in Fourth Quarter of 2013
International Development Association263889Total Disbursement in First Quarter of 2014
International Development Association-5276Total Interest Repayment in Second Quarter of 2014
International Development Association-4858Total Interest Repayment in Fourth Quarter of 2014
International Development Association494464Total Disbursement in First Quarter of 2015
International Development Association-5420Total Interest Repayment in Second Quarter of 2015
International Development Association17470749Total Disbursement in Fourth Quarter of 2015
International Development Association-6430Total Interest Repayment in Fourth Quarter of 2015
International Development Association9926904Total Disbursement in First Quarter of 2016
International Development Association3303164Total Disbursement in Second Quarter of 2016
International Development Association-83140Total Interest Repayment in Second Quarter of 2016
International Development Association3173681Total Disbursement in Third Quarter of 2016
International Development Association3388271Total Disbursement in Third Quarter of 2016
International Development Association3437875Total Disbursement in Fourth Quarter of 2016
International Development Association-129341Total Interest Repayment in Fourth Quarter of 2016
International Development Association1651160Total Disbursement in First Quarter of 2017
International Development Association1687603Total Disbursement in First Quarter of 2017
International Development Association3353650Total Disbursement in First Quarter of 2017
International Development Association-171128Total Interest Repayment in Second Quarter of 2017
International Development Association125000Total Disbursement in Third Quarter of 2017
International Development Association76551Total Disbursement in Fourth Quarter of 2017
International Development Association-191791Total Interest Repayment in Fourth Quarter of 2017
International Development Association910459Total Disbursement in First Quarter of 2018
International Development Association-191412Total Interest Repayment in Second Quarter of 2018
International Development Association22613Total Disbursement in Third Quarter of 2018
International Development Association52452Total Disbursement in Third Quarter of 2018
International Development Association853673Total Disbursement in Third Quarter of 2018
International Development Association109504Total Disbursement in Fourth Quarter of 2018
International Development Association500000Total Disbursement in Fourth Quarter of 2018
International Development Association-189723Total Interest Repayment in Fourth Quarter of 2018
International Development Association62445Total Disbursement in First Quarter of 2019
International Development Association76551Total Disbursement in Second Quarter of 2019
International Development Association532806Total Disbursement in Second Quarter of 2019
International Development Association-193273Total Interest Repayment in Second Quarter of 2019
International Development Association521214Total Disbursement in Fourth Quarter of 2019
International Development Association-193228Total Interest Repayment in Fourth Quarter of 2019
International Development Association186361Total Disbursement in First Quarter of 2020
International Development Association-2887728Total Disbursement in Second Quarter of 2020
International Development Association209065Total Disbursement in Second Quarter of 2020
International Development AssociationProject Information DocumentProject Information DocumentProject Information DocumentProject Information DocumentProject Appraisal DocumentProject Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportFinancing AgreementContract AwardsProject URLProcurement Notices
Finance Agreement :Article V, Paragraph 5.01 (a) | Description :the ABC Subsidiary Agreement and the AASANA Subsidiary Agreementhave been executed on behalf of the parties thereto | Due Date :17-Oct-2011
Finance Agreement :Article V, Paragraph 5.01 (b) | Description :the ABC Operational Manual and the AASANA Operational Manual havebeen adopted by both agencies, all in a manner acceptable for theAssociation | Due Date :17-Oct-2011
Finance Agreement :Achedule 2, Section I, Paragraph A(b) (i) | Description :The recipient shall cause ABC and AASANA to ensure thata team of dedicated professionals is established and maintained throughout project implementation | Frequency :Yearly
Finance Agreement :Schedule 2, Section I, Paragraph B(a) (b) and (c) | Description :The recipient shall cause ABC and AASANA tocarry out the project in accordance with (i) IPP, (ii) Resettlement Plan, and (iii) Environmental Management Plans | Frequency:Yearly
Finance Agreement :Schedule 2, Section I, Paragraph C.3 | Description :The Recipient shall ensure that the runway of the airport isregularly maintained and continues to be operational throughout project implementation | Frequency :Yearly
Finance Agreement :Schedule 2, Section I, Paragraph C.4 | Description :The Recipient shall ensure that sufficient funds areallocated for component 3; and that ABT, SERNAP and VIAS BOLIVIA provide technical contributions for component 3(b) | Frequency:Yearly
Finance Agreement :Schedule 2, Section I, Paragraph C.5 | Description :The Recipient shall create and maintain operational aparticipatory working group for the sustainable development of the area economically benefiting from the project | Frequency :Yearly
PDO Indicator
Reduce the transport costs to the San Buenaventura - Ixiamas road users, including vehicle operating costs and monetary value of travel time
PDO Indicator
Increase the number of inbound and outbound flights actually operated at the Rurrenabaque Airport as per the published schedule, inpercentage of the total scheduled flights
PDO Indicator
Vehicle Operating Costs- Car (US$/veh-km)
PDO Indicator
Vehicle Operating Costs- Pick-Up (US$/veh-km)
PDO Indicator
Vehicle Operating Costs- Bus (US$/veh-km)
PDO Indicator
Vehicle Operating Costs -Trailer Truck (US$/veh-km)
PDO Indicator
Vehicle Operating Costs- Large Truck (US$/veh-km)
PDO Indicator
Vehicle Operating Costs -Medium truck (US$/veh-km)
Intermediate Results Indicator
Passenger terminal, control tower, taxiway and apron completed
Intermediate Results Indicator
ABC has and operates under a unique and reliable source of information
Intermediate Results Indicator
Roads rehablitated
Intermediate Results Indicator
Roads rehabilitated - rural
Intermediate Results Indicator
Average cruise speed for different kind of vehicles
Intermediate Results Indicator
Car
Intermediate Results Indicator
Pick-Up
Intermediate Results Indicator
Bus
Intermediate Results Indicator
Trailer Truck
Intermediate Results Indicator
Large Truck
Intermediate Results Indicator
Medium Truck
44000-P106449
World Bank
Emergency Recovery and Disaster Management
International Development Association
MINISTRY OF FINANCE
International Development Association
MINISTRY OF FINANCEPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Armando Eduardo Guzman Escobar
+1-202-473-1000aguzman3@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BOLIVIA, PLURINATIONAL STATE OF
La Santisima Trinidad
-14.8330 -64.9000
Tarija
-21.5350 -64.7300
Santa Cruz de la Sierra
-17.7860 -63.1810
Potosi
-19.5840 -65.7530
Oruro
-17.9830 -67.1500
Cochabamba
-17.3900 -66.1570
Cobija
-11.0270 -68.7690
Sucre
-19.0330 -65.2630
La Paz
-16.5000 -68.1500
Housing ConstructionCentral Government (Central Agencies)Sub-National GovernmentOther Water Supply, Sanitation and Waste ManagementRural and Inter-Urban RoadsDisaster Risk ReductionUrban DevelopmentDisaster Response and RecoveryDisaster Risk FinanceUrban Infrastructure and Service DeliveryDisaster Risk ManagementFinance for DevelopmentDisaster Preparedness
166666.66
166666.67
166666.67
333333.33
333333.33
333333.34
333333.33
333333.33
333333.34
0.00
0.00
0.00
166666.66
166666.67
166666.67
333333.33
333333.33
333333.34
333333.33
333333.33
333333.34
333333.33
333333.33
333333.34
333333.33
333333.33
333333.34
333333.33
333333.33
333333.34
333333.33
333333.33
333333.34
333333.33
333333.33
333333.34
333333.33
333333.33
333333.34
333333.33
333333.33
333333.34
166666.66
166666.67
166666.67
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
167097.22
167097.22
167097.23
227095.83
227095.83
227095.83
422090.17
422090.17
422090.17
231711.17
231711.17
231711.17
91525.72
91525.72
91525.72
0.00
0.00
0.00
378965.11
378965.12
378965.12
0.00
0.00
0.00
295423.83
295423.83
295423.83
135593.89
135593.89
135593.89
136113.17
136113.17
136113.18
117855.93
117855.94
117855.94
25418.78
25418.78
25418.79
0.00
0.00
0.00
89129.64
89129.64
89129.65
174689.66
174689.67
174689.67
43756.12
43756.12
43756.13
365052.50
365052.50
365052.51
621346.20
621346.20
621346.20
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
12500000Total Commitment in Fourth Quarter of 2007
International Development Association4400000Total Commitment in Second Quarter of 2008
International Development Association501292Total Disbursement in First Quarter of 2009
International Development Association62900Total Disbursement in Second Quarter of 2009
International Development Association300000Total Disbursement in Second Quarter of 2009
International Development Association318387Total Disbursement in Second Quarter of 2009
International Development Association414769Total Disbursement in Third Quarter of 2009
International Development Association851501Total Disbursement in Third Quarter of 2009
International Development Association-8101Total Interest Repayment in Third Quarter of 2009
International Development Association315376Total Disbursement in Fourth Quarter of 2009
International Development Association379757Total Disbursement in Fourth Quarter of 2009
International Development Association50000Total Disbursement in First Quarter of 2010
International Development Association224577Total Disbursement in First Quarter of 2010
International Development Association-9771Total Interest Repayment in First Quarter of 2010
International Development Association336895Total Disbursement in Third Quarter of 2010
International Development Association-11992Total Interest Repayment in Third Quarter of 2010
International Development Association800000Total Disbursement in Third Quarter of 2010
International Development Association413951Total Disbursement in First Quarter of 2011
International Development Association-14158Total Interest Repayment in First Quarter of 2011
International Development Association472320Total Disbursement in First Quarter of 2011
International Development Association-2924Total Interest Repayment in First Quarter of 2011
International Development Association406782Total Disbursement in Second Quarter of 2011
International Development Association-15875Total Interest Repayment in Third Quarter of 2011
International Development Association408340Total Disbursement in Third Quarter of 2011
International Development Association-5765Total Interest Repayment in Third Quarter of 2011
International Development Association61414Total Disbursement in Fourth Quarter of 2011
International Development Association292154Total Disbursement in Fourth Quarter of 2011
International Development Association76256Total Disbursement in First Quarter of 2012
International Development Association-15734Total Interest Repayment in First Quarter of 2012
International Development Association-8660Total Interest Repayment in First Quarter of 2012
International Development Association-15758Total Interest Repayment in Third Quarter of 2012
International Development Association267389Total Disbursement in Third Quarter of 2012
International Development Association-8687Total Interest Repayment in Third Quarter of 2012
International Development Association-6061239Total Commitment Cancellations in Fourth Quarter of 2012
International Development Association524069Total Disbursement in Fourth Quarter of 2012
International Development Association32090Total Disbursement in First Quarter of 2013
International Development Association149178Total Disbursement in First Quarter of 2013
International Development Association-15992Total Interest Repayment in First Quarter of 2013
International Development Association-10824Total Interest Repayment in First Quarter of 2013
International Development Association146997Total Disbursement in Second Quarter of 2013
International Development Association434672Total Disbursement in Second Quarter of 2013
International Development Association135339Total Disbursement in Third Quarter of 2013
International Development Association-16548Total Interest Repayment in Third Quarter of 2013
International Development Association-11715Total Interest Repayment in Third Quarter of 2013
International Development Association-865024Total Commitment Cancellations in Fourth Quarter of 2013
International Development Association64043Total Disbursement in Fourth Quarter of 2013
International Development Association309141Total Disbursement in Fourth Quarter of 2013
International Development Association-163096Total Commitment Cancellations in Fourth Quarter of 2013
International Development Association124943Total Disbursement in Fourth Quarter of 2013
International Development Association-94988Total Disbursement in First Quarter of 2014
International Development Association127129Total Disbursement in First Quarter of 2014
International Development Association-18364Total Interest Repayment in First Quarter of 2014
International Development Association-58211Total Disbursement in First Quarter of 2014
International Development Association-13922Total Interest Repayment in First Quarter of 2014
International Development Association-330364Total Commitment Cancellations in Second Quarter of 2014
International Development Association-219301Total Commitment Cancellations in Third Quarter of 2014
International Development Association-19502Total Interest Repayment in Third Quarter of 2014
International Development Association-13879Total Interest Repayment in Third Quarter of 2014
International Development Association-17770Total Interest Repayment in First Quarter of 2015
International Development Association-12621Total Interest Repayment in First Quarter of 2015
International Development Association-17621Total Interest Repayment in Third Quarter of 2015
International Development Association-12515Total Interest Repayment in Third Quarter of 2015
International Development Association-531Total Commitment Cancellations in Fourth Quarter of 2015
International Development Association-531Total Disbursement in Fourth Quarter of 2015
International Development Association-17496Total Interest Repayment in First Quarter of 2016
International Development Association-12428Total Interest Repayment in First Quarter of 2016
International Development Association-17667Total Interest Repayment in Third Quarter of 2016
International Development Association-12549Total Interest Repayment in Third Quarter of 2016
International Development Association-16817Total Interest Repayment in First Quarter of 2017
International Development Association-11946Total Interest Repayment in First Quarter of 2017
International Development Association-17480Total Interest Repayment in Third Quarter of 2017
International Development Association-12417Total Interest Repayment in Third Quarter of 2017
International Development Association-16206Total Interest Repayment in First Quarter of 2018
International Development Association-61028Total Loan Repayment in First Quarter of 2018
International Development Association-12835Total Interest Repayment in First Quarter of 2018
International Development Association-19454Total Interest Repayment in Third Quarter of 2018
International Development Association-57882Total Loan Repayment in Third Quarter of 2018
International Development Association-12718Total Interest Repayment in Third Quarter of 2018
International Development Association-41115Total Loan Repayment in Third Quarter of 2018
International Development Association-16560Total Interest Repayment in First Quarter of 2019
International Development Association-58015Total Loan Repayment in First Quarter of 2019
International Development Association-11916Total Interest Repayment in First Quarter of 2019
International Development Association-41210Total Loan Repayment in First Quarter of 2019
International Development Association-17011Total Interest Repayment in Third Quarter of 2019
International Development Association-57505Total Loan Repayment in Third Quarter of 2019
International Development Association-12238Total Interest Repayment in Third Quarter of 2019
International Development Association-40848Total Loan Repayment in Third Quarter of 2019
International Development Association-16307Total Interest Repayment in First Quarter of 2020
International Development Association-57218Total Loan Repayment in First Quarter of 2020
International Development Association-11736Total Interest Repayment in First Quarter of 2020
International Development Association-40644Total Loan Repayment in First Quarter of 2020
International Development AssociationProject Information DocumentImplementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementFinancing AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
The Subsidiary Agreement has been executed on behalf of the Recipient and FPS
The Operation Manual has been adopted in a manner satisfactory to the Association
Intermediate Results Indicator
Recommendations for a National Risk Management System submitted to the MPD for consideration.
A National Program on DRM has been submitted to MPD.
Intermediate Results Indicator
Percentage of trainees in the 9 target sectors obtaining more than 75% in skills tests post training in risk prevention and vulnerability reduction.
The remaining participants are being trained through VIDECI's program Educate 2.
Intermediate Results Indicator
Level of acceptance and participation of the community regarding the works executed.
The level of acceptance for works continues high in all communities, according to FPS.
PDO Indicator
Number of infrastructure facilities restored and number of beneficiaries.
The implementation of the remaining subprojects is on schedule.
PDO Indicator
Disaster Risk Management Units established in 9 target sectors and 9 departments; staff trained; staff of units fully paid by respective entities; submission by all 9 sectors of sectoral risk Mgmt.
Intermediate Results Indicator
Roads rehabilitated, Rural
The portfolio of civil works was adjusted over time based on actual needs. Thus, the end target has been exceeded.