44000-P100332
World Bank
Bhutan Second Rural Access Project
International Development Association
DEPARTMENT OF ROADS
International Development Association
DEPARTMENT OF ROADSPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
A.K. Farhad Ahmed
+1-202-473-1000fahmed8@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BHUTAN
Lhuentse Dzongkhag
27.7500 91.1830
Zhemgang Dzongkhag
27.0830 90.8500
Trashigang Dzongkhag
27.2500 91.7500
Wangdue Phodrang Dzongkhag
27.5000 90.1330
Trashi Yangste
27.5850 91.4550
Dangchu
27.5530 90.2110
Tsangkha
27.0280 90.0490
Lajab
27.0900 90.0140
Drukgyegang
26.9790 90.0290
Khar
26.9410 91.3900
Chongshing
27.0010 91.3580
Yurung
27.0440 91.3450
Ritang
27.5500 90.1670
Khar
27.0000 91.3500
Central Government (Central Agencies)Rural and Inter-Urban RoadsPublic AdministrationAdministrative and Civil Service ReformRural Infrastructure and service deliveryRural Development
0.00
0.00
0.00
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
0.00
0.00
0.00
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
10000000Total Commitment in Second Quarter of 2007
International Development Association2481940Total Disbursement in Second Quarter of 2007
International Development Association767927Total Disbursement in Second Quarter of 2008
International Development Association318767Total Disbursement in Fourth Quarter of 2008
International Development Association550236Total Disbursement in First Quarter of 2009
International Development Association653693Total Disbursement in First Quarter of 2009
International Development Association178288Total Disbursement in Third Quarter of 2009
International Development Association424156Total Disbursement in Fourth Quarter of 2009
International Development Association311479Total Disbursement in First Quarter of 2010
International Development Association911250Total Disbursement in Second Quarter of 2010
International Development Association1869847Total Disbursement in Third Quarter of 2010
International Development Association1802019Total Disbursement in Second Quarter of 2011
International Development Association-147Total Commitment Cancellations in First Quarter of 2013
International Development AssociationProject Information DocumentProject Information DocumentProject Information DocumentProject Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportFinancing AgreementContract AwardsProject URLProcurement Notices
Safeguard Compliance
Socio-economic impact monitoring study
Socio-economic impact monitoring study
MTR Review
Intermediate Results Indicator
Share of rural population with access to an all season road [% beneficiaries from Project Area (36 direct beneficiary villages (TBC) to be placed within 2 km or 30 min of walking distance to all-seaso
Intermediate Results Indicator
% of target feeder roads constructed.
Intermediate Results Indicator
% of target feeder roads improved to all-season standards.
All 3 feeder roads improved to all season standard
Intermediate Results Indicator
% of target bridges constructed
Out of 8 target bridges 7 constructed. In one case vented causeway has been constructed instead of a bridge. There was no need ofany further bridges.
Intermediate Results Indicator
% of target feeder roads maintained to all-season standards.
PDO Indicator
50% reduction in travel time of beneficiaries to key economic and social centers in the nearest town by EOP.
78% reduction achieved, as per the final socio-economic impact monitoring study report (May 2012)
PDO Indicator
50% reduction in transportation costs of goods and supplies from/to beneficiary villages to/from the nearest town by EOP.
PDO Indicator
10% lower basic commodity prices in project villages than in unconnected villages as a result of newly constructed roads by EOP.
PDO Indicator
Overall beneficiaries' satisfaction with the improved delivery of road infrastructure.
93% satisfaction level achieved as per the final socio-economic impact monitoring study (May 2012)
Intermediate Results Indicator
Roads rehabilitated, Rural
Intermediate Results Indicator
Roads constructed, Rural
Also 15.2 km of roads were constructed with low-cost surfacing
Intermediate Results Indicator
Roads in good and fair condition as a share of total classified roads
no provision in the project to collect this.
Intermediate Results Indicator
Size of the total classified network
no provision in the project to collect this.
44000-P164290
World Bank
Strengthening Fiscal Management & Private Sector Employment
International Development Association
International Development Association
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Kenechukwu Maria Ezemenari
+1-202-473-1000kezemenari@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BHUTAN
Thimphu
27.4661 89.6419
Other Non-bank Financial InstitutionsOther Industry, Trade and ServicesOther EducationOther Energy and ExtractivesCentral Government (Central Agencies)Job CreationPublic Finance ManagementFiscal PolicyMitigationClimate changeFiscal sustainabilityJobsSkills DevelopmentGenderRural DevelopmentCredit InfrastructureEnergy EfficiencyLabor Market Policy and ProgramsPayment & markets infrastructureMSME DevelopmentEnterprise DevelopmentRural MarketsFinancial Infrastructure and AccessEnergyDomestic Revenue Administration
0.00
0.00
30000000Total Commitment in First Quarter of 2018
International Development Association29202766Total Disbursement in Second Quarter of 2018
International Development Association-43934Total Interest Repayment in Third Quarter of 2018
International Development Association-106527Total Interest Repayment in First Quarter of 2019
International Development Association-106752Total Interest Repayment in Third Quarter of 2019
International Development Association-105640Total Interest Repayment in First Quarter of 2020
International Development AssociationProject Appraisal DocumentProject Appraisal DocumentProject Information DocumentFinancing AgreementContract AwardsProject URLProcurement Notices 44000-P073458
World Bank
Bhutan Private Sector Development
International Development Association
MINISTRY OF INFORMATION & TECHNOLOGY
International Development Association
MINISTRY OF INFORMATION & TECHNOLOGYPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Cecile Thioro Niang
+1-202-473-1000cniang@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BHUTAN
Kingdom of Bhutan
27.5000 90.5000
Phuntsholing
26.8520 89.3880
Samtse
26.9130 89.0840
Kanglung
27.2900 91.5400
Thimphu
27.4660 89.6420
Other Information and Communications TechnologiesPublic Administration - Information and Communications TechnologiesOther Industry, Trade and ServicesICT ServicesOther Non-bank Financial InstitutionsOther EducationCentral Government (Central Agencies)Urban DevelopmentActive Labor Market ProgramsUrban Infrastructure and Service DeliveryJob CreationJobsInvestment and Business ClimateStandards, Curriculum and TextbooksRural DevelopmentBusiness Enabling EnvironmentRural Infrastructure and service deliveryScience and TechnologyTeachersLabor Market Policy and ProgramsAccess to EducationLabor Market InstitutionsEducation
50000.00
50000.00
50000.00
50000.00
50000.00
50000.00
66666.67
66666.67
66666.66
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
333333.33
333333.33
333333.34
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
333333.33
333333.33
333333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
50000.00
50000.00
50000.00
50000.00
50000.00
50000.00
66666.67
66666.67
66666.66
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
333333.33
333333.33
333333.34
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
333333.33
333333.33
333333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
8000000Total Commitment in Second Quarter of 2007
International Development Association150252Total Disbursement in Fourth Quarter of 2007
International Development Association1065060Total Disbursement in Second Quarter of 2008
International Development Association23028Total Disbursement in Fourth Quarter of 2008
International Development Association291798Total Disbursement in Second Quarter of 2009
International Development Association501380Total Disbursement in First Quarter of 2010
International Development Association510540Total Disbursement in Third Quarter of 2010
International Development Association468975Total Disbursement in First Quarter of 2011
International Development Association865261Total Disbursement in First Quarter of 2011
International Development Association3004554Total Disbursement in Third Quarter of 2011
International Development Association464035Total Disbursement in Fourth Quarter of 2011
International Development Association407997Total Disbursement in First Quarter of 2012
International Development Association39475Total Disbursement in Fourth Quarter of 2012
International Development Association167250Total Disbursement in Fourth Quarter of 2012
International Development Association126094Total Disbursement in First Quarter of 2013
International Development Association101557Total Disbursement in Third Quarter of 2013
International Development Association-68914Total Commitment Cancellations in Fourth Quarter of 2013
International Development Association30811Total Disbursement in Fourth Quarter of 2013
International Development AssociationProject Information DocumentProject Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportGrant or Trust Fund AgreementContract AwardsProject URLProcurement Notices
Maintain Program Steering Committee
Maintain Project Implementation Agency including designated FM and Procurement specialist
Maintain Empowered Task Force, Task force on IT Skills developmenet and Financial Sector IT Task Force
Environmental Assessment and Environmental Management Plan to be prepared within a specific deadline once the private developer ison board
Project Implementation Plan to be prepared within three months of project effectiveness
Intermediate Results Indicator
Leads generated for new investments in the IT Park
Intermediate Results Indicator
Percent of students clearing ITES industry competency assessment that is widely recognized
Intermediate Results Indicator
Percentage of students trained are successfully employed by the private sector
PDO Indicator
Cumulative job creation in theIT/ITES sector in the IT park
Intermediate Results Indicator
Number of companies successfully incubated in the IT Park
Intermediate Results Indicator
Percentage of lettable space leased out
Intermediate Results Indicator
Number of ATM financial transactions at Bank of Bhutan per year
Intermediate Results Indicator
Per cent of district coverage for financial literacy campaign
Intermediate Results Indicator
Percentage automation of stock exchange trading, settlement, and delivery with straight through processing
44000-P128201
World Bank
BT: DPC 2
International Development Association
MINISTRY OF FINANCE
International Development Association
MINISTRY OF FINANCEPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Genevieve F. Boyreau
+1-202-473-1000gboyreau@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BHUTAN
Thimphu
27.4661 89.6419
Other Industry, Trade and ServicesSub-National GovernmentOther TransportationCentral Government (Central Agencies)Disaster Response and RecoveryFinancial Sector IntegrityJobsPublic AdministrationDisaster Risk FinancePublic Expenditure ManagementBusiness Enabling EnvironmentFinance for DevelopmentDisaster Risk ManagementPublic Finance ManagementDisaster Risk ReductionDisaster PreparednessLabor Market InstitutionsFinancial Sector oversight and policy/banking regulation & restructuringActive Labor Market ProgramsRegulation and Competition PolicyLabor Market Policy and ProgramsTransparency, Accountability and Good GovernanceFinancial Stability
0.00
0.00
36000000Total Commitment in Fourth Quarter of 2012
International Development Association36841372Total Disbursement in Fourth Quarter of 2012
International Development Association-187544Total Interest Repayment in Second Quarter of 2013
International Development Association-361012Total Interest Repayment in Fourth Quarter of 2013
International Development Association-372965Total Interest Repayment in Second Quarter of 2014
International Development Association-356933Total Interest Repayment in Fourth Quarter of 2014
International Development Association-329763Total Interest Repayment in Second Quarter of 2015
International Development Association-333333Total Interest Repayment in Fourth Quarter of 2015
International Development Association-330618Total Interest Repayment in Second Quarter of 2016
International Development Association-341041Total Interest Repayment in Fourth Quarter of 2016
International Development Association-324287Total Interest Repayment in Second Quarter of 2017
International Development Association-337449Total Interest Repayment in Fourth Quarter of 2017
International Development Association-347812Total Interest Repayment in Second Quarter of 2018
International Development Association-573330Total Loan Repayment in Second Quarter of 2018
International Development Association-328087Total Interest Repayment in Fourth Quarter of 2018
International Development Association-550426Total Loan Repayment in Fourth Quarter of 2018
International Development Association-320819Total Interest Repayment in Second Quarter of 2019
International Development Association-547417Total Loan Repayment in Second Quarter of 2019
International Development Association-309409Total Interest Repayment in Fourth Quarter of 2019
International Development Association-537113Total Loan Repayment in Fourth Quarter of 2019
International Development Association-304907Total Interest Repayment in Second Quarter of 2020
International Development Association-538647Total Loan Repayment in Second Quarter of 2020
International Development AssociationProject Information DocumentProject Appraisal DocumentProject Information DocumentImplementation Completion Report ReviewFinancing AgreementContract AwardsProject URLProcurement Notices 44000-P147806
World Bank
BT: 2nd DPC Series
International Development Association
MINISTRY OF FINANCE
International Development Association
MINISTRY OF FINANCEPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Genevieve F. Boyreau
+1-202-473-1000gboyreau@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BHUTAN
Thimphu
27.4661 89.6419
Other Non-bank Financial InstitutionsServicesOther Industry, Trade and ServicesCentral Government (Central Agencies)Banking InstitutionsPublic Finance ManagementBusiness Enabling EnvironmentRegulation and Competition PolicyTax policyMSME FinanceFiscal sustainabilityEnterprise DevelopmentMSME DevelopmentFinancial Sector oversight and policy/banking regulation & restructuringDebt ManagementFiscal PolicyFinancial Infrastructure and AccessFinancial StabilityFinancial Sector IntegrityDomestic Revenue Administration
0.00
0.00
20000000Total Commitment in Second Quarter of 2015
International Development Association20068048Total Disbursement in Third Quarter of 2015
International Development Association-73671Total Interest Repayment in Fourth Quarter of 2015
International Development Association-199305Total Interest Repayment in Second Quarter of 2016
International Development Association-197369Total Interest Repayment in Fourth Quarter of 2016
International Development Association-192993Total Interest Repayment in Second Quarter of 2017
International Development Association-205111Total Interest Repayment in Fourth Quarter of 2017
International Development Association-204235Total Interest Repayment in Second Quarter of 2018
International Development Association-197579Total Interest Repayment in Fourth Quarter of 2018
International Development Association-197673Total Interest Repayment in Second Quarter of 2019
International Development Association-196363Total Interest Repayment in Fourth Quarter of 2019
International Development Association-194582Total Interest Repayment in Second Quarter of 2020
International Development AssociationProject Appraisal DocumentProject Information DocumentImplementation Completion and Results ReportImplementation Completion Report ReviewFinancing AgreementContract AwardsProject URLProcurement Notices 44000-P168166
World Bank
Strengthening Fiscal Management and Private Sector Employment Opportunities
International Development Association
International Development Association
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Kenechukwu Maria Ezemenari
+1-202-473-1000kezemenari@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BHUTAN
Thimphu
27.4661 89.6419
Other EducationCentral Government (Central Agencies)Banking InstitutionsHealthHealth Systems and PoliciesPublic Finance ManagementClimate changeMitigationPayment & markets infrastructureReproductive and Maternal HealthFinancial Infrastructure and AccessE-Government, incl. e-servicesAccess to EducationCredit InfrastructureEducationPublic AdministrationPublic Expenditure ManagementDomestic Revenue AdministrationAdaptation
0.00
0.00
30000000Total Commitment in Second Quarter of 2019
International Development Association30154971Total Disbursement in Second Quarter of 2019
International Development Association-141574Total Interest Repayment in First Quarter of 2020
International Development AssociationProject Appraisal DocumentProject Appraisal DocumentProject Information DocumentFinancing AgreementContract AwardsProject URLProcurement Notices 44000-P123820
World Bank
Remote Rural Communities Development Project
International Development Association
MINISTRY OF AGRICULTURE AND FORESTS
International Development Association
MINISTRY OF AGRICULTURE AND FORESTSPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Izabela Leao
+1-202-473-1000ileao@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BHUTAN
Chhukha Dzongkhag
27.0000 89.5500
Dagana Dzongkhag
27.1000 89.8670
Haa Dzongkhag
27.3330 89.1830
Samtse Dzongkhag
27.0330 89.0830
Trongsa Dzongkhag
27.3500 90.5330
Wangdue Phodrang Dzongkhag
27.5000 90.1330
CropsIrrigation and DrainageAgricultural markets, commercialization and agri-businessPublic Administration - Agriculture, Fishing & ForestryRural and Inter-Urban RoadsRural MarketsParticipation and Civic EngagementBiodiversityLandscape ManagementAdaptationRural Infrastructure and service deliveryAgriculture FinanceSocial InclusionFinance for DevelopmentRural DevelopmentClimate changeLand Administration and ManagementRenewable Natural Resources Asset Management
0.00
0.00
50000.00
50000.00
50000.00
50000.00
50000.00
50000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
158333.33
158333.33
158333.34
161666.66
161666.67
161666.67
208333.33
208333.33
208333.34
375000.00
375000.00
375000.00
541666.66
541666.67
541666.67
541666.66
541666.67
541666.67
240000.00
240000.00
240000.00
206666.66
206666.67
206666.67
116666.66
116666.67
116666.67
50000.00
50000.00
50000.00
50000.00
50000.00
50000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
50000.00
50000.00
50000.00
50000.00
50000.00
50000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
158333.33
158333.33
158333.34
161666.66
161666.67
161666.67
208333.33
208333.33
208333.34
375000.00
375000.00
375000.00
541666.66
541666.67
541666.67
541666.66
541666.67
541666.67
240000.00
240000.00
240000.00
206666.66
206666.67
206666.67
116666.66
116666.67
116666.67
50000.00
50000.00
50000.00
50000.00
50000.00
50000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
9000000Total Commitment in Fourth Quarter of 2012
International Development Association305892Total Disbursement in First Quarter of 2013
International Development Association385994Total Disbursement in Third Quarter of 2013
International Development Association-3806Total Interest Repayment in Fourth Quarter of 2013
International Development Association629398Total Disbursement in First Quarter of 2014
International Development Association4703982Total Disbursement in First Quarter of 2014
International Development Association-11627Total Interest Repayment in Second Quarter of 2014
International Development Association-69973Total Interest Repayment in Fourth Quarter of 2014
International Development Association-54935Total Interest Repayment in Second Quarter of 2015
International Development Association-54529Total Interest Repayment in Fourth Quarter of 2015
International Development Association-53953Total Interest Repayment in Second Quarter of 2016
International Development Association-55117Total Interest Repayment in Fourth Quarter of 2016
International Development Association779059Total Disbursement in Second Quarter of 2017
International Development Association935745Total Disbursement in Second Quarter of 2017
International Development Association-52639Total Interest Repayment in Second Quarter of 2017
International Development Association19847Total Disbursement in Fourth Quarter of 2017
International Development Association-69907Total Interest Repayment in Fourth Quarter of 2017
International Development Association-139105Total Loan Repayment in Fourth Quarter of 2017
International Development Association252119Total Disbursement in First Quarter of 2018
International Development Association949067Total Disbursement in First Quarter of 2018
International Development Association-79273Total Interest Repayment in Second Quarter of 2018
International Development Association-142028Total Loan Repayment in Second Quarter of 2018
International Development Association-269089Total Commitment Cancellations in Fourth Quarter of 2018
International Development Association-268399Total Disbursement in Fourth Quarter of 2018
International Development Association-80417Total Interest Repayment in Fourth Quarter of 2018
International Development Association-137228Total Loan Repayment in Fourth Quarter of 2018
International Development Association-76704Total Interest Repayment in Second Quarter of 2019
International Development Association-132687Total Loan Repayment in Second Quarter of 2019
International Development Association-72956Total Interest Repayment in Fourth Quarter of 2019
International Development Association-131973Total Loan Repayment in Fourth Quarter of 2019
International Development Association-74550Total Interest Repayment in Second Quarter of 2020
International Development Association-130946Total Loan Repayment in Second Quarter of 2020
International Development AssociationProject Information DocumentProject Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportContract AwardsProject URLProcurement Notices
Intermediate Results Indicator
At least 40 project chiogs with improved road access to markets
Intermediate Results Indicator
At least 50 project chiogs with improved access to marketing and community infrastructure
Intermediate Results Indicator
At least 60 percent of targeted crop area rehabilitated and is productive (Cardamom)
Intermediate Results Indicator
At least 10 new technologies developed
Intermediate Results Indicator
At least 5 best practice documents published and disseminated.
Intermediate Results Indicator
Annual geog work plans prepared through aneffective participatory process and implemented in a timely manner
Intermediate Results Indicator
Project progress reports are prepared in timely manner and of acceptable quality
Intermediate Results Indicator
Clients who have adopted an improved agr. technology promoted by the project
Intermediate Results Indicator
Roads constructed, Rural
Intermediate Results Indicator
Operational water user associations created and/or strengthened (number)
Intermediate Results Indicator
Area provided with irrigation and drainage services (ha)
PDO Indicator
Marketed value of agricultural production increased by 20 percent in target area (Million BTN)
PDO Indicator
Share of beneficiaries with access to critical community infrastructure increased by 20 percent in target area- Improved source ofdrinking water
PDO Indicator
Productivity of crops increased by at least 20 percent in targeted irrigation systems - Maize (Tons per hectare)
PDO Indicator
Productivity of crops increased by at least 20 percent in targeted irrigation systems - Paddy (Tons per hectare)
PDO Indicator
Share of beneficiaries with access to critical community infrastructure increased by 20 percent in target area - Sanitation
PDO Indicator
Direct project beneficiaries
Intermediate Results Indicator
Clients who adopted an improved agr. technology promoted by project – female
Intermediate Results Indicator
Area provided with irrigation and drainage services - New (ha)
Intermediate Results Indicator
Area provided with irrigation and drainage services - Improved (ha)
PDO Indicator
Female beneficiaries
44000-P157469
World Bank
Development Policy Credit 2: Fiscal Sustainability&Investment Climate
International Development Association
DEPARTMENT OF PUBLIC ACCOUNTS, MINISTRY OF FINANCE
International Development Association
DEPARTMENT OF PUBLIC ACCOUNTS, MINISTRY OF FINANCEPlanned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Yoichiro Ishihara
+1-202-473-1000yishihara@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BHUTAN
Thimphu
27.4661 89.6419
Other Industry, Trade and ServicesInsurance and PensionBanking InstitutionsCentral Government (Central Agencies)Other Non-bank Financial InstitutionsPublic Finance ManagementTax policyLand Administration and ManagementFiscal PolicyMSME FinanceRural DevelopmentBusiness Enabling EnvironmentCredit InfrastructurePublic Private PartnershipsPayment & markets infrastructureInvestment and Business ClimateFinancial Infrastructure and AccessDebt Management
0.00
0.00
24000000Total Commitment in Fourth Quarter of 2016
International Development Association23832725Total Disbursement in First Quarter of 2017
International Development Association-182758Total Interest Repayment in Third Quarter of 2017
International Development Association-250803Total Interest Repayment in First Quarter of 2018
International Development Association-249582Total Interest Repayment in Third Quarter of 2018
International Development Association-241323Total Interest Repayment in First Quarter of 2019
International Development Association-241833Total Interest Repayment in Third Quarter of 2019
International Development Association-239314Total Interest Repayment in First Quarter of 2020
International Development AssociationProject Appraisal DocumentProject Appraisal DocumentProject Information DocumentImplementation Completion and Results ReportFinancing AgreementContract AwardsProject URLProcurement Notices 44000-P171780
World Bank
Strengthening Fiscal Management and Private Sector Employment Opportunities Development Policy Credit
International Development Association
International Development Association
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Florian Michael Blum
+1-202-473-1000fblum@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BHUTANSecondary EducationOther Energy and ExtractivesBanking InstitutionsOther Industry, Trade and ServicesSocial ProtectionHealthPrimary EducationCentral Government (Central Agencies)AdaptationNutritionPublic Finance ManagementHealth Systems and PoliciesFiscal PolicyMitigationRegulation and Competition PolicyClimate changeFinancial Sector oversight and policy/banking regulation & restructuringBusiness Enabling EnvironmentFiscal sustainabilitySkills DevelopmentAdministrative and Civil Service ReformNutrition and Food SecurityPublic AdministrationEnergy Policies & ReformGenderPublic Private PartnershipsEnergy EfficiencyChild HealthReproductive and Maternal HealthPayment & markets infrastructureLabor Market Policy and ProgramsPublic Expenditure ManagementInvestment and Business ClimateEducationAccess to EducationTeachersFinancial Infrastructure and AccessFinancial StabilityHealth FinanceEnergyDomestic Revenue Administration
0.00
0.00
0.00
0.00
0.00
0.00
40000000Total Commitment in Second Quarter of 2020
International Development Association39820916Total Disbursement in Second Quarter of 2020
International Development AssociationProject Appraisal DocumentProject Information DocumentContract AwardsProject URLProcurement Notices 44000-P090157
World Bank
Second Urban Development Project
International Development Association
International Development Association
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Zahed Hossain Khan
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BHUTAN
Thimphu
27.4660 89.6420
Other Energy and ExtractivesSanitationWater SupplyPublic Administration - Social ProtectionUrban TransportServices and Housing for the PoorUrban Infrastructure and Service DeliveryAdministrative and Civil Service ReformPublic AdministrationUrban DevelopmentLand Administration and ManagementRural DevelopmentMunicipal Institution Building
0.00
0.00
0.00
0.00
0.05
0.05
0.06
0.05
0.05
0.06
0.06
0.06
0.06
0.14
0.14
0.14
0.14
0.14
0.14
0.14
0.14
0.15
0.14
0.14
0.15
0.22
0.22
0.23
0.22
0.22
0.23
0.22
0.23
0.23
0.22
0.23
0.23
0.26
0.27
0.27
0.26
0.27
0.27
0.26
0.27
0.27
0.26
0.27
0.27
0.22
0.22
0.23
0.22
0.22
0.23
0.22
0.23
0.23
0.22
0.23
0.23
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
633333.33
633333.33
633333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
226666.66
226666.67
226666.67
150000.00
150000.00
150000.00
0.00
0.00
0.00
633333.33
633333.33
633333.34
333333.33
333333.33
333333.34
0.00
0.00
0.00
20000.00
20000.00
20000.00
0.00
0.00
0.00
120000.00
120000.00
120000.00
166666.66
166666.67
166666.67
233333.33
233333.33
233333.34
50000.00
50000.00
50000.00
333333.33
333333.33
333333.34
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
333333.33
333333.33
333333.34
500000.00
500000.00
500000.00
333333.33
333333.33
333333.34
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
366666.66
366666.67
366666.67
500000.00
500000.00
500000.00
366666.66
366666.67
366666.67
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
12007500Total Commitment in Second Quarter of 2010
International Development Association1962094Total Disbursement in First Quarter of 2011
International Development Association-2609Total Interest Repayment in First Quarter of 2011
International Development Association-7649Total Interest Repayment in Third Quarter of 2011
International Development Association-7365Total Interest Repayment in First Quarter of 2012
International Development Association287012Total Disbursement in Third Quarter of 2012
International Development Association398153Total Disbursement in Third Quarter of 2012
International Development Association-7242Total Interest Repayment in Third Quarter of 2012
International Development Association414926Total Disbursement in Fourth Quarter of 2012
International Development Association-10964Total Interest Repayment in First Quarter of 2013
International Development Association1919382Total Disbursement in Second Quarter of 2013
International Development Association910326Total Disbursement in Third Quarter of 2013
International Development Association-16622Total Interest Repayment in Third Quarter of 2013
International Development Association66026Total Disbursement in First Quarter of 2014
International Development Association-22471Total Interest Repayment in First Quarter of 2014
International Development Association17400000Total Commitment in Second Quarter of 2014
International Development Association366151Total Disbursement in Third Quarter of 2014
International Development Association-22447Total Interest Repayment in Third Quarter of 2014
International Development Association451492Total Disbursement in Fourth Quarter of 2014
International Development Association42523Total Disbursement in Fourth Quarter of 2014
International Development Association419708Total Disbursement in First Quarter of 2015
International Development Association-22158Total Interest Repayment in First Quarter of 2015
International Development Association216533Total Disbursement in First Quarter of 2015
International Development Association-304Total Interest Repayment in First Quarter of 2015
International Development Association101295Total Disbursement in Second Quarter of 2015
International Development Association-24984Total Interest Repayment in Third Quarter of 2015
International Development Association-2083Total Interest Repayment in Third Quarter of 2015
International Development Association298917Total Disbursement in Fourth Quarter of 2015
International Development Association523545Total Disbursement in Fourth Quarter of 2015
International Development Association49763Total Disbursement in Fourth Quarter of 2015
International Development Association429179Total Disbursement in Fourth Quarter of 2015
International Development Association-26875Total Interest Repayment in First Quarter of 2016
International Development Association454280Total Disbursement in First Quarter of 2016
International Development Association-3589Total Interest Repayment in First Quarter of 2016
International Development Association235535Total Disbursement in Second Quarter of 2016
International Development Association309034Total Disbursement in Second Quarter of 2016
International Development Association176293Total Disbursement in Third Quarter of 2016
International Development Association-28740Total Interest Repayment in Third Quarter of 2016
International Development Association-13409Total Interest Repayment in Third Quarter of 2016
International Development Association472519Total Disbursement in Fourth Quarter of 2016
International Development Association352053Total Disbursement in Fourth Quarter of 2016
International Development Association-29925Total Interest Repayment in First Quarter of 2017
International Development Association415643Total Disbursement in First Quarter of 2017
International Development Association-16219Total Interest Repayment in First Quarter of 2017
International Development Association86184Total Disbursement in Third Quarter of 2017
International Development Association-31325Total Interest Repayment in Third Quarter of 2017
International Development Association6112489Total Disbursement in Third Quarter of 2017
International Development Association-22735Total Interest Repayment in Third Quarter of 2017
International Development Association-33440Total Interest Repayment in First Quarter of 2018
International Development Association2912996Total Disbursement in First Quarter of 2018
International Development Association-78358Total Interest Repayment in First Quarter of 2018
International Development Association1396421Total Disbursement in Second Quarter of 2018
International Development Association-32363Total Interest Repayment in Third Quarter of 2018
International Development Association-108739Total Interest Repayment in Third Quarter of 2018
International Development Association-31702Total Interest Repayment in First Quarter of 2019
International Development Association-126458Total Interest Repayment in First Quarter of 2019
International Development Association2988624Total Disbursement in Second Quarter of 2019
International Development Association-31249Total Interest Repayment in Third Quarter of 2019
International Development Association-125864Total Interest Repayment in Third Quarter of 2019
International Development Association-258185Total Loan Repayment in Third Quarter of 2019
International Development Association8724Total Disbursement in First Quarter of 2020
International Development Association-31364Total Interest Repayment in First Quarter of 2020
International Development Association69629Total Disbursement in First Quarter of 2020
International Development Association-160089Total Interest Repayment in First Quarter of 2020
International Development Association-257573Total Loan Repayment in First Quarter of 2020
International Development Association-2344949Total Commitment Cancellations in Second Quarter of 2020
International Development Association-70337Total Commitment Cancellations in Second Quarter of 2020
International Development Association-24507Total Disbursement in Second Quarter of 2020
International Development AssociationProject Information DocumentProject Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementFinancing AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Financing Agreement :Schedule 2 Section I D(a) | Description :NEC to carry out a program to revise EA rules. procedures andguidelines. | Due Date :30-Jun-2011
Financing Agreement :Schedule 2 Section I D3 | Description :Carry out Action Plan in Table 1 attached to the Safeguards DiagnosticReview. | Due Date :31-Dec-2010
Financing Agreement :Schedule 2 Section II A | Description :Project Progress Reporting semi-annually | Frequency :SemiAnnual
Financing Agreement :Schedule 2 Section II B | Description :Interim Unaudited Financial Reports, no later than 45 days after theend of each quarter | Frequency :Quarterly
Financing Agreement :Schedule 2 Section II B | Description :Audit Report on Financial Statements, no later than 6 months after theend of fiscal year | Frequency :Yearly
PDO Indicator
Local revenue collection (Thimphu Thromde)
PDO Indicator
Number of people in urban areas provided with access to all-season roads within a 500 meter range under the project
PDO Indicator
Number of building permits issues for LAPs
PDO Indicator
Number of households with new piped water connections
PDO Indicator
Number of househodls with new sewerage connections
Intermediate Results Indicator
Number of Property Tax Records Computerized
Intermediate Results Indicator
Number of newly serviced plots for construction
Intermediate Results Indicator
Number of Staff at TCC and PCC Trained
Intermediate Results Indicator
New roadside footpaths constructed
Intermediate Results Indicator
New off-road footpaths constructed
Intermediate Results Indicator
Internal roads constructed, non-rural
Intermediate Results Indicator
Roadside drains
Intermediate Results Indicator
Water pipelines
Intermediate Results Indicator
Sewage Pipelines
44000-P173787
World Bank
Bhutan: COVID-19 Emergency Response and Health Systems Preparedness Project
International Development Association
International Development Association
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Manav Bhattarai
+1-202-473-1000mbhattarai@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
BHUTANPublic Administration - HealthHealth Systems and PoliciesHealth System StrengtheningPandemic ResponseDisease Control
0.00
0.00
2000000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.37
50000.00
50000.00
50000.00
50000.00
50000.00
50000.00
50000.00
50000.00
50000.00
50000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2000000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.37
50000.00
50000.00
50000.00
50000.00
50000.00
50000.00
50000.00
50000.00
50000.00
50000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
5000000Total Commitment in Second Quarter of 2020
International Development Association993904Total Disbursement in Second Quarter of 2020
International Development AssociationContract AwardsProject URLProcurement Notices