44000-P132101
World Bank
International Development Association
MINISTRY OF PUBLIC WORKS
International Development Association
MINISTRY OF PUBLIC WORKSMADAGASCAR
Emergency Infrastructure Preservation & Vulnerability Reduction Project
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Noroarisoa Rabefaniraka
nrabefaniraka@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Other Water Supply, Sanitation and Waste ManagementOther EducationSocial ProtectionIrrigation and DrainageRural and Inter-Urban RoadsSocial Insurance and PensionsBiodiversityDisaster PreparednessLandscape ManagementLand Administration and ManagementRural Infrastructure and service deliveryDisaster Risk ManagementFinance for DevelopmentDisaster Response and RecoveryDisaster Risk ReductionSocial Safety NetsDisaster Risk FinanceSocial ProtectionRenewable Natural Resources Asset ManagementRural Development
International Development Association102000000Total Commitment in Fourth Quarter of 2012
International Development Association1350000Total Disbursement in Second Quarter of 2013
International Development Association6350000Total Disbursement in Second Quarter of 2013
International Development Association1053211Total Disbursement in Third Quarter of 2013
International Development Association8875092Total Disbursement in Third Quarter of 2013
International Development Association451578Total Disbursement in Fourth Quarter of 2013
International Development Association1330548Total Disbursement in Fourth Quarter of 2013
International Development Association1524429Total Disbursement in Fourth Quarter of 2013
International Development Association-38437Total Interest Repayment in Fourth Quarter of 2013
International Development Association520571Total Disbursement in First Quarter of 2014
International Development Association1647068Total Disbursement in First Quarter of 2014
International Development Association2216783Total Disbursement in First Quarter of 2014
International Development Association1045948Total Disbursement in Second Quarter of 2014
International Development Association1388441Total Disbursement in Second Quarter of 2014
International Development Association1596152Total Disbursement in Second Quarter of 2014
International Development Association-89371Total Interest Repayment in Second Quarter of 2014
International Development Association1317694Total Disbursement in Third Quarter of 2014
International Development Association2065331Total Disbursement in Third Quarter of 2014
International Development Association2555797Total Disbursement in Third Quarter of 2014
International Development Association1797023Total Disbursement in Fourth Quarter of 2014
International Development Association1849469Total Disbursement in Fourth Quarter of 2014
International Development Association2535830Total Disbursement in Fourth Quarter of 2014
International Development Association-116874Total Interest Repayment in Fourth Quarter of 2014
International Development Association1171354Total Disbursement in First Quarter of 2015
International Development Association1443488Total Disbursement in First Quarter of 2015
International Development Association2343416Total Disbursement in First Quarter of 2015
International Development Association600949Total Disbursement in Second Quarter of 2015
International Development Association1341054Total Disbursement in Second Quarter of 2015
International Development Association1427908Total Disbursement in Second Quarter of 2015
International Development Association-146976Total Interest Repayment in Second Quarter of 2015
International Development Association1509427Total Disbursement in Third Quarter of 2015
International Development Association2704594Total Disbursement in Third Quarter of 2015
International Development Association3178737Total Disbursement in Third Quarter of 2015
International Development Association1636001Total Disbursement in Fourth Quarter of 2015
International Development Association1705706Total Disbursement in Fourth Quarter of 2015
International Development Association2292355Total Disbursement in Fourth Quarter of 2015
International Development Association-193780Total Interest Repayment in Fourth Quarter of 2015
International Development Association1127448Total Disbursement in First Quarter of 2016
International Development Association1152850Total Disbursement in First Quarter of 2016
International Development Association1994857Total Disbursement in First Quarter of 2016
International Development Association537629Total Disbursement in Second Quarter of 2016
International Development Association628641Total Disbursement in Second Quarter of 2016
International Development Association2930250Total Disbursement in Second Quarter of 2016
International Development Association-228967Total Interest Repayment in Second Quarter of 2016
International Development Association295838Total Disbursement in Third Quarter of 2016
International Development Association469213Total Disbursement in Third Quarter of 2016
International Development Association702364Total Disbursement in Third Quarter of 2016
International Development Association608147Total Disbursement in Fourth Quarter of 2016
International Development Association2363167Total Disbursement in Fourth Quarter of 2016
International Development Association2581357Total Disbursement in Fourth Quarter of 2016
International Development Association-254676Total Interest Repayment in Fourth Quarter of 2016
International Development Association865828Total Disbursement in First Quarter of 2017
International Development Association1720000Total Disbursement in First Quarter of 2017
International Development Association2120583Total Disbursement in First Quarter of 2017
International Development Association256481Total Disbursement in Second Quarter of 2017
International Development Association897841Total Disbursement in Second Quarter of 2017
International Development Association948446Total Disbursement in Second Quarter of 2017
International Development Association-279467Total Interest Repayment in Second Quarter of 2017
International Development Association714039Total Disbursement in Third Quarter of 2017
International Development Association1075947Total Disbursement in Third Quarter of 2017
International Development Association869848Total Disbursement in Fourth Quarter of 2017
International Development Association1054580Total Disbursement in Fourth Quarter of 2017
International Development Association-321645Total Interest Repayment in Fourth Quarter of 2017
International Development Association344219Total Disbursement in First Quarter of 2018
International Development Association3371022Total Disbursement in First Quarter of 2018
International Development Association666610Total Disbursement in Second Quarter of 2018
International Development Association1345886Total Disbursement in Second Quarter of 2018
International Development Association-334831Total Interest Repayment in Second Quarter of 2018
International Development Association-370172Total Disbursement in Fourth Quarter of 2018
International Development Association-337612Total Disbursement in Fourth Quarter of 2018
International Development Association-337648Total Interest Repayment in Fourth Quarter of 2018
International Development Association-21732Total Disbursement in Second Quarter of 2019
International Development Association-336350Total Interest Repayment in Second Quarter of 2019Project Information DocumentImplementation Completion and Results ReportImplementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Amoron'i Mania Region
-20.5000 46.7000
Haute Matsiatra Region
-21.3700 46.5000
Vatovavy Fitovinany Region
-21.3000 47.9000
Atsimo-Atsinanana Region
-23.2000 47.4000
Androy Region
-24.7500 45.5000
0.00
0.00
0.00
0.00
0.00
833333.33
833333.33
833333.34
1916666.67
1916666.67
1916666.66
1916666.67
1916666.67
1916666.66
2000000.00
2000000.00
2000000.00
2000000.00
2000000.00
2000000.00
2916666.67
2916666.67
2916666.66
2916666.67
2916666.67
2916666.66
2916666.67
2916666.67
2916666.66
2916666.67
2916666.67
2916666.66
2166666.67
2166666.67
2166666.66
2166666.67
2166666.67
2166666.66
2166666.67
2166666.67
2166666.66
2166666.67
2166666.67
2166666.66
1083333.33
1083333.33
1083333.34
1083333.33
1083333.33
1083333.34
1083333.33
1083333.33
1083333.34
1083333.33
1083333.33
1083333.34
666666.67
666666.67
666666.66
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
962500.00
962500.00
962500.00
962500.00
962500.00
962500.00
962500.00
962500.00
1804166.67
1804166.67
1804166.67
1804166.67
1804166.67
1804166.67
1804166.67
1804166.67
1804166.67
1804166.67
1804166.67
1804166.63
1704166.67
1704166.67
1704166.67
1704166.67
1704166.67
1704166.67
1704166.67
1704166.67
1704166.67
1704166.67
1704166.67
1704166.63
2275000.00
2275000.00
2275000.00
2275000.00
2275000.00
2275000.00
2275000.00
2275000.00
2275000.00
2275000.00
2275000.00
2275000.00
1825000.00
1825000.00
1825000.00
1825000.00
1825000.00
1825000.00
1825000.00
1825000.00
1825000.00
1825000.00
1825000.00
1825000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Finance Agreement :Schedule 2 - Section I.B.5 (b) | Description :The Recipient, acting through PN-BVPI, shall enter into twoagreements, each inform and substance acceptable to the Association, with FAO, one for the provision of technical assistance andone for the provision of goods and related services (collectively, the "FAOAgreements". | Due Date :31-Jul-2013
44000-P150503
World Bank
International Development Association
International Development Association
MADAGASCAR
MG-Reengagement DPO
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Keiko Kubota
kkubota@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Social ProtectionOther Industry, Trade and ServicesCentral Government (Central Agencies)Fiscal sustainabilityPublic Finance ManagementDebt ManagementSocial protection delivery systemsTransparency, Accountability and Good GovernanceInvestment and Business ClimateSocial ProtectionPublic AdministrationFiscal PolicyBusiness Enabling Environment
International Development Association45000000Total Commitment in Fourth Quarter of 2014
International Development Association44175590Total Disbursement in Fourth Quarter of 2014
International Development Association-91959Total Interest Repayment in Second Quarter of 2015
International Development Association-160541Total Interest Repayment in Fourth Quarter of 2015
International Development Association-161773Total Interest Repayment in Second Quarter of 2016
International Development Association-157964Total Interest Repayment in Fourth Quarter of 2016
International Development Association-154396Total Interest Repayment in Second Quarter of 2017
International Development Association-162517Total Interest Repayment in Fourth Quarter of 2017
International Development Association-166952Total Interest Repayment in Second Quarter of 2018
International Development Association-158224Total Interest Repayment in Fourth Quarter of 2018
International Development Association-160231Total Interest Repayment in Second Quarter of 2019Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportFinancing AgreementContract AwardsProject URLProcurement Notices
Intermediate Results Indicator
(ii) number of pupils in public primary schools,
Intermediate Results Indicator
of which girls (%)
Intermediate Results Indicator
(i) Number of infants (0-11 months) vaccinated during the year;
Intermediate Results Indicator
Restructured arrears outstanding to the 3 petroleum companies and Ambatovy
Intermediate Results Indicator
Share of cabinet ministers filing asset declaration with BIANCO
Intermediate Results Indicator
The ratio of “fees collected” to “estimated value of electricity generated” (based on the amount of fuel inputs used) by JIRAMA
Intermediate Results Indicator
Transparency in the treatment of seized precious wood logs, measured by the periodical reports of the interministerial committee tothe Council of Ministers on the execution of approved use plan of th
Intermediate Results Indicator
Share of loan items starting without implication of MFB from the beginning
0.00
0.00
44000-P159756
World Bank
International Development Association
International Development Association
MADAGASCAR
Integrated Urban Development and Resilience Project for Greater Antananarivo
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Michel Matera
mmatera@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Sub-National GovernmentOther Water Supply, Sanitation and Waste ManagementDisaster PreparednessAdaptationServices and Housing for the PoorJob CreationClimate changeFlood and Drought Risk ManagementMunicipal FinanceParticipation and Civic EngagementUrban DevelopmentSocial InclusionJobsDisaster Risk Management
International Development Association75000000Total Commitment in Second Quarter of 2018
International Development Association633023Total Disbursement in Second Quarter of 2019
International Development Association1259983Total Disbursement in Second Quarter of 2019
International Development Association2820815Total Disbursement in Second Quarter of 2019Project Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Republic of Madagascar
-20.0000 47.0000
Analamanga Region
-18.4500 47.5000
Ambohimahasoa
-21.0680 47.1520
Ambohidratrimo District
-18.8180 47.4360
Anosivavaka
-18.8730 47.5080
Andavamamba Anjezika
-18.9150 47.5070
Ambohimamory
-19.5500 47.5830
Ambohijanahary
-18.9170 47.5170
Ambohidratrimo
-18.8180 47.4340
Ambohidrapeto
-18.9000 47.4670
Ambohidahy
-20.2670 47.4000
Amboasary
-24.3330 45.9500
Ikopa
-16.7830 46.8330
Antohomadinika
-19.2330 46.5670
Antetezana
-17.7830 49.5000
Antehiroka
-18.8500 47.4830
Ankazoabo
-22.2830 44.5170
Ankasina
-25.0170 44.2670
Ankadimbahoaka
-18.9330 47.5170
Ankadimanga
-18.9670 47.7500
Ankadifotsy
-18.8830 47.5170
Andriantany
-18.8330 47.4170
Andranonahoatra
-19.9000 46.8670
Andoharanofotsy
-19.7670 47.5500
Andekaleka
-18.7830 48.6000
Analakely
-18.9000 47.5170
Ambohitrimanjaka
-18.8670 47.4330
Soavinandriana
-19.1670 46.7330
Soavimasoandro
-18.8500 47.5500
Sisaony
-18.8500 47.3830
Namontana
-19.0670 46.6830
Morondava
-20.2890 44.3180
Miadanandriana
-19.0330 47.7830
Mamba
-18.8330 47.4000
Itaosy
-18.9170 47.4670
Bemasoandro
-19.8670 47.3330
Antananarivo
-18.9140 47.5360
Fiadanana
-18.0170 48.1000
Anosizato
-18.9330 47.5000
Anosibe
-17.8830 46.2330
Anosiala
-25.4830 45.3330
Intermediate Results Indicator
Annual increase of properties for which owners have been identified for tax purposes over previous year
Intermediate Results Indicator
Increase of water and sanitation community groups (RF2) operational within the project area
Intermediate Results Indicator
Percentage of complaints regarding project activities addressed per the grievance redressal system established by the project
Intermediate Results Indicator
Detailed Urban Plan completed in a 2-year timeframe
Intermediate Results Indicator
Revenue Enhancement strategy and action plan for CUA
Intermediate Results Indicator
Solid Waste Management Strategy approved
Intermediate Results Indicator
Length of canals and embankments rehabilitated
Intermediate Results Indicator
Roads constructed or rehabilitated
Intermediate Results Indicator
Pedestrian paths constructed or rehabilitated
Intermediate Results Indicator
Amount of sludge dredged from the C3 and safely disposed
Intermediate Results Indicator
People provided with access to improved sanitation services
Intermediate Results Indicator
People provided with access to improved sanitation services - Female (RMS requirement)
Intermediate Results Indicator
Neighborhoods (Fokontany) which have prepared and tested a contingency plans and evacuation strategy
Intermediate Results Indicator
Person-days of temporary jobs created
PDO Indicator
Share of direct project beneficiaries that are satisfied with the project interventions
PDO Indicator
People provided with improved urban living conditions
PDO Indicator
People provided with improved urban living conditions - Female (RMS requirement)
PDO Indicator
People protected by restored or improved flood protection infrastructure
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
294300.00
242250.00
278250.00
310575.00
339900.00
379575.00
427200.00
458025.00
473175.00
485625.00
502875.00
511575.00
919716.67
919716.67
919716.67
919716.67
919716.67
919716.67
919716.67
919716.67
919716.67
919716.67
919716.67
919716.63
1299945.83
1299945.83
1299945.83
1299945.83
1299945.83
1299945.83
1299945.83
1299945.83
1299945.83
1299945.83
1299945.83
1299945.87
1663725.00
1731075.00
1781700.00
1845750.00
1916475.00
1975725.00
2033025.00
2119800.00
2185500.00
2224725.00
2252700.00
2278050.00
2324100.00
2359350.00
2391000.00
2436450.00
2478450.00
2516475.00
2554125.00
2592525.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
294300.00
242250.00
278250.00
310575.00
339900.00
379575.00
427200.00
458025.00
473175.00
485625.00
502875.00
511575.00
919716.67
919716.67
919716.67
919716.67
919716.67
919716.67
919716.67
919716.67
919716.67
919716.67
919716.67
919716.63
1299945.83
1299945.83
1299945.83
1299945.83
1299945.83
1299945.83
1299945.83
1299945.83
1299945.83
1299945.83
1299945.83
1299945.87
1663725.00
1731075.00
1781700.00
1845750.00
1916475.00
1975725.00
2033025.00
2119800.00
2185500.00
2224725.00
2252700.00
2278050.00
2324100.00
2359350.00
2391000.00
2436450.00
2478450.00
2516475.00
2554125.00
2592525.00
Schedule 2, Section I.F.1. The Recipient shall, not later than three (3) months after the Effective Date, establish and maintain afinancial management system including records, accounts and preparation of related financial statements in accordance withaccounting standards acceptable to the Association.
Schedule 2, Section I.F.2. The Recipient shall ensure that financial statements of the project shall be audited in accordance withinternational auditing standards and that such audited financial statements for each fiscal year shall be furnished to theAssociation not later than six (6) months after the end of the fiscal year.
Schedule 2, Section I.F.3. The Recipient shall cause the Service Provider to furnish the annual financial statements audit reportto the Association not later than six (6) months after the end of the fiscal year.
Schedule 2, Section I.F.4. The Recipient shall, not later than three (3) months after the Effective Date, recruit (i) a seniorinternal auditor and (ii) and independent external auditor, with qualifications and experience acceptable to the Association.
Schedule 2, Section I.A.4(a) For purposes of verifying the number of people who would be affected by resettlement under Parts1.1(iv) and Part 1.2 (iv) of the Project, including the amount of cash compensation and or resettlement assistance to be paid tosuch people, no later than three (3) months after the Effective Date, the Recipient shall hire an independent agent under terms andconditions acceptable to the Association; and immediately thereafter furnish to the Association an audited compensation statementreport, acceptable to the Association.
Schedule 2, Section I.A.4(b) For auditing purposes, the Recipient shall ensure that the independent agent referred to in Schedule2, Section I.A.4 paragraph (a) of the Financing Agreement, furnishes annual financial statement audit reports of the cashcompensation paid to the people who would be affected by the resettlement under Parts 1.1(iv) and Part 1.2 (iv) of the Project.
Schedule 2, Section I.C.2 The Recipient shall furnish to the Association, not later than November 30 of each year, the annual workplans and budgets approved by the Project Steering Committee for the Association's review and approval; except for the annual workplan and budget for the Project for the first year of Project implementation, which shall be furnished no later than one (1) monthafter the Effective Date. Only the activities included in an annual work plan and budget expressly approved by the Association(each an “Annual Work Plan and Budget”) are eligible to be financed from the proceeds of the Financing.
44000-P151785
World Bank
International Development Association
International Development Association
MADAGASCAR
MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP)
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Massan Elise Akitani
makitani@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Non-Renewable Energy GenerationRenewable Energy HydroPublic Administration - Energy and ExtractivesEnergy Transmission and DistributionRural DevelopmentUrban Infrastructure and Service DeliveryJob CreationState-owned Enterprise Reform and PrivatizationUrban DevelopmentTransparency, Accountability and Good GovernanceRural Infrastructure and service deliveryPublic AdministrationJobs
International Development Association65000000Total Commitment in First Quarter of 2016
International Development Association723899Total Disbursement in Third Quarter of 2016
International Development Association245744Total Disbursement in Fourth Quarter of 2016
International Development Association4684111Total Disbursement in Fourth Quarter of 2016
International Development Association250000Total Disbursement in First Quarter of 2017
International Development Association784073Total Disbursement in Second Quarter of 2017
International Development Association908924Total Disbursement in Second Quarter of 2017
International Development Association2409676Total Disbursement in Second Quarter of 2017
International Development Association-15384Total Interest Repayment in Second Quarter of 2017
International Development Association818056Total Disbursement in Third Quarter of 2017
International Development Association1076000Total Disbursement in Third Quarter of 2017
International Development Association2698784Total Disbursement in Third Quarter of 2017
International Development Association543858Total Disbursement in Fourth Quarter of 2017
International Development Association1271549Total Disbursement in Fourth Quarter of 2017
International Development Association5927215Total Disbursement in Fourth Quarter of 2017
International Development Association-42090Total Interest Repayment in Fourth Quarter of 2017
International Development Association524107Total Disbursement in First Quarter of 2018
International Development Association794353Total Disbursement in First Quarter of 2018
International Development Association3691907Total Disbursement in First Quarter of 2018
International Development Association751340Total Disbursement in Second Quarter of 2018
International Development Association1773315Total Disbursement in Second Quarter of 2018
International Development Association1870932Total Disbursement in Second Quarter of 2018
International Development Association-84666Total Interest Repayment in Second Quarter of 2018
International Development Association40000000Total Commitment in Second Quarter of 2018
International Development Association136318Total Disbursement in Third Quarter of 2018
International Development Association820851Total Disbursement in Third Quarter of 2018
International Development Association1144785Total Disbursement in Third Quarter of 2018
International Development Association80214Total Disbursement in Fourth Quarter of 2018
International Development Association2228209Total Disbursement in Fourth Quarter of 2018
International Development Association-119037Total Interest Repayment in Fourth Quarter of 2018
International Development Association7773Total Disbursement in First Quarter of 2019
International Development Association240769Total Disbursement in First Quarter of 2019
International Development Association2676148Total Disbursement in First Quarter of 2019
International Development Association945011Total Disbursement in Second Quarter of 2019
International Development Association976356Total Disbursement in Second Quarter of 2019
International Development Association1974802Total Disbursement in Second Quarter of 2019
International Development Association-139855Total Interest Repayment in Second Quarter of 2019
International Development Association14947Total Disbursement in Third Quarter of 2019
International Development Association578661Total Disbursement in Third Quarter of 2019Project Information DocumentProject Information DocumentProject Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementFinancing AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Soanierana Ivongo
-16.9170 49.5830
Morondava
-20.2890 44.3180
Mitsinjo
-23.6170 45.3000
Manakara
-22.1490 48.0110
Mampikony
-16.1000 47.6330
Ihosy
-22.4030 46.1260
Antananarivo
-18.9140 47.5360
Ankazoabo
-22.2830 44.5170
Brickaville
-18.8200 49.0640
Antananarivo-Atsimondrano
-18.9270 47.6110
Manjakandriana
-18.8380 47.7600
Antanifotsy
-19.7450 47.4810
Ambatolampy
-19.4620 47.5500
Befandriana Avaratra District
-15.1450 48.7800
Antananarivo-Avaradrano District
-19.0000 47.5010
Andapa District
-14.6500 49.6500
Marovoay District
-16.1500 46.6170
Vavatenina District
-17.5170 48.9500
Maroantsetra District
-15.3840 49.5650
Mananara Nord District
-16.2160 49.5480
Farafangana District
-22.8020 47.5980
Vangaindrano District
-23.4930 47.4500
Bealanana District
-14.5730 48.7710
Mahabo District
-20.6360 45.1650
Ambohidratrimo District
-18.8180 47.4360
Sakaraha District
-22.9180 44.5300
Ampanihy District
-24.6960 44.7460
Ambovombe District
-25.1770 46.0870
Bekily District
-24.1830 45.3830
Antalaha
-14.9000 50.2790
Antsohihy
-14.8800 47.9880
Nosy Be
-13.3420 48.2580
Soavinandriana
-19.2260 46.5620
Miarinarivo
-18.8750 46.8180
Vohemary
-21.3670 44.8330
Sambava
-14.2670 50.1670
Mahanoro
-24.9830 46.7500
Fenoarivo Atsinanana
-17.3810 49.4080
Ampanefena
-13.8670 49.9670
Ambositra
-20.5300 47.2430
Ambilobe
-13.2000 49.0500
Ambatondrazaka
-17.8330 48.4170
Ambanja
-13.6830 48.4500
Antsirabe
-19.8660 47.0330
Antsiranana
-12.2790 49.2920
Belo sur Tsiribihina
-19.6980 44.5460
Mahajanga
-15.7170 46.3170
Mananjary
-21.2300 48.3420
Toamasina
-18.1490 49.4020
Intermediate Results Indicator
Percentage of total sales (kWh) covered by the Revenue Protection Program (RPP).
Intermediate Results Indicator
Completion of key studies: Least Cost Power Development Plan (LCPDP), Tariff Study
Intermediate Results Indicator
Percentage of technical positions held by females that report directly to Directors in JIRAMA
Intermediate Results Indicator
JIRAMA customer satisfaction survey undertaken in project area and report on customer feedback and how it was addressed by JIRAMA
Intermediate Results Indicator
Installation of Management Information System (MIS) at JIRAMA, and populated with data
Intermediate Results Indicator
JIRAMA's Management Improvement Plan (MIP) completed and key management positions recruited
Intermediate Results Indicator
Time taken for first disbursement of funds requested by Government for an eligible emergency or crisis
Intermediate Results Indicator
Dispatching Center and Distribution Control Center constructed and commissioned
Intermediate Results Indicator
Public availability of customer satisfaction survey
Intermediate Results Indicator
Transmission lines constructed or rehabilitated under the project
Intermediate Results Indicator
Transmission lines constructed under the project
Intermediate Results Indicator
Transmission lines rehabilitated under the project
Intermediate Results Indicator
Distribution lines constructed or rehabilitated under the project
Intermediate Results Indicator
Distribution lines constructed under the project
Intermediate Results Indicator
Distribution lines rehabilitated under the project
Intermediate Results Indicator
Competitive Bidding process for the development of one priority small hydro site launched
PDO Indicator
Total electricity losses per year in the project area
PDO Indicator
Female beneficiaries
PDO Indicator
Interruptions in electricity service per year in the project area
PDO Indicator
Direct project beneficiaries
0.00
0.00
161850.00
93210.00
209950.00
241150.00
269165.00
294580.00
158795.00
351000.00
385645.00
404560.00
414765.00
212355.00
435825.00
443365.00
441025.00
430105.00
214045.00
437320.00
463255.00
493805.00
507455.00
262145.00
553540.00
590980.00
616005.00
320645.00
676260.00
725010.00
744965.00
771420.00
403520.00
854100.00
898560.00
934310.00
488020.00
1028885.00
1102530.00
1164930.00
1230060.00
639405.00
1329705.00
1408225.00
1472705.00
1523990.00
776685.00
1599650.00
1660945.00
1712295.00
1761955.00
909870.00
1868750.00
1913470.00
1941875.00
1960270.00
991770.00
2014220.00
2044770.00
2072200.00
1050790.00
2130570.00
2164695.00
2197065.00
2230215.00
1127620.00
2280850.00
1786330.00
0.00
0.00
0.00
0.00
0.00
0.00
63765.00
63765.00
63765.00
63765.00
318429.58
318429.58
318429.58
318429.58
318429.58
318429.58
318429.58
318429.58
318429.58
318429.58
318429.58
318429.62
444193.75
444193.75
444193.75
444193.75
444193.75
444193.75
444193.75
444193.75
444193.75
444193.75
444193.75
444193.75
1149375.83
1149375.83
1149375.83
1149375.83
1149375.83
1149375.83
1149375.83
1149375.83
1149375.83
1149375.83
1149375.83
1149375.87
2252124.17
2252124.17
2252124.17
2252124.17
2252124.17
2252124.17
2252124.17
2252124.17
2252124.17
2252124.17
2252124.17
2252124.13
3112537.08
3112537.08
3112537.08
3112537.08
3112537.08
3112537.08
3112537.08
3112537.08
3112537.08
3112537.08
3112537.08
3112537.12
1742501.50
1742501.50
1742501.50
1742501.50
1742501.50
1742501.50
1742501.50
1742501.50
1742501.50
1742501.50
Finance Agreement :Recruitment of external audit firm | Description :Schedule 2, Section V.1: By no later than 6 months after theEffective Date, the Recipient shall recruit an external auditor in accordance with the provisions of Section III of Schedule 2 tothe Financing Agreement, and on the basis of terms of reference, qualifications and experience acceptable to the Association. | DueDate :24 February 2017
Finance Agreement :Appointment or recruitment of a qualified accountant and procurement assistant | Description :Schedule 2,Section V.2: By no later than 3 months after the Effective Date, the Recipient shall appoint or recruit a qualified accountant anda procurement assistant at the MEH in accordance with the provisions of Section III of Schedule 2 to the Financing Agreement, andon the basis of terms of reference, qualifications and experience acceptable to the Association. | Due Date :24 November 2016
Finance Agreement :Launching of a competitive and transparent selection of staff at JIRAMA | Description :Schedule 2, Section V.3:By no later than 12 months after the Effective Date, the Recipient, with the support of specialized consultants, shall launch acompetitive and transparent selection of staff at JIRAMA to occupy the top management positions. | Due Date : 24 August 2017
Finance Agreement :Launching of a competitive and transparent selection of staff at JIRAMA | Description :Schedule 2, Section V.3:By no later than 12 months after the Effective Date, the Recipient, with the support of specialized consultants, shall launch acompetitive and transparent selection of staff at JIRAMA to occupy the top management positions. | Due Date : 24 August 2017
44000-P131945
World Bank
International Development Association
International Development Association
MADAGASCAR
Madagascar Emergency Support to Critical Education, Health and Nutrition Services Project
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Jumana N. Qamruddin
jqamruddin@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
HealthPrimary EducationNutritionChild HealthAccess to EducationReproductive and Maternal HealthNutrition and Food SecurityHealth System StrengtheningFood SecurityEducation FinancingHealth Systems and PoliciesEducation
International Development Association65000000Total Commitment in Fourth Quarter of 2012
International Development Association9000000Total Disbursement in Second Quarter of 2013
International Development Association54611Total Disbursement in Third Quarter of 2013
International Development Association568715Total Disbursement in Fourth Quarter of 2013
International Development Association1695088Total Disbursement in Fourth Quarter of 2013
International Development Association2478747Total Disbursement in Fourth Quarter of 2013
International Development Association-24473Total Interest Repayment in Fourth Quarter of 2013
International Development Association351801Total Disbursement in First Quarter of 2014
International Development Association576894Total Disbursement in First Quarter of 2014
International Development Association2040506Total Disbursement in First Quarter of 2014
International Development Association10000000Total Commitment in First Quarter of 2014
International Development Association986428Total Disbursement in Second Quarter of 2014
International Development Association2130920Total Disbursement in Second Quarter of 2014
International Development Association2701588Total Disbursement in Second Quarter of 2014
International Development Association-54077Total Interest Repayment in Second Quarter of 2014
International Development Association395952Total Disbursement in Third Quarter of 2014
International Development Association716600Total Disbursement in Third Quarter of 2014
International Development Association1186891Total Disbursement in Third Quarter of 2014
International Development Association985054Total Disbursement in Fourth Quarter of 2014
International Development Association1129017Total Disbursement in Fourth Quarter of 2014
International Development Association1971624Total Disbursement in Fourth Quarter of 2014
International Development Association-81852Total Interest Repayment in Fourth Quarter of 2014
International Development Association1300000Total Disbursement in Fourth Quarter of 2014
International Development Association428976Total Disbursement in First Quarter of 2015
International Development Association1014417Total Disbursement in First Quarter of 2015
International Development Association1380181Total Disbursement in First Quarter of 2015
International Development Association73497Total Disbursement in First Quarter of 2015
International Development Association577584Total Disbursement in Second Quarter of 2015
International Development Association1228864Total Disbursement in Second Quarter of 2015
International Development Association1806493Total Disbursement in Second Quarter of 2015
International Development Association-100334Total Interest Repayment in Second Quarter of 2015
International Development Association26515Total Disbursement in Second Quarter of 2015
International Development Association-3704Total Interest Repayment in Second Quarter of 2015
International Development Association427033Total Disbursement in Third Quarter of 2015
International Development Association768684Total Disbursement in Third Quarter of 2015
International Development Association3677713Total Disbursement in Third Quarter of 2015
International Development Association54258Total Disbursement in Third Quarter of 2015
International Development Association201718Total Disbursement in Third Quarter of 2015
International Development Association1028884Total Disbursement in Fourth Quarter of 2015
International Development Association3567826Total Disbursement in Fourth Quarter of 2015
International Development Association4005849Total Disbursement in Fourth Quarter of 2015
International Development Association-124550Total Interest Repayment in Fourth Quarter of 2015
International Development Association114642Total Disbursement in Fourth Quarter of 2015
International Development Association138351Total Disbursement in Fourth Quarter of 2015
International Development Association258360Total Disbursement in Fourth Quarter of 2015
International Development Association-5318Total Interest Repayment in Fourth Quarter of 2015
International Development Association1491157Total Disbursement in First Quarter of 2016
International Development Association1986547Total Disbursement in First Quarter of 2016
International Development Association2147699Total Disbursement in First Quarter of 2016
International Development Association273518Total Disbursement in First Quarter of 2016
International Development Association433634Total Disbursement in First Quarter of 2016
International Development Association640849Total Disbursement in Second Quarter of 2016
International Development Association1199013Total Disbursement in Second Quarter of 2016
International Development Association-175729Total Interest Repayment in Second Quarter of 2016
International Development Association380152Total Disbursement in Second Quarter of 2016
International Development Association386956Total Disbursement in Second Quarter of 2016
International Development Association454814Total Disbursement in Second Quarter of 2016
International Development Association-8603Total Interest Repayment in Second Quarter of 2016
International Development Association895193Total Disbursement in Third Quarter of 2016
International Development Association1394372Total Disbursement in Third Quarter of 2016
International Development Association502107Total Disbursement in Third Quarter of 2016
International Development Association735928Total Disbursement in Third Quarter of 2016
International Development Association164008Total Disbursement in Fourth Quarter of 2016
International Development Association420062Total Disbursement in Fourth Quarter of 2016
International Development Association1306056Total Disbursement in Fourth Quarter of 2016
International Development Association-204646Total Interest Repayment in Fourth Quarter of 2016
International Development Association884345Total Disbursement in Fourth Quarter of 2016
International Development Association1176843Total Disbursement in Fourth Quarter of 2016
International Development Association-15642Total Interest Repayment in Fourth Quarter of 2016
International Development Association310279Total Disbursement in First Quarter of 2017
International Development Association506067Total Disbursement in First Quarter of 2017
International Development Association655062Total Disbursement in First Quarter of 2017
International Development Association-1649835Total Disbursement in Second Quarter of 2017
International Development Association-160Total Disbursement in Second Quarter of 2017
International Development Association-210079Total Interest Repayment in Second Quarter of 2017
International Development Association407900Total Disbursement in Second Quarter of 2017
International Development Association-25556Total Interest Repayment in Second Quarter of 2017
International Development Association-2078100Total Commitment Cancellations in Third Quarter of 2017
International Development Association-108709Total Disbursement in Third Quarter of 2017
International Development Association-4823Total Disbursement in Third Quarter of 2017
International Development Association73336Total Disbursement in Third Quarter of 2017
International Development Association-4823Total Commitment Cancellations in Fourth Quarter of 2017
International Development Association-217801Total Interest Repayment in Fourth Quarter of 2017
International Development Association-35268Total Interest Repayment in Fourth Quarter of 2017
International Development Association-21008Total Commitment Cancellations in First Quarter of 2018
International Development Association-20688Total Disbursement in First Quarter of 2018
International Development Association-222797Total Interest Repayment in Second Quarter of 2018
International Development Association-35544Total Interest Repayment in Second Quarter of 2018
International Development Association-211154Total Interest Repayment in Fourth Quarter of 2018
International Development Association-33645Total Interest Repayment in Fourth Quarter of 2018
International Development Association-213832Total Interest Repayment in Second Quarter of 2019
International Development Association-34071Total Interest Repayment in Second Quarter of 2019Project Information DocumentImplementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementFinancing AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Amoron'i Mania Region
-20.5000 46.7000
Haute Matsiatra Region
-21.3700 46.5000
Vatovavy Fitovinany Region
-21.3000 47.9000
Atsimo-Atsinanana Region
-23.2000 47.4000
Androy Region
-24.7500 45.5000
Intermediate Results Indicator
Number of community teachers certified to be in service paid
Intermediate Results Indicator
Number of children receiving anti-helminth treatment (school age children)
Intermediate Results Indicator
Number of parents' associations/school management committees trained on teacher accountability process and use of school grants year
Intermediate Results Indicator
Number of children enrolled in the MUAC program between 2-5 years of age
Intermediate Results Indicator
Number of Community Nutrition Agents trained to provide health and nutrition education
Intermediate Results Indicator
Number of schools supported by ACN during de-worming
Intermediate Results Indicator
Number of households receiving support kits (inputs and equipment) for short cycle agriculture and livestock activities
Intermediate Results Indicator
Number of teachers trained in school health and nutrition activities
Intermediate Results Indicator
Pregnant women receiving antenatal care during a visit to a health provider (number)
Intermediate Results Indicator
Health facilities constructed, renovated, and/or equipped (number)
Intermediate Results Indicator
Percentage of women attending antenatal clinic who are tested for syphilis
Intermediate Results Indicator
School grants paid by the project on time
Intermediate Results Indicator
Percentage of facilities visited by the district technical assistants
Intermediate Results Indicator
percentage of Nutrition sites Monthly Report submitted within +5 days of the end of the month through mobile phones
Intermediate Results Indicator
Number of children under 2 years enrolled in the growth monitoring program
Intermediate Results Indicator
of which % of female
PDO Indicator
Female beneficiaries
PDO Indicator
Children under the age of 24 months benefiting from improved infant and young child feeding (IYCF) practices
PDO Indicator
Female beneficiaries
PDO Indicator
Direct project beneficiaries
PDO Indicator
Births (deliveries) attended by skilled health personnel (number)
PDO Indicator
Children immunized (number)
PDO Indicator
People with access to a basic package of health, nutrition, or reproductive health services (number)
PDO Indicator
Pregnant/lactating women
PDO Indicator
Children under 5
PDO Indicator
Children immunized - under 12 months against DTP3 (number)
PDO Indicator
Total number of schools receiving school grants funded by the project
PDO Indicator
Students enrolled in primary schools in targeted regions
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1796998.42
1796998.42
1796998.43
770142.18
770142.18
770142.18
1796998.42
1796998.42
1796998.43
1026856.24
1026856.24
1026856.25
1283570.30
1283570.30
1283570.31
1283570.30
1283570.30
1283570.31
2567140.60
2567140.60
2567140.61
2567140.60
2567140.60
2567140.61
2567140.60
2567140.60
2567140.61
2567140.60
2567140.60
2567140.61
1216824.64
1216824.64
1216824.64
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Finance Agreement :Section 5.01 of the Financing Agreement | Description :Establishment of the Technical steering committee | DueDate :25-Apr-2013
Finance Agreement :Section I.A.2 (a) of Schedule 2 of the Financing Agreement | Description :Establishment of the projectcoordination cell | Due Date :09-May-2013
Finance Agreement :Section I.A.3 (c) of Schedule 2 of the Financing Agreement | Description :Terms of reference of PIU staff | DueDate :09-May-2013
Finance Agreement :Section I.B.4 of Schedule 2 of the Financing Agreement | Description :Adoption of a regulation on school grants| Due Date :25-Jul-2013
Finance Agreement :Section I.D.2 (a) of Schedule 2 of the Financing Agreement | Description :Publication of a revised medical wastemanagement plan | Due Date :30-Sep-2014
Finance Agreement :Section I.E.2 of Schedule 2 of the Financing Agreement | Description :Transmission of Annual plan and budget toIDA for approbation | Due Date :25-May-2013
Finance Agreement :Section I.F.1 of Schedule 2 of the Financing Agreement | Description :Updated Education, Health and NutritionManuals | Due Date :25-Jul-2013
Finance Agreement :Section I.F.2 of Schedule 2 of the Financing Agreement | Description :Adoption of Project Implementation Manual| Due Date :17-Jul-2013
Finance Agreement :Section II.B.4 of Schedule 2 of the Financing Agreement | Description :Engagement of independent auditors forthe carrying out of audits of the Recipient's financial statement | Due Date :31-Dec-2013
Finance Agreement :Section IV.B.1 (b) of Schedule 2 of the Financing Agreement | Description :Payment Agreements signed and PaymentAccount opened | Due Date :30-Sep-2013
Finance Agreement :Section IV.B.1 (c) of Schedule 2 of the Financing Agreement | Description :Payment Agreements signed and PaymentAccount opened; School Grant Regulation adopted | Due Date :31-Aug-2013
44000-P074235
World Bank
International Development Association
MINISTRY OF THE ENVIRONMENT, WATER AND FORESTS
International Development Association
MINISTRY OF THE ENVIRONMENT, WATER AND FORESTSMADAGASCAR
Third Environment Program Support Project
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Giovanni Ruta
gruta@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Other Agriculture, Fishing and ForestryRenewable Energy BiomassSub-National GovernmentRenewable Energy WindRenewable Energy SolarRenewable Energy GeothermalCentral Government (Central Agencies)Soil PollutionWater PollutionAir quality managementBiodiversityParticipation and Civic EngagementEnvironmental Health and Pollution ManagementSocial InclusionRenewable Natural Resources Asset ManagementMitigationJobsEnvironmental policies and institutionsClimate change
International Development Association40000000Total Commitment in Second Quarter of 2004
International Development Association1050000Total Disbursement in Fourth Quarter of 2004
International Development Association1356068Total Disbursement in Fourth Quarter of 2004
International Development Association172232Total Disbursement in First Quarter of 2005
International Development Association759397Total Disbursement in First Quarter of 2005
International Development Association72044Total Disbursement in Second Quarter of 2005
International Development Association898541Total Disbursement in Second Quarter of 2005
International Development Association135829Total Disbursement in Third Quarter of 2005
International Development Association209910Total Disbursement in Third Quarter of 2005
International Development Association368101Total Disbursement in Third Quarter of 2005
International Development Association236171Total Disbursement in Fourth Quarter of 2005
International Development Association415023Total Disbursement in Fourth Quarter of 2005
International Development Association1050000Total Disbursement in Fourth Quarter of 2005
International Development Association163240Total Disbursement in First Quarter of 2006
International Development Association469980Total Disbursement in First Quarter of 2006
International Development Association598940Total Disbursement in Second Quarter of 2006
International Development Association699916Total Disbursement in Second Quarter of 2006
International Development Association172694Total Disbursement in Third Quarter of 2006
International Development Association271474Total Disbursement in Third Quarter of 2006
International Development Association283719Total Disbursement in Third Quarter of 2006
International Development Association669848Total Disbursement in Fourth Quarter of 2006
International Development Association988482Total Disbursement in Fourth Quarter of 2006
International Development Association1091271Total Disbursement in Fourth Quarter of 2006
International Development Association106712Total Disbursement in First Quarter of 2007
International Development Association4309638Total Disbursement in First Quarter of 2007
International Development Association356414Total Disbursement in Second Quarter of 2007
International Development Association604916Total Disbursement in Second Quarter of 2007
International Development Association2491724Total Disbursement in Second Quarter of 2007
International Development Association935908Total Disbursement in Third Quarter of 2007
International Development Association945777Total Disbursement in Third Quarter of 2007
International Development Association851111Total Disbursement in Fourth Quarter of 2007
International Development Association115716Total Disbursement in First Quarter of 2008
International Development Association1114465Total Disbursement in First Quarter of 2008
International Development Association420740Total Disbursement in Second Quarter of 2008
International Development Association1144336Total Disbursement in Second Quarter of 2008
International Development Association10283Total Disbursement in Third Quarter of 2008
International Development Association136431Total Disbursement in Third Quarter of 2008
International Development Association1556714Total Disbursement in Third Quarter of 2008
International Development Association292014Total Disbursement in Fourth Quarter of 2008
International Development Association670620Total Disbursement in Fourth Quarter of 2008
International Development Association273272Total Disbursement in First Quarter of 2009
International Development Association416791Total Disbursement in First Quarter of 2009
International Development Association187180Total Disbursement in Fourth Quarter of 2009
International Development Association4266229Total Disbursement in Fourth Quarter of 2009
International Development Association119118Total Disbursement in First Quarter of 2010
International Development Association266100Total Disbursement in Second Quarter of 2010
International Development Association441757Total Disbursement in Third Quarter of 2010
International Development Association965353Total Disbursement in Third Quarter of 2010
International Development Association1282958Total Disbursement in Third Quarter of 2010
International Development Association184275Total Disbursement in Fourth Quarter of 2010
International Development Association1213839Total Disbursement in Fourth Quarter of 2010
International Development Association42000000Total Commitment in Second Quarter of 2011
International Development Association989912Total Disbursement in Second Quarter of 2011
International Development Association138687Total Disbursement in Third Quarter of 2011
International Development Association342661Total Disbursement in Third Quarter of 2011
International Development Association525403Total Disbursement in Third Quarter of 2011
International Development Association130060Total Disbursement in Fourth Quarter of 2011
International Development Association154353Total Disbursement in Fourth Quarter of 2011
International Development Association171242Total Disbursement in Fourth Quarter of 2011
International Development Association4500000Total Disbursement in Second Quarter of 2012
International Development Association-16720Total Disbursement in Second Quarter of 2012
International Development Association12309Total Disbursement in Second Quarter of 2012
International Development Association26377Total Disbursement in Second Quarter of 2012
International Development Association2369881Total Disbursement in Third Quarter of 2012
International Development Association-8329Total Interest Repayment in Third Quarter of 2012
International Development Association-556155Total Commitment Cancellations in Third Quarter of 2012
International Development Association1070842Total Disbursement in Fourth Quarter of 2012
International Development Association649804Total Disbursement in First Quarter of 2013
International Development Association2595271Total Disbursement in First Quarter of 2013
International Development Association-29600Total Interest Repayment in First Quarter of 2013
International Development Association1060999Total Disbursement in Second Quarter of 2013
International Development Association1385998Total Disbursement in Second Quarter of 2013
International Development Association622009Total Disbursement in Third Quarter of 2013
International Development Association1023414Total Disbursement in Third Quarter of 2013
International Development Association-47064Total Interest Repayment in Third Quarter of 2013
International Development Association954734Total Disbursement in Fourth Quarter of 2013
International Development Association638736Total Disbursement in First Quarter of 2014
International Development Association5074866Total Disbursement in First Quarter of 2014
International Development Association-65830Total Interest Repayment in First Quarter of 2014
International Development Association899454Total Disbursement in Second Quarter of 2014
International Development Association971215Total Disbursement in Second Quarter of 2014
International Development Association1948952Total Disbursement in Second Quarter of 2014
International Development Association645433Total Disbursement in Third Quarter of 2014
International Development Association-94176Total Interest Repayment in Third Quarter of 2014
International Development Association354235Total Disbursement in Fourth Quarter of 2014
International Development Association578141Total Disbursement in Fourth Quarter of 2014
International Development Association511115Total Disbursement in First Quarter of 2015
International Development Association1618776Total Disbursement in First Quarter of 2015
International Development Association2010876Total Disbursement in First Quarter of 2015
International Development Association-94457Total Interest Repayment in First Quarter of 2015
International Development Association615825Total Disbursement in Second Quarter of 2015
International Development Association729785Total Disbursement in Second Quarter of 2015
International Development Association238247Total Disbursement in Third Quarter of 2015
International Development Association-112580Total Interest Repayment in Third Quarter of 2015
International Development Association209917Total Disbursement in Fourth Quarter of 2015
International Development Association421782Total Disbursement in Fourth Quarter of 2015
International Development Association538761Total Disbursement in Fourth Quarter of 2015
International Development Association299707Total Disbursement in First Quarter of 2016
International Development Association300889Total Disbursement in First Quarter of 2016
International Development Association591114Total Disbursement in First Quarter of 2016
International Development Association-117785Total Interest Repayment in First Quarter of 2016
International Development Association22187Total Disbursement in Second Quarter of 2016
International Development Association2867189Total Disbursement in Second Quarter of 2016
International Development Association-135159Total Interest Repayment in Third Quarter of 2016
International Development Association-107136Total Disbursement in Fourth Quarter of 2016
International Development Association-130371Total Interest Repayment in First Quarter of 2017
International Development Association-197859Total Disbursement in Second Quarter of 2017
International Development Association-729Total Disbursement in Third Quarter of 2017
International Development Association-134071Total Interest Repayment in Third Quarter of 2017
International Development Association-140518Total Interest Repayment in First Quarter of 2018
International Development Association-6088Total Disbursement in Second Quarter of 2018
International Development Association-136241Total Interest Repayment in Third Quarter of 2018
International Development Association-730630Total Commitment Cancellations in First Quarter of 2019
International Development Association-97209Total Disbursement in First Quarter of 2019
International Development Association-133333Total Interest Repayment in First Quarter of 2019Project Information DocumentProject Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementAgreementAgreementAgreementAgreementAgreementAgreementContract AwardsProject URLProcurement Notices
Tahiry Nanaharin' i Zahamena
-17.7010 48.9190
Alan' ny Mikea
-22.5000 43.3830
Midongy Atsimo
-23.5900 47.0150
Foret de Kalambatritra
-23.3670 46.4830
Tsingin' i Bemaraha
-18.6670 44.7510
Belo
-20.7400 44.0080
Tahiry Nanaharin' Ankarafantsika
-16.1500 47.0330
Alan Ambohitra
-12.6170 49.1500
Andasibe-Mantadia National Park
-18.8350 48.4590
Andringitra National Park
-22.1130 46.9230
Masoala National Park
-15.3000 50.0530
Tahiry Nanahary Antsingin'i Namoroka
-16.4670 45.3330
Baie de Baly
-15.9670 45.2830
Tahiry Manokan' i Kirindy
-20.7830 44.1670
Farihy Tsimanampetsotsa
-24.1170 43.7500
GEO Indicator
Level of threat in project supported PAs (number of fires declared)
Intermediate Results Indicator
Number of management transfer contracts established or renewed
Intermediate Results Indicator
Number of validated studies on the strategy of illicit rosewood stockpile management
Intermediate Results Indicator
Number of PAs with a restructured Park Support Committee and strengthened technical capacity
Intermediate Results Indicator
Number of established community ecotourism projects
Intermediate Results Indicator
Weighted management effectiveness tracking tool score for targeted protected areas
Intermediate Results Indicator
Ratio of the operational costs of FAPBM to the amount of financing delivered to PAs
Intermediate Results Indicator
Study on the reform of the PA network management is approved
Intermediate Results Indicator
Conservation infrastructures built or renovated
Intermediate Results Indicator
Number of affected households (PAP) that benefitted from social safeguards sub-projects
Intermediate Results Indicator
Number of paid patrolling days of local surveillance committees
Intermediate Results Indicator
Number of reference scenarios for emissions linked to deforestation defined for the Eastern Humid Forest ecoregion
Intermediate Results Indicator
Number of concessions signed with the private sector
Intermediate Results Indicator
Number of surveillance grids monitored in 30 national parks and 3 corridors
Intermediate Results Indicator
Index of management efficiency of PCU in implementation and monitoring of project
Intermediate Results Indicator
Km of tourism circuits equipped to operational standards
Intermediate Results Indicator
Km of Protected Area boundaries materialized and maintained
Intermediate Results Indicator
Km of access roads delivered
PDO Indicator
Surface of Protected Area network with recurrent costs co-funded from revenues from the combined project endowment and previous EP3(IDA) endowment to the Foundation
PDO Indicator
Number of households adjacent to the Protected Areas that have benefitted from park, natural resource and livelihood activities
PDO Indicator
Of which female beneficiaries
PDO Indicator
A precious woods stockpile use plan has been submitted to the Convention on International Trade in Endangered Species of Wild Faunaand Flora (CITES)
PDO Indicator
All illegal precious woods stockpiles seized by Government have been audited and secured.
PDO Indicator
Government has validated and adopted a schedule for the reform of protected areas managed by Madagascar National Parks (MNP)
1000000.00
1000000.00
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.63
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.63
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.63
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.63
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1000000.00
1000000.00
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.63
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.63
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.63
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.63
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
333333.33
333333.33
333333.33
333333.33
333333.33
333333.33
333333.33
333333.33
333333.33
333333.33
333333.33
333333.37
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
583333.33
583333.33
583333.33
583333.33
583333.33
583333.33
583333.33
583333.33
583333.33
583333.33
583333.33
583333.37
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.63
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.37
536987.11
536987.11
536987.11
536987.11
536987.11
536987.11
536987.11
536987.11
536987.11
536987.11
536987.11
536987.16
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Finance Agreement: Madagascar National Parks Project Agreement: Schedule, Section IV, Paragraph 1 | Description: MadagascarNational Parks shall use its own internally generated revenues to cover the depreciation costs of equipment and other investmentsfinanced by the project. | Due Date :11-Jan-2012
Finance Agreement: Financing Agreement: Paragraph 4.01(c) | Description: The Recipient shall apply sound social, environmental andecological standards and practices to PAs, to avoid compromising the achievement of project objectives and raising reputationalrisks | Frequency :Quarterly
Finance Agreement: Financing Agreement: Paragraph 4.01(d) | Description: The Recipient shall not repeal, waive, suspend, set aside,or fail to enforce Decree 2010-141 prohibiting the cutting, extraction or export of rosewood and ebony, or any provisions thereof |Frequency :Quarterly
Finance Agreement: Financing Agreement: Paragraph 4.01(e) | Description: The Recipient shall execute an administrative order orother instrument purporting to delegate authority to NGOs | Due Date :31-Dec-2011
Finance Agreement: Financing Agreement: Paragraph 5.01(a) | Description: The Recipient shall execute subsidiary agreements withMadagascar National Parks and the Foundation. | Due Date :11-Jan-2012
Finance Agreement: Financing Agreement, Paragraph 4.02 | Description: The co-financing deadline for the effectiveness of theco-financing agreement for NGO financing is September 30, 2013 | Due Date :30-Sep-2013
Finance Agreement: Financing Agreement: Paragraph 5.01(b) | Description: The Recipient shall execute the GEF Grant Agreement andfulfill all conditions precedent to its effectiveness or to the right to make withdrawals. | Due Date :11-Jan-2012
Finance Agreement: Financing Agreement: Paragraph 5.01(c) | Description: The Recipient shall establish a Project SteeringCommittee, Project Coordination Unit and prepare and adopt a Project Implementation Plan. | Due Date :11-Jan-2012
Finance Agreement: Financing Agreement: Schedule II, Section 1, F, Paragraph 1 | Description: The Recipient shall ensure that theproject activities are implemented in accordance with the safeguards instruments applicable to the additional financing. |Frequency :Yearly
Finance Agreement: Financing Agreement, Schedule 2, Section II, Paragraph B.4 | Description: The Recipient shall recruit aninternal auditor to the PCU staff and adopt acceptable revised TOR for the recruitment of the auditors referred to in Section4.09(b) of the General Conditions | Due Date :11-Apr-2012
Finance Agreement: Financing Agreement, Schedule 2, Section IV, Paragraph B.1 (b) | Description: No withdrawals from the IDA creditshall be made in relation to any NGO, unless the Delegated Management Contract or Service Contract is acceptable to the Bank. |Frequency :Yearly
Finance Agreement: GEF Grant Agreement: Paragraph 5.01(d) | Description: The Foundation shall update its Administrative andFinancial Procedures Manual | Due Date :11-Jan-2012
Finance Agreement: Madagascar National Parks Project Agreement: Schedule, Section II, B(3) | Description: MNP shall establish anaudit committee; strengthen internal audit reporting arrangements; prepare a comprehensive annual internal audit plan; and submitquarterly audit reports | Frequency :Quarterly
44000-P073689
World Bank
International Development Association
MINISTRY OF TRANSPORT AND MINISTRY OF PUBLIC WORKS
International Development Association
MINISTRY OF TRANSPORT AND MINISTRY OF PUBLIC WORKSMADAGASCAR
Rural Transport Project
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Noroarisoa Rabefaniraka
nrabefaniraka@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Rural and Inter-Urban RoadsPorts/WaterwaysRailwaysOther TransportationLand Administration and ManagementBiodiversityLandscape ManagementRural Infrastructure and service deliveryRenewable Natural Resources Asset ManagementRural Development
International Development Association77082884Total Commitment in Fourth Quarter of 2002
International Development Association2917116Total Commitment in Fourth Quarter of 2002
International Development Association2250000Total Disbursement in Second Quarter of 2003
International Development Association306061Total Disbursement in Fourth Quarter of 2003
International Development Association555751Total Disbursement in Fourth Quarter of 2003
International Development Association-8930Total Interest Repayment in Fourth Quarter of 2003
International Development Association1762445Total Disbursement in First Quarter of 2004
International Development Association6153666Total Disbursement in First Quarter of 2004
International Development Association425990Total Disbursement in Second Quarter of 2004
International Development Association501119Total Disbursement in Second Quarter of 2004
International Development Association1971174Total Disbursement in Second Quarter of 2004
International Development Association-226660Total Interest Repayment in Second Quarter of 2004
International Development Association397381Total Disbursement in Third Quarter of 2004
International Development Association1503214Total Disbursement in Third Quarter of 2004
International Development Association1738114Total Disbursement in Third Quarter of 2004
International Development Association1502254Total Disbursement in Fourth Quarter of 2004
International Development Association4311567Total Disbursement in Fourth Quarter of 2004
International Development Association4974174Total Disbursement in Fourth Quarter of 2004
International Development Association-241860Total Interest Repayment in Fourth Quarter of 2004
International Development Association1837559Total Disbursement in First Quarter of 2005
International Development Association2665790Total Disbursement in First Quarter of 2005
International Development Association5180904Total Disbursement in First Quarter of 2005
International Development Association288084Total Disbursement in Second Quarter of 2005
International Development Association668125Total Disbursement in Second Quarter of 2005
International Development Association-232107Total Interest Repayment in Second Quarter of 2005
International Development Association680278Total Disbursement in Fourth Quarter of 2005
International Development Association1539018Total Disbursement in Fourth Quarter of 2005
International Development Association-225149Total Interest Repayment in Fourth Quarter of 2005
International Development Association263100Total Disbursement in First Quarter of 2006
International Development Association1123886Total Disbursement in First Quarter of 2006
International Development Association2459981Total Disbursement in First Quarter of 2006
International Development Association-1753178Total Disbursement in Second Quarter of 2006
International Development Association2735727Total Disbursement in Second Quarter of 2006
International Development Association-224634Total Interest Repayment in Second Quarter of 2006
International Development Association3291601Total Disbursement in Second Quarter of 2006
International Development Association569974Total Disbursement in Third Quarter of 2006
International Development Association2397503Total Disbursement in Third Quarter of 2006
International Development Association1185120Total Disbursement in Fourth Quarter of 2006
International Development Association2350202Total Disbursement in Fourth Quarter of 2006
International Development Association-247130Total Interest Repayment in Fourth Quarter of 2006
International Development Association137521Total Disbursement in First Quarter of 2007
International Development Association170657Total Disbursement in Second Quarter of 2007
International Development Association232629Total Disbursement in Second Quarter of 2007
International Development Association-237020Total Interest Repayment in Second Quarter of 2007
International Development Association468231Total Disbursement in Third Quarter of 2007
International Development Association739395Total Disbursement in Fourth Quarter of 2007
International Development Association1271740Total Disbursement in Fourth Quarter of 2007
International Development Association-245980Total Interest Repayment in Fourth Quarter of 2007
International Development Association155723Total Disbursement in First Quarter of 2008
International Development Association1416010Total Disbursement in First Quarter of 2008
International Development Association273268Total Disbursement in Second Quarter of 2008
International Development Association-254382Total Interest Repayment in Second Quarter of 2008
International Development Association1168845Total Disbursement in Fourth Quarter of 2008
International Development Association1215469Total Disbursement in Fourth Quarter of 2008
International Development Association-229323Total Interest Repayment in Fourth Quarter of 2008
International Development Association-219891Total Interest Repayment in Second Quarter of 2009
International Development Association-246292Total Interest Repayment in Fourth Quarter of 2009
International Development Association3345098Total Disbursement in Second Quarter of 2010
International Development Association-223113Total Interest Repayment in Second Quarter of 2010
International Development Association194694Total Disbursement in Third Quarter of 2010
International Development Association351722Total Disbursement in Third Quarter of 2010
International Development Association1363738Total Disbursement in Third Quarter of 2010
International Development Association18117Total Disbursement in Fourth Quarter of 2010
International Development Association36254Total Disbursement in Fourth Quarter of 2010
International Development Association-241894Total Interest Repayment in Fourth Quarter of 2010
International Development Association205597Total Disbursement in First Quarter of 2011
International Development Association5193Total Disbursement in Second Quarter of 2011
International Development Association108642Total Disbursement in Second Quarter of 2011
International Development Association-263974Total Interest Repayment in Second Quarter of 2011
International Development Association169105Total Disbursement in Third Quarter of 2011
International Development Association43585Total Disbursement in Fourth Quarter of 2011
International Development Association1653406Total Disbursement in Fourth Quarter of 2011
International Development Association2562744Total Disbursement in Fourth Quarter of 2011
International Development Association-262833Total Interest Repayment in Fourth Quarter of 2011
International Development Association10632Total Disbursement in First Quarter of 2012
International Development Association766894Total Disbursement in First Quarter of 2012
International Development Association1172139Total Disbursement in First Quarter of 2012
International Development Association44283Total Disbursement in Second Quarter of 2012
International Development Association959315Total Disbursement in Second Quarter of 2012
International Development Association-269977Total Interest Repayment in Second Quarter of 2012
International Development Association642138Total Disbursement in Third Quarter of 2012
International Development Association971312Total Disbursement in Third Quarter of 2012
International Development Association1829509Total Disbursement in Third Quarter of 2012
International Development Association739799Total Disbursement in Fourth Quarter of 2012
International Development Association2786684Total Disbursement in Fourth Quarter of 2012
International Development Association-283026Total Interest Repayment in Fourth Quarter of 2012
International Development Association-891880Total Loan Repayment in Fourth Quarter of 2012
International Development Association6958664Total Disbursement in First Quarter of 2013
International Development Association-1227948Total Commitment Cancellations in Second Quarter of 2013
International Development Association-98841Total Disbursement in Second Quarter of 2013
International Development Association-305594Total Interest Repayment in Second Quarter of 2013
International Development Association-871656Total Loan Repayment in Second Quarter of 2013
International Development Association-316706Total Interest Repayment in Fourth Quarter of 2013
International Development Association-880833Total Loan Repayment in Fourth Quarter of 2013
International Development Association-330505Total Interest Repayment in Second Quarter of 2014
International Development Association-889176Total Loan Repayment in Second Quarter of 2014
International Development Association-303863Total Interest Repayment in Fourth Quarter of 2014
International Development Association-844064Total Loan Repayment in Fourth Quarter of 2014
International Development Association-255575Total Interest Repayment in Second Quarter of 2015
International Development Association-816322Total Loan Repayment in Second Quarter of 2015
International Development Association-315717Total Interest Repayment in Fourth Quarter of 2015
International Development Association-797932Total Loan Repayment in Fourth Quarter of 2015
International Development Association-273174Total Interest Repayment in Second Quarter of 2016
International Development Association-810548Total Loan Repayment in Second Quarter of 2016
International Development Association-280476Total Interest Repayment in Fourth Quarter of 2016
International Development Association-786096Total Loan Repayment in Fourth Quarter of 2016
International Development Association-247854Total Interest Repayment in Second Quarter of 2017
International Development Association-795711Total Loan Repayment in Second Quarter of 2017
International Development Association-298869Total Interest Repayment in Fourth Quarter of 2017
International Development Association-813417Total Loan Repayment in Fourth Quarter of 2017
International Development Association-273708Total Interest Repayment in Second Quarter of 2018
International Development Association-819995Total Loan Repayment in Second Quarter of 2018
International Development Association-262946Total Interest Repayment in Fourth Quarter of 2018
International Development Association-796542Total Loan Repayment in Fourth Quarter of 2018
International Development Association-259996Total Interest Repayment in Second Quarter of 2019
International Development Association-796923Total Loan Repayment in Second Quarter of 2019Project Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportCredit AgreementAgreementAgreementContract AwardsProject URLProcurement Notices
Manakara
-22.1490 48.0110
Fianarantsoa
-21.4530 47.0860
Intermediate Results Indicator
At least 30% of the Road maintenance Fund resources are allocated to rural roads maintenance
Rural roads, including those financed by APL2
Average percentage between 2005 and 2010
Intermediate Results Indicator
Roads in good and fair condition as a share of total classified roads
Insufficient maintenance of rehabilitation roads
This data couldn't be validated by the Ministry. A physical inventory of the rural roads rehabilitated by the project.
Intermediate Results Indicator
Number of bridges rehabilitated
This indicator has been added to reflect additional activities
Works are scheduled to start during the second semester of this year
Intermediate Results Indicator
Number of jetties built
This indicator has been added to reflect additional activities
Works are scheduled to start during the second semester of this year
Intermediate Results Indicator
Rural roads unit has been created and is operational
However, RRU was operational from 2003 to 2005, as CTR (Cellule des Transports Ruraux) within the SE/PST, zns as CSSR (Cellule deSuivi des Routes Rurales) within the Road Authority, from 2006 to 2008
Ministry to decide RRU creation by the end of 2011
But Road Authority still functional
Intermediate Results Indicator
Roads rehabilitated, Rural
All rural roads (RNT, RP & RC) = 24,299 km - Rural roads to be rehabilitated by APL2: initial objective 9,000 km; revisedobjective 1,500 km, then 1400 km
Objective achieved up to 89% in 2008. No additional financing for rural roads.
Linear km rehabilitated: 1335 km in 2008.
Intermediate Results Indicator
Size of the total classified network
PDO Indicator
Size of the total classified network
PDO Indicator
Accessibility improved, especially in rural areas (from APL 1)
15.5 vehicles per day38,8 bicycles per day14,6 carts per day(Data collected based on manual counting on 4 selected roads)
33. 22 vehicles per day (+10% p.a. since 2001)Overall, the objectives have been achieved since 2007.
Updated results expected during second semester
PDO Indicator
Direct project beneficiaries
Of which 636.000 females, for 1,086km rehabilitated. Source : Road Authority & Consultant, in 2006.
Of which 640,000 females for 1,500 Km of roads rehabilitated
Of which 640,000 females for 1,500 Km of roads rehabilitated
PDO Indicator
Roads in good and fair condition as a share of total classified roads
Size of the total classified network: 38,000Km. Rural roads:24,299Km, of which 2,920 Km (12%) in good and fair condition
Objective 20% revised (too ambitious as road investment financings were suspended by all Donors since 2009).
Ministry and Road Authority carry out a new inventory: However, due to inaccessibility of most roads + lack of staff available,they could carry out only 17 % of the total rural roads. Results should be available by the end of this year
PDO Indicator
Reduction of average transit time in rehabilitated rural roads
10.53 minutes/ km(Data collected based on manual counting on 7 selected roads)
6.8 minutes/ km
5.17minutes / KmThe objectives of reduced average transit time by 20% have been largely achieved.
PDO Indicator
Improved accessibility from remote areas of the country to the main production and consumption centers
Not available. Ministry could not find the baseline data calculation and is unable to give current and target values
PDO Indicator
Female beneficiaries
0.00
0.00
641405.83
641405.83
641405.81
641405.83
641405.83
641405.81
1274025.27
1274025.27
1274025.25
1274025.27
1274025.27
1274025.25
1274025.27
1274025.27
1274025.25
1274025.27
1274025.27
1274025.25
1397034.60
1397034.60
1397034.60
1397034.60
1397034.60
1397034.60
1397034.60
1397034.60
1397034.60
1397034.60
1397034.60
1397034.60
1335529.92
1335529.92
1335529.94
1335529.92
1335529.92
1335529.94
1335529.92
1335529.92
1335529.94
1335529.92
1335529.92
1335529.94
1098297.63
1098297.63
1098297.65
1098297.63
1098297.63
1098297.65
1098297.63
1098297.63
1098297.65
1098297.63
1098297.63
1098297.65
878638.12
878638.12
878638.10
878638.12
878638.12
878638.10
878638.12
878638.12
878638.10
878638.12
878638.12
878638.10
724876.44
724876.44
724876.44
724876.44
724876.44
724876.44
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.01
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
750000.00
750000.00
750000.00
0.00
0.00
0.00
287270.62
287270.62
287270.62
2638703.84
2638703.84
2638703.85
966094.13
966094.13
966094.12
1212902.91
1212902.91
1212902.91
3595998.32
3595998.32
3595998.31
3228084.33
3228084.33
3228084.33
318736.46
318736.46
318736.45
0.00
0.00
0.00
739765.21
739765.21
739765.20
1282322.31
1282322.31
1282322.30
1424716.72
1424716.72
1424716.72
989158.91
989158.91
989158.90
1178440.59
1178440.59
1178440.59
45840.31
45840.31
45840.30
134428.74
134428.74
134428.75
156077.10
156077.10
156077.10
670378.35
670378.35
670378.35
523910.98
523910.98
523910.99
74077.79
74077.79
74077.77
0.00
0.00
0.00
794771.29
794771.29
794771.29
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1115032.78
1115032.78
1115032.77
636717.95
636717.95
636717.96
833570.38
833570.38
833570.38
566666.67
566666.67
566666.66
506666.67
506666.67
506666.66
500000.00
500000.00
500000.00
409000.00
409000.00
409000.00
342333.33
342333.33
342333.34
333333.33
333333.33
333333.34
202666.67
202666.67
202666.66
142333.33
142333.33
142333.34
66666.67
66666.67
66666.66
0.00
0.00
0.00
0.00
0.00
0.00
44000-P160866
World Bank
International Development Association
MINISTRY OF FINANCE AND BUDGET
International Development Association
MINISTRY OF FINANCE AND BUDGETMADAGASCAR
MG - Public Finance Sustainability and Investment DPF
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Faniry Nantenaina Razafimanantsoa Harivelo
frazafimanantsoa@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Central Government (Central Agencies)Fiscal PolicyInvestment and Business ClimateFiscal sustainabilityBusiness Enabling Environment
International Development Association65000000Total Commitment in Fourth Quarter of 2016
International Development Association62329830Total Disbursement in Fourth Quarter of 2016Financing AgreementContract AwardsProject URLProcurement Notices
0.00
0.00
44000-P163870
World Bank
International Development Association
International Development Association
MADAGASCAR
Madagascar - Least-Cost Electricity Access Development Project - LEAD
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Jan Friedrich Kappen
jkappen@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Public Administration - Energy and ExtractivesRenewable Energy SolarEnergy Transmission and DistributionEnergyAccess to EnergyEnergy Policies & ReformMitigationClimate change
International Development Association150000000Total Commitment in First Quarter of 2019Implementation Status and Results ReportFinancing AgreementContract AwardsProject URLProcurement Notices
Toamasina
-18.1490 49.4020
Mahajanga
-15.7170 46.3170
Fianarantsoa
-21.4530 47.0860
Antakotako
-15.3170 49.8000
Andapa District
-14.6500 49.6500
Antananarivo Province
-18.7500 46.7500
Sambava
-14.2170 49.8470
Nosy Be
-13.3420 48.2580
Intermediate Results Indicator
Households provided with new on-grid electricity access
Intermediate Results Indicator
Beneficiaries of job-focused interventions
Intermediate Results Indicator
Households and businesses provided with new off-grid electricity access
Intermediate Results Indicator
Number of SMEs with a loan or line of credit
Intermediate Results Indicator
Volume of results-based financing channeled to private companies
Intermediate Results Indicator
Volume of debt financing extended to private companies (cumulative)
Intermediate Results Indicator
Number of participating participating firms and financial Institutions under the OMDF
Intermediate Results Indicator
Enterprises provided with new on-grid electricity service
Intermediate Results Indicator
Enterprises provided with new off-grid electricity service
Intermediate Results Indicator
Health centers provided with new or improved electricity access
Intermediate Results Indicator
Health centers provided with new on-grid electricity service
Intermediate Results Indicator
Beneficiaries reached with financial services
Intermediate Results Indicator
Beneficiaries reached with financial services, of which: female borrowers
Intermediate Results Indicator
Response rate to GRM complaints
Intermediate Results Indicator
Monitoring in place of follow-up actions by participants of job-focused interventions
Intermediate Results Indicator
Public availability of customer satisfaction survey
Intermediate Results Indicator
Consumer awareness campaign completed
Intermediate Results Indicator
New connection policy for grid connections approved
Intermediate Results Indicator
Lighting Global quality standards for solar home systems adopted and published
Intermediate Results Indicator
The Board of JIRAMA approves a financial recovery plan for the company
Intermediate Results Indicator
Geospatial analysis and planning platform established and operational
Intermediate Results Indicator
National Electrification Investment Plan developed and adopted
Intermediate Results Indicator
OMDF has operational tracking system to monitor portfolio quality of loans/credit extended by participating FIs and OGS companies
Intermediate Results Indicator
Generation capacity of energy constructed or rehabilitated
Intermediate Results Indicator
Renewable energy generation capacity (other than hydropower) constructed under the project
PDO Indicator
People provided with new or improved electricity service
PDO Indicator
Enterprises provided with new or improved electricity services
PDO Indicator
Health centers provided with new or improved electricity services
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
176250.00
412350.00
484500.00
556500.00
621150.00
679800.00
759150.00
854400.00
916050.00
946350.00
481200.00
989400.00
1017000.00
1025400.00
1003800.00
987600.00
1009200.00
1069050.00
1139550.00
1171050.00
1230450.00
651900.00
1363800.00
1421550.00
1505250.00
1621350.00
1702500.00
1742550.00
1832550.00
1971000.00
2073600.00
1064250.00
2218050.00
2374350.00
2544300.00
2688300.00
2838600.00
2988600.00
3160050.00
3327450.00
3462150.00
1771050.00
3618300.00
3766350.00
3893850.00
4006800.00
4148700.00
4312500.00
4415700.00
4481250.00
2256300.00
4556100.00
4648200.00
4718700.00
4782000.00
4872900.00
4956900.00
5032950.00
5108250.00
5185050.00
5263500.00
4122300.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
176250.00
412350.00
484500.00
556500.00
621150.00
679800.00
759150.00
854400.00
916050.00
946350.00
481200.00
989400.00
1017000.00
1025400.00
1003800.00
987600.00
1009200.00
1069050.00
1139550.00
1171050.00
1230450.00
651900.00
1363800.00
1421550.00
1505250.00
1621350.00
1702500.00
1742550.00
1832550.00
1971000.00
2073600.00
1064250.00
2218050.00
2374350.00
2544300.00
2688300.00
2838600.00
2988600.00
3160050.00
3327450.00
3462150.00
1771050.00
3618300.00
3766350.00
3893850.00
4006800.00
4148700.00
4312500.00
4415700.00
4481250.00
2256300.00
4556100.00
4648200.00
4718700.00
4782000.00
4872900.00
4956900.00
5032950.00
5108250.00
5185050.00
5263500.00
4122300.00
FA, Schedule 2, Section I, A, 5: The Recipient shall, not later than three (3) months from the Effective Date, appoint anindependent verification agent, with qualifications, experience and under terms of reference acceptable to the Association.
FA, Schedule 2, Section I, E, 4a: The Recipient shall, and shall cause JIRAMA and/or any pertinent Project service providers, atall times throughout the period of Project implementation to take all measures necessary on its part to collect, compile, andfurnish to the Association through Project Reports, and promptly in a separate report or reports, if so requested by theAssociation, information on the status of compliance with the ESMF and RPF and the management tools and instruments referred totherein, all such reports in form and substance acceptable to the Association, setting out, among other things: (i) the status ofimplementation of the ESMF/RPF; (ii) conditions, if any, which interfere or threaten to interfere with the implementation of theESMF/RPF; and (iii) corrective and preventive measures taken or required to be taken to address such conditions.
FA, Schedule 2, Section II: The Recipient shall furnish to the Association each Project Report not later than one month after theend of each calendar semester, covering the calendar semester.
44000-P153084
World Bank
International Development Association
MFB
International Development Association
MFBMADAGASCAR
MG - Resilience DPO
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Faniry Nantenaina Razafimanantsoa Harivelo
frazafimanantsoa@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Central Government (Central Agencies)Other Public AdministrationFiscal sustainabilityTax policyPublic Finance ManagementPublic Expenditure PolicyMacroeconomic ResilienceMonetary and Credit PoliciesDebt ManagementMacro-financial policiesExternal FinanceFiscal Policy
International Development Association55000000Total Commitment in Fourth Quarter of 2015
International Development Association54642284Total Disbursement in Fourth Quarter of 2015
International Development Association-137273Total Interest Repayment in Second Quarter of 2016
International Development Association-207463Total Interest Repayment in Fourth Quarter of 2016
International Development Association-199235Total Interest Repayment in Second Quarter of 2017
International Development Association-211954Total Interest Repayment in Fourth Quarter of 2017
International Development Association-211967Total Interest Repayment in Second Quarter of 2018
International Development Association-204802Total Interest Repayment in Fourth Quarter of 2018
International Development Association-204728Total Interest Repayment in Second Quarter of 2019Implementation Completion and Results ReportImplementation Completion Report ReviewFinancing AgreementContract AwardsProject URLProcurement Notices
0.00
0.00
44000-P166752
World Bank
International Development Association
International Development Association
MADAGASCAR
Fiscal Sustainability and Energy Development Policy Operation
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Natasha Sharma
nsharma9@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Other Energy and ExtractivesOther Public AdministrationCentral Government (Central Agencies)Energy EfficiencyEnergy Policies & ReformEnergyDebt ManagementPublic Finance ManagementMitigationFiscal sustainabilityState-owned Enterprise Reform and PrivatizationTransparency, Accountability and Good GovernancePublic Assets and Investment ManagementFiscal PolicyClimate changePublic Administration
International Development Association100000000Total Commitment in Second Quarter of 2019
International Development Association98720648Total Disbursement in Third Quarter of 2019Project Information DocumentFinancing AgreementContract AwardsProject URLProcurement Notices
0.00
0.00
44000-P160071
World Bank
International Development Association
International Development Association
MADAGASCAR
Madagascar-Statistical Capacity Building
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Abdoullahi Beidou
abeidou@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
ICT InfrastructureCentral Government (Central Agencies)Data production, accessibility and useInstitutional strengthening and capacity buildingData Development and Capacity Building
International Development Association30000000Total Commitment in First Quarter of 2017
International Development Association3500000Total Disbursement in Third Quarter of 2017
International Development Association408283Total Disbursement in Fourth Quarter of 2017
International Development Association1429370Total Disbursement in Fourth Quarter of 2017
International Development Association2514044Total Disbursement in Fourth Quarter of 2017
International Development Association337731Total Disbursement in First Quarter of 2018
International Development Association369086Total Disbursement in First Quarter of 2018
International Development Association12102575Total Disbursement in First Quarter of 2018
International Development Association-14523Total Interest Repayment in First Quarter of 2018
International Development Association571065Total Disbursement in Second Quarter of 2018
International Development Association4806919Total Disbursement in Second Quarter of 2018
International Development Association5397609Total Disbursement in Second Quarter of 2018
International Development Association326434Total Disbursement in Third Quarter of 2018
International Development Association-67837Total Interest Repayment in Third Quarter of 2018
International Development Association280456Total Disbursement in Fourth Quarter of 2018
International Development Association-122357Total Interest Repayment in First Quarter of 2019
International Development Association-117626Total Interest Repayment in Third Quarter of 2019Project Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Republic of Madagascar
-20.0000 47.0000
Institut National de la Statistique
-18.9180 47.5210
Intermediate Results Indicator
Number of staff who have achieved improvements in skill/knowledge compared to a pre-training baseline
Intermediate Results Indicator
Number of census, welfare, employment, and business surveys implemented
Intermediate Results Indicator
Number of statistical reports funded by the project available online, disaggregated by availability of gendered statistics
Intermediate Results Indicator
Number of survey and census micro-datasets available online
Intermediate Results Indicator
Improved national accounts and CPI
Intermediate Results Indicator
Focus groups held to gather feedback on the quality, relevance and timeliness of statistics
PDO Indicator
Increase in the Statistical Capacity Index (SCI) score for the SCI variables that the project will influence
PDO Indicator
Number of statistical products that are released according to the statistical release calendar
PDO Indicator
Number of statistical products supported by the project designed and implemented in line with international standards
PDO Indicator
Number of views of anonymized micro-datasets available online
1862835.50
1862835.50
1651250.00
1651250.00
1651250.00
1651250.00
1651250.00
1651250.00
1651250.00
1651250.00
1651250.00
1651250.00
1651250.00
1651250.00
197083.33
197083.33
197083.33
197083.33
197083.33
197083.33
197083.33
197083.33
197083.33
197083.33
197083.33
197083.33
97083.33
97083.33
97083.33
97083.33
97083.33
97083.33
97083.33
97083.33
97083.33
97083.33
97083.33
97083.33
172083.33
172083.33
172083.33
172083.33
172083.33
172083.33
172083.33
172083.33
172083.33
172083.33
172083.33
172083.33
108041.12
108041.12
108041.12
108041.12
108041.12
108041.12
108041.12
108041.28
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1750000.00
1750000.00
2185416.67
2185416.67
2185416.67
2185416.67
2185416.67
2185416.67
2185416.67
2185416.67
2185416.67
2185416.67
2185416.67
2185416.63
22916.67
22916.67
22916.67
22916.67
22916.67
22916.67
22916.67
22916.67
22916.67
22916.67
22916.67
22916.63
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
44000-P113134
World Bank
International Development Association
FONDS D'INTERVENTION POUR LE DEVELOPPEMENT (FID)
International Development Association
FONDS D'INTERVENTION POUR LE DEVELOPPEMENT (FID)MADAGASCAR
Madagascar - Emergency Food Security and Reconstruction Project
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Andrea Vermehren
avermehren@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Primary EducationOther Water Supply, Sanitation and Waste ManagementSocial ProtectionRural and Inter-Urban RoadsPublic Administration - Social ProtectionDisaster PreparednessFood SecurityRural Infrastructure and service deliveryDisaster Response and RecoveryDisaster Risk ManagementDisaster Risk ReductionDisaster Risk FinanceRural DevelopmentJobsNutrition and Food SecurityFinance for Development
International Development Association40000000Total Commitment in Fourth Quarter of 2008
International Development Association3117726Total Disbursement in Fourth Quarter of 2009
International Development Association1163996Total Disbursement in First Quarter of 2010
International Development Association3141631Total Disbursement in Second Quarter of 2010
International Development Association6355216Total Disbursement in Third Quarter of 2010
International Development Association-24395Total Interest Repayment in Third Quarter of 2010
International Development Association10936118Total Disbursement in Fourth Quarter of 2010
International Development Association-69724Total Interest Repayment in First Quarter of 2011
International Development Association2198159Total Disbursement in Third Quarter of 2011
International Development Association-97676Total Interest Repayment in Third Quarter of 2011
International Development Association1600000Total Disbursement in Fourth Quarter of 2011
International Development Association4147056Total Disbursement in First Quarter of 2012
International Development Association-103570Total Interest Repayment in First Quarter of 2012
International Development Association1665675Total Disbursement in Second Quarter of 2012
International Development Association3233984Total Disbursement in Third Quarter of 2012
International Development Association-119445Total Interest Repayment in Third Quarter of 2012
International Development Association1074913Total Disbursement in Fourth Quarter of 2012
International Development Association2568021Total Disbursement in First Quarter of 2013
International Development Association-141561Total Interest Repayment in First Quarter of 2013
International Development Association314245Total Disbursement in Second Quarter of 2013
International Development Association-149817Total Interest Repayment in Third Quarter of 2013
International Development Association-155954Total Interest Repayment in First Quarter of 2014
International Development Association-154446Total Interest Repayment in Third Quarter of 2014
International Development Association-142798Total Interest Repayment in First Quarter of 2015
International Development Association-140051Total Interest Repayment in Third Quarter of 2015
International Development Association-139556Total Interest Repayment in First Quarter of 2016
International Development Association-140758Total Interest Repayment in Third Quarter of 2016
International Development Association-136517Total Interest Repayment in First Quarter of 2017
International Development Association-140865Total Interest Repayment in Third Quarter of 2017
International Development Association-145877Total Interest Repayment in First Quarter of 2018
International Development Association-145193Total Interest Repayment in Third Quarter of 2018
International Development Association-136734Total Interest Repayment in First Quarter of 2019
International Development Association-374889Total Loan Repayment in First Quarter of 2019
International Development Association-140323Total Interest Repayment in Third Quarter of 2019
International Development Association-368430Total Loan Repayment in Third Quarter of 2019Project Information DocumentImplementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportContract AwardsProject URLProcurement Notices
Intermediate Results Indicator
IRI 4.4 Completion of a technical audit
A technical audit has been finalized in December 2011.
Intermediate Results Indicator
IRI 4.5 Completion of an impact evaluation
This is the second phase of the impact evaluation of the Community development Fund Project. This impact evaluation -- conductedbyINSTAT -- could not be finalized before due to the
Intermediate Results Indicator
IRI 4.6 Assessment of cash-for-work
Intermediate Results Indicator
IRI 4.7 Assessment of post-cyclone reconstruction
Intermediate Results Indicator
Health facilities constructed, renovated, and/or equipped (number)
This indicator relates to component 2 and 3.
The number of health facilities is below target because communes have generally prioritized the reconstruction of schools.
Intermediate Results Indicator
Number of additional classrooms built or rehabilitated at the primary level resulting from project interventions.
This indicator relates to all micro-Projects implemented under this Project.
Intermediate Results Indicator
IRI 1.2 Social protection sub-projects completed
This indicator relates to the cash-for-work program (Component 1) which was authorized in November 2009.
Intermediate Results Indicator
IRI 1.4 Percentage of women among beneficiaries
This indicator relates to the cash-for-work program (Component 1) which was authorized in November 2009.
Intermediate Results Indicator
IRI 2.1 Community-based sub-projects completed
This indicator relates to the community-based infrastructure component (Component 2) which was authorized in May 2010.
Intermediate Results Indicator
IRI 4.2 Sub-projects completed within contracted period
This indicators relate to the micro-projects implemented under components 2 and 3.
Intermediate Results Indicator
IRI 2.2 Beneficiaries from sub-projects
This indicator relates to the community-based infrastructure component (Component 2) which was authorized in May 2010.
This indicator is above target as numerous communities have selected "feeder roads" which have comparatively more beneficiariesthan other sub-project types.
Intermediate Results Indicator
IRI 3.1 Sub-projects rehabilitated or reconstructed
This indicator relates to post-catastrophe reconstruction (Component 3) which was authorized in May 2010.
Intermediate Results Indicator
IRI 3.2 Schools reconstructed or rehabilitated
This indicator relates to post-catastrophe reconstruction (Component 3) which was authorized in May 2010.
Intermediate Results Indicator
IRI 3.3 Classrooms built and/or rehabilitated
This indicator relates to post-catastrophe reconstruction (Component 3) which was authorized in May 2010.
Intermediate Results Indicator
IRI 3.4 Health centers built or rehabilitated
This indicator relates to post-catastrophe reconstruction which was authorized in May 2010.
Communes have comparatively preferred to prioritize schools (instead of health centers) during project implementation.
Intermediate Results Indicator
IRI 4.1 Management costs
This activity relates to Project management (Component 4) which was authorized to disburse in November 2009.
Intermediate Results Indicator
IRI 1.3 Roads rehabilitated, rural areas
This indicator relates to the roads rehabilitated under the cash-for-work program which was authorized in November 2009.
Intermediate Results Indicator
IRI 2.4 Roads rehabilitated, rural areas
This indicator relates to community-based infrastructure component (Component 2) which was authorized in May 2010.
Intermediate Results Indicator
IRI 3.5 Roads rehabilitated, rural areas
This indicator relates to post-catastrophe reconstruction (Component 3) which was authorized in May 2010.
Communes have prioritized the rehabilitation of schools (instead of that of roads) during project implementation.
Intermediate Results Indicator
Roads rehabilitated, Rural
This indicator relates to all micro-Projects implemented under this Project.
Intermediate Results Indicator
IRI 1.5 People in Project areas benefitting from improved roads implemented under the cash-for-work program
This indicator relates to the cash-for-work program (Component 1) which was authorized in November 2009.
The end-of-project target was not defined during Project preparation as the choice of micro-project type is not known a priori butdepends on community's selection during Project implementation.
Intermediate Results Indicator
IRI 1.1 Person-days of employment created (million)
This indicator relates to the cash-for-work program (Component 1) which was authorized in November 2009.
Intermediate Results Indicator
IRI 2.3 Irrigated land rehabilitated
This indicator relates to the community-based infrastructure component (Component 2) which was authorized in May 2010.
This indicator is below target as few communities have selected the rehabilitation or irrigated land as a sub-project type.
PDO Indicator
I.1. Beneficiaries of cash-for-work program
This activity (Component 1) was authorized in November 2009.
This indicator is above end-of-project target partially because FID initially authorized the rotation of workers duringmicro-project execution.
PDO Indicator
I.2. Initiated social and economic services restored within 6 months following a natural disaster
This activity (Component 3) was authorized in May 2010.
This ratio corresponds to the micro-projects that have been implemented to respond to the 2011/12 cyclone season. Theprioritization of the micro-project by the commune is taken as the beginning of the 6 months. More specifically, FID has been ableto rehabilitate within six-month 56% of the sub-projects that it was responsible to implement in the aftermath of the 2011/12cyclone season.
PDO Indicator
Female beneficiaries
PDO Indicator
Roads rehabilitated, Rural
This activity (related to Components 1, 2 and 3) was authorized in November 2009.
The end-of-project target has not been defined as the choice of micro-project type is not known a priori but depends oncommunity'sselection during Project implementation.
PDO Indicator
Direct project beneficiaries
Components 1 and 4 of the Project were authorized to resume in November 2009.
This indicator is above end-of-project targets because in part FID initially authorized the rotation of workers during theimplementation of the cash-for-work program (see below the indicator related to the number of beneficiaries of the cash-for-workprogram).
PDO Indicator
Improved community water points constructed or rehabilitated under the project
This activity (related to Components 2 and 3) was authorized in May 2010.
The end-of-project target was not defined during Project preparation as the choice of micro-project type is not known a priori butdepends on community's selection during Project implementation.
PDO Indicator
People in Project areas benefiting from improved roads
This activity (related to Components 1, 2 and 3) was authorized in November 2009.
The end-of-project target has not been defined as the choice of micro-project type is not known a priori but depends oncommunity'sselection during Project implementation.
PDO Indicator
Number of people in rural areas provided with access to Improved Water Sources under the project
This activity (related to Components 2 and 3) was authorized in May 2010.
The end-of-project target has not been defined as the choice of micro-project type is not known a priori but depends oncommunity'sselection during Project implementation.
1166666.67
1166666.67
1166666.66
1166666.67
1166666.67
1166666.66
1083333.33
1083333.33
1083333.34
1083333.33
1083333.33
1083333.34
1083333.33
1083333.33
1083333.34
1083333.33
1083333.33
1083333.34
1083333.33
1083333.33
1083333.34
1083333.33
1083333.33
1083333.34
1083333.33
1083333.33
1083333.34
1083333.33
1083333.33
1083333.34
1166666.67
1166666.67
1166666.66
1166666.67
1166666.67
1166666.66
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1039075.46
1039075.46
1039075.46
387998.72
387998.73
387998.73
1047210.22
1047210.22
1047210.23
2118405.39
2118405.40
2118405.40
3645372.65
3645372.65
3645372.66
0.00
0.00
0.00
0.00
0.00
0.00
826989.59
826989.59
826989.59
826989.59
826989.59
826989.59
826989.59
826989.59
826989.59
826989.59
826989.59
826989.59
826989.59
826989.59
826989.59
826989.59
826989.59
826989.59
66666.66
66666.67
66666.67
66666.66
66666.67
66666.67
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
44000-P150116
World Bank
International Development Association
MINISTRY OF FINANCE ECONOMY AND BUDGET
International Development Association
MINISTRY OF FINANCE ECONOMY AND BUDGETMADAGASCAR
Public Sector Performance Project
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Tiago Carneiro Peixoto
tpeixoto@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Public Administration - EducationPublic Administration - Energy and ExtractivesCentral Government (Central Agencies)Sub-National GovernmentPublic Expenditure ManagementMunicipal Institution BuildingTransparency, Accountability and Good GovernanceFragility, Conflict and ViolenceDomestic Revenue AdministrationTax policyFiscal PolicyPublic Finance ManagementPublic Administration
International Development Association40000000Total Commitment in Second Quarter of 2016
International Development Association712405Total Disbursement in Second Quarter of 2017
International Development Association750000Total Disbursement in Second Quarter of 2017
International Development Association181495Total Disbursement in Fourth Quarter of 2017
International Development Association431435Total Disbursement in Fourth Quarter of 2017
International Development Association-5863Total Interest Repayment in Fourth Quarter of 2017
International Development Association19108Total Disbursement in First Quarter of 2018
International Development Association47595Total Disbursement in First Quarter of 2018
International Development Association7740209Total Disbursement in First Quarter of 2018
International Development Association258603Total Disbursement in Second Quarter of 2018
International Development Association271616Total Disbursement in Second Quarter of 2018
International Development Association-28929Total Interest Repayment in Second Quarter of 2018
International Development Association186139Total Disbursement in Third Quarter of 2018
International Development Association243281Total Disbursement in Third Quarter of 2018
International Development Association240099Total Disbursement in Fourth Quarter of 2018
International Development Association5640837Total Disbursement in Fourth Quarter of 2018
International Development Association-38757Total Interest Repayment in Fourth Quarter of 2018
International Development Association150425Total Disbursement in First Quarter of 2019
International Development Association23307Total Disbursement in Second Quarter of 2019
International Development Association116084Total Disbursement in Second Quarter of 2019
International Development Association131786Total Disbursement in Second Quarter of 2019
International Development Association-59363Total Interest Repayment in Second Quarter of 2019
International Development Association171911Total Disbursement in Third Quarter of 2019Project Information DocumentProject Information DocumentProject Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Republic of Madagascar
-20.0000 47.0000
Antananarivo
-23.9830 46.1830
Sofia Region
-15.2000 48.4000
Alaotra Mangoro Region
-17.9000 48.4000
Analamanga Region
-18.4500 47.5000
Intermediate Results Indicator
High/substantial risks audits completed by Internal Audit Departments
Intermediate Results Indicator
Number of revenue offices that have been subject to external evaluation of their performance contracts/program
Intermediate Results Indicator
Semiannual public debates on the budget law, the performance of revenue agencies and project performance led by CSOs.
Intermediate Results Indicator
Improved taxpayers registration
Intermediate Results Indicator
Establishment of a single administrative identification number
Intermediate Results Indicator
Improved formalization of small-scale miners
Intermediate Results Indicator
Share of schools targeted by the component with an operational FEFFI, planning and implementing PECs
Intermediate Results Indicator
Increased rate of confirmed suspicious customs transactions related to home use at Tomasina Custom Office (in case of physical examination).
Intermediate Results Indicator
Improved recovery of revenue (not including grants) by local governments
Intermediate Results Indicator
Percentage of FRAM teachers in the areas selected by the component receiving subsidies with less than two months of delay
Intermediate Results Indicator
Modernization of the Integrated Tax Administration System (ITAS)
Intermediate Results Indicator
Improved timeliness of service-delivery fiscal transfers to local governments
Intermediate Results Indicator
Timely availability of the Court of Acccount (CA) public report (process indicator)
PDO Indicator
Direct Project Beneficiaries (number), of which female (percentage) (Number, Custom)
PDO Indicator
Availability of a teachers' information management system (Text, Custom)
PDO Indicator
TADAT PO-8 indicators "Efficient Revenue Management" rated B (Text, Custom)
PDO Indicator
Increased tax revenue collection (Domestic tax revenue/GDP ratio)
PDO Indicator
Communes with IGL higher than 6 (Percentage, Custom)
1600000.00
894166.67
894166.67
894166.67
894166.67
894166.67
894166.67
894166.67
894166.67
894166.67
894166.67
894166.67
894166.67
829166.67
829166.67
829166.67
829166.67
829166.67
829166.67
829166.67
829166.67
829166.67
829166.67
829166.67
829166.67
826666.67
826666.67
826666.67
826666.67
826666.67
826666.67
826666.67
826666.67
826666.67
826666.67
826666.67
826666.67
650000.00
650000.00
650000.00
650000.00
650000.00
650000.00
650000.00
650000.00
650000.00
650000.00
650000.00
650000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1600000.00
894166.67
894166.67
894166.67
894166.67
894166.67
894166.67
894166.67
894166.67
894166.67
894166.67
894166.67
894166.67
829166.67
829166.67
829166.67
829166.67
829166.67
829166.67
829166.67
829166.67
829166.67
829166.67
829166.67
829166.67
826666.67
826666.67
826666.67
826666.67
826666.67
826666.67
826666.67
826666.67
826666.67
826666.67
826666.67
826666.67
650000.00
650000.00
650000.00
650000.00
650000.00
650000.00
650000.00
650000.00
650000.00
650000.00
650000.00
650000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Finance Agreement :Establishment of a Procurement complaint handling mechanism | Description : Schedule 2, Section III, EBy nolater than three (3) months after the Effective Date, the Recipient shall have established a procurement complaint handlingmechanism acceptable to the Association. | Due Date :01-Feb-2017
Finance Agreement :External auditor | Description :Schedule 2, Section V, 1 By no later than six (6) months after the EffectiveDate, the Recipient shall recruit an external auditor pursuant to terms of reference satisfactory to the Association. | Due Date:01-May-2017
Finance Agreement :Qualified accountant and a procurement assistant six (6) months after the Effect | Description :Schedule 2,Section V, 2 By no later than six (6) months after the Effective Date, the Recipient shall recruit a qualified accountant and aprocurement assistant at the PREA Coordination unit pursuant to terms of reference satisfactory to the Association. | Due Date:01-May-2017
Finance Agreement :Accounting information management system three (3) months after the Effective da | Description :Schedule 2,Section V, 3 By no later than three (3) months after the Effectiveness Date, the Recipient shall have installed an accountinginformation management system satisfactory to the Association. | Due Date :01-Feb-2017
44000-P161491
World Bank
International Development Association
International Development Association
MADAGASCAR
Madagascar Financial Inclusion Project
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Djibrilla Adamou Issa
dissa1@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Banking InstitutionsPublic Administration - Financial SectorGenderJobsCredit InfrastructureJob CreationMSME FinancePayment & markets infrastructureFinancial inclusionICT SolutionsICTFinancial Infrastructure and Access
International Development Association45000000Total Commitment in First Quarter of 2018
International Development Association400792Total Disbursement in Fourth Quarter of 2018
International Development Association2500000Total Disbursement in Fourth Quarter of 2018
International Development Association3635246Total Disbursement in Fourth Quarter of 2018
International Development Association11443Total Disbursement in First Quarter of 2019
International Development Association1537328Total Disbursement in First Quarter of 2019
International Development Association21987Total Disbursement in Second Quarter of 2019
International Development Association50726Total Disbursement in Second Quarter of 2019
International Development Association2105566Total Disbursement in Second Quarter of 2019
International Development Association-23445Total Interest Repayment in Second Quarter of 2019
International Development Association30689Total Disbursement in Third Quarter of 2019
International Development Association444292Total Disbursement in Third Quarter of 2019Project Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Mahasoakely
-19.1670 45.2330
Republic of Madagascar
-20.0000 47.0000
Antananarivo
-18.9140 47.5360
Diana Region
-13.5000 49.0000
Sava Region
-14.2000 49.8000
Analanjirofo Region
-16.5000 49.5000
Betsiboka Region
-17.2000 47.1000
Alaotra Mangoro Region
-17.9000 48.4000
Vakinankaratra Region
-19.7000 46.9000
Itasy Region
-18.9500 46.9500
Analamanga Region
-18.4500 47.5000
Atsinanana Region
-19.0000 48.9000
Anosy Region
-24.1000 46.3000
Intermediate Results Indicator
The number of MFIs that allow loan repayment through a mobile money account (“wallet-to-account”)
Intermediate Results Indicator
Number of enterprises reached with BDS
Intermediate Results Indicator
Number of women-led enterprises reached with BDS
Intermediate Results Indicator
Percentage of loans extended to MSMEs registered under the portfolio guarantee that are non-performing
Intermediate Results Indicator
Percentage of banks and microfinance institutions reporting data to the CBSF on financial consumer complaints
Intermediate Results Indicator
Shared MIS developed and operational
Intermediate Results Indicator
National Switch developed and operational
Intermediate Results Indicator
Banks and MFIs report data to a centralized electronic collateral registry
Intermediate Results Indicator
Report drafted annually on Citizen Engagement Survey
260000.00
260000.00
260000.00
260000.00
260000.00
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.63
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.37
891666.67
891666.67
891666.67
891666.67
891666.67
891666.67
891666.67
891666.67
891666.67
891666.67
891666.67
891666.63
0.00
0.00
0.00
0.00
0.00
0.00
0.00
260000.00
260000.00
260000.00
260000.00
260000.00
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.63
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.33
833333.37
891666.67
891666.67
891666.67
891666.67
891666.67
891666.67
891666.67
891666.67
891666.67
891666.67
891666.67
891666.63
0.00
0.00
0.00
0.00
0.00
0.00
0.00
The Recipient shall furnish to the Association, as soon as available, but in any case not later than November 30 of each year, theannual work plans and budgets approved by the Steering Committee and the evidences referred to in subparagraph 1(b) of theFinancingAgreement, for the Association's review and approval; except for the Annual Work Plan and Budget for the Project for thefirst year of Project implementation, and the evidence which may be required for the implementation of the activities included inthe draft Annual Work Plan and Budget for such period, which shall be furnished no later than one (1) month after the EffectiveDate. Only the activities included in an Annual Work Plan and Budget expressly approved by the Association (each an “Annual WorkPlan and Budget”) are eligible to a financing from the proceeds of the Financing.
The Recipient through the CNFI, Ministry of Finance and BCM (including CSBF) shall, not later than three (3) months of theEffective Date, establish a working group to coordinate the financial education activities and to prepare and follow-up on anaction plan for a mutualized MIS for MFIs.
The Recipient shall not later than three (3) months after the Effective Date, establish, and at all times during Projectimplementation maintain, a grievance redress mechanism at all times during Project implementation.
The Recipient shall, not later than three (3) months after the Effective Date, establish and, at all times during Projectimplementation, maintain the PPCG Supervision Committee (SSC).
The Recipient shall, not later than three (3) months establish, and at all times during Project implementation, maintain the PPCGOrientation Committee (OC).
The Recipient shall, not later than three (3) months after the Effective Date, cause the PPCG Fund to establish, and at all timesduring Project implementation, maintain, and publicize the availability of, a grievance redress mechanism, in a form and substancesatisfactory to the Association, to hear and determine fairly and in good faith all complaints raised in relation to the Project,and take all measures necessary to implement the determinations made by such mechanism in a manner satisfactory to the Association.
44000-P147514
World Bank
International Development Association
MINISTRY OF AGRICULTURE
International Development Association
MINISTRY OF AGRICULTUREMADAGASCAR
Madagascar Emergency Food Security and Social Protection Project
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Giuseppe Fantozzi
gfantozzi@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
ForestryIrrigation and DrainageAgricultural Extension, Research, and Other Support ActivitiesSocial ProtectionDisaster PreparednessRural Infrastructure and service deliveryDisaster Risk ManagementRural MarketsAgriculture FinanceFinance for DevelopmentDisaster Response and RecoveryDisaster Risk ReductionSocial Safety NetsDisaster Risk FinanceRural DevelopmentSocial Protection
International Development Association65000000Total Commitment in First Quarter of 2014
International Development Association3000000Total Disbursement in Third Quarter of 2014
International Development Association169915Total Disbursement in Fourth Quarter of 2014
International Development Association5000000Total Disbursement in Fourth Quarter of 2014
International Development Association99677Total Disbursement in First Quarter of 2015
International Development Association298520Total Disbursement in First Quarter of 2015
International Development Association167318Total Disbursement in Second Quarter of 2015
International Development Association224847Total Disbursement in Second Quarter of 2015
International Development Association259476Total Disbursement in Second Quarter of 2015
International Development Association-30630Total Interest Repayment in Second Quarter of 2015
International Development Association247194Total Disbursement in Third Quarter of 2015
International Development Association294679Total Disbursement in Third Quarter of 2015
International Development Association1481733Total Disbursement in Third Quarter of 2015
International Development Association293999Total Disbursement in Fourth Quarter of 2015
International Development Association1123303Total Disbursement in Fourth Quarter of 2015
International Development Association1801896Total Disbursement in Fourth Quarter of 2015
International Development Association-34856Total Interest Repayment in Fourth Quarter of 2015
International Development Association435187Total Disbursement in First Quarter of 2016
International Development Association601457Total Disbursement in First Quarter of 2016
International Development Association859094Total Disbursement in First Quarter of 2016
International Development Association613130Total Disbursement in Second Quarter of 2016
International Development Association1085875Total Disbursement in Second Quarter of 2016
International Development Association1513191Total Disbursement in Second Quarter of 2016
International Development Association-52955Total Interest Repayment in Second Quarter of 2016
International Development Association361739Total Disbursement in Third Quarter of 2016
International Development Association694468Total Disbursement in Third Quarter of 2016
International Development Association1316181Total Disbursement in Third Quarter of 2016
International Development Association1890393Total Disbursement in Fourth Quarter of 2016
International Development Association2338652Total Disbursement in Fourth Quarter of 2016
International Development Association2795618Total Disbursement in Fourth Quarter of 2016
International Development Association-72356Total Interest Repayment in Fourth Quarter of 2016
International Development Association379136Total Disbursement in First Quarter of 2017
International Development Association3542269Total Disbursement in First Quarter of 2017
International Development Association1590960Total Disbursement in Second Quarter of 2017
International Development Association1674661Total Disbursement in Second Quarter of 2017
International Development Association2468230Total Disbursement in Second Quarter of 2017
International Development Association-98203Total Interest Repayment in Second Quarter of 2017
International Development Association2142509Total Disbursement in Third Quarter of 2017
International Development Association2324648Total Disbursement in Third Quarter of 2017
International Development Association2988327Total Disbursement in Third Quarter of 2017
International Development Association269861Total Disbursement in Fourth Quarter of 2017
International Development Association6285268Total Disbursement in Fourth Quarter of 2017
International Development Association6811042Total Disbursement in Fourth Quarter of 2017
International Development Association-151757Total Interest Repayment in Fourth Quarter of 2017
International Development Association-336845Total Disbursement in First Quarter of 2018
International Development Association-223466Total Interest Repayment in Second Quarter of 2018
International Development Association-27940Total Disbursement in Fourth Quarter of 2018
International Development Association-222047Total Interest Repayment in Fourth Quarter of 2018
International Development Association-400386Total Commitment Cancellations in First Quarter of 2019
International Development Association-5603Total Disbursement in First Quarter of 2019
International Development Association-220812Total Interest Repayment in Second Quarter of 2019Project Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportFinancing AgreementContract AwardsProject URLProcurement Notices
Sava Region
-14.2000 49.8000
Boeny Region
-16.3000 46.1000
Alaotra Mangoro Region
-17.9000 48.4000
Bongolava Region
-18.5000 46.1000
Vakinankaratra Region
-19.7000 46.9000
Itasy Region
-18.9500 46.9500
Menabe Region
-20.2000 45.0700
Amoron'i Mania Region
-20.5000 46.7000
Haute Matsiatra Region
-21.3700 46.5000
Ihorombe Region
-22.3000 46.2000
1666666.67
1666666.67
1666666.66
1666666.67
1666666.67
1666666.66
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1666666.67
1666666.67
1666666.66
1666666.67
1666666.67
1666666.66
1666666.67
1666666.67
1666666.66
1666666.67
1666666.67
1666666.66
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1666666.67
1666666.67
1666666.66
1666666.67
1666666.67
1666666.66
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1250000.00
1666666.67
1666666.67
1666666.66
1666666.67
1666666.67
1666666.66
1666666.67
1666666.67
1666666.66
1666666.67
1666666.67
1666666.66
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
166666.67
166666.67
166666.66
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Finance Agreement: National Steering Committee | Description: The Recipient shall establish and thereafter maintain the NationalSteering Committee with composition and terms of reference satisfactory to the Association. | Due Date: 28-Jun-2014
Finance Agreement: Recruiting Project Secretariat staff | Description: The Recipient shall recruit a monitoring and evaluationspecialist and a financial management specialist, each on the basis of terms of reference, qualifications and experiencesatisfactory to the Association and in accordance with the provisions of Section III of Schedule 2 to the Financing Agreement, tobe assigned to the Project Secretariat. | Due Date: 28-Jul-2014
Finance Agreement: PN-BVPI Project Manuals | Description: The Recipient shall revise and update the PN-BVPI Project Manuals, andadopt the Project Implementation Manual, each in form and substance acceptable to the Association, for the purpose of implementingProject activities to be implemented by PN-BVPI. | Due Date: 14-Nov-2014
Finance Agreement: FID Project Manuals | Description:The Recipient shall have caused the Project Implementing Entity to revise andupdate the FID Project Manuals (except the Cash-for-Tree Procedure Manual), in form and substance acceptable to the Association,forthe purpose of implementing its Respective part of the Project. | Due Date: 28-Jul-2014
Legal covenant Finance Agreement: Cash-for-Tree Procedure Manual | Description: The Recipient shall have caused the ProjectImplementing Entity to adopt the Cash-for-Tree Procedure Manual, in form and substance acceptable to the Association, for thepurpose of implementing Part A.2(a) of the Project. | Due Date: 28-Feb-2015
Finance Agreement: Audit | Description: The Recipient has engaged independent auditors for the purpose of carrying out theProject's annual audits in accordance with the provisions of Section III of Schedule 2 to the Financing Agreement. | Due Date:28-Nov-2014
Finance Agreement: Procurement Complaint handling mechanism | Description: The Recipient shall have established a procurementcomplaint handling mechanism acceptable to the Association. | Due Date:14-Nov-2014
44000-P083351
World Bank
International Development Association
SECRETARIAT NATIONAL
International Development Association
SECRETARIAT NATIONALMADAGASCAR
Integrated Growth Poles
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Michael Olavi Engman
mengman@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Other TransportationOther Energy and ExtractivesOther Public AdministrationOther Industry, Trade and ServicesPublic Private PartnershipsRural Infrastructure and service deliveryJob CreationRural DevelopmentMSME FinanceMSME DevelopmentJobsUrban DevelopmentUrban Infrastructure and Service DeliveryFinancial Infrastructure and AccessEnterprise Development
International Development Association129800000Total Commitment in Third Quarter of 2005
International Development Association1634835Total Disbursement in Fourth Quarter of 2005
International Development Association4722489Total Disbursement in Fourth Quarter of 2005
International Development Association7800000Total Disbursement in Fourth Quarter of 2005
International Development Association0Total Disbursement in First Quarter of 2006
International Development Association359959Total Disbursement in First Quarter of 2006
International Development Association-134660Total Interest Repayment in First Quarter of 2006
International Development Association510305Total Disbursement in Second Quarter of 2006
International Development Association726281Total Disbursement in Second Quarter of 2006
International Development Association2497470Total Disbursement in Second Quarter of 2006
International Development Association179974Total Disbursement in Third Quarter of 2006
International Development Association407954Total Disbursement in Third Quarter of 2006
International Development Association-232268Total Interest Repayment in Third Quarter of 2006
International Development Association472037Total Disbursement in Fourth Quarter of 2006
International Development Association679738Total Disbursement in Fourth Quarter of 2006
International Development Association3096743Total Disbursement in Fourth Quarter of 2006
International Development Association442425Total Disbursement in First Quarter of 2007
International Development Association1546031Total Disbursement in First Quarter of 2007
International Development Association-181482Total Interest Repayment in First Quarter of 2007
International Development Association391851Total Disbursement in Second Quarter of 2007
International Development Association7036634Total Disbursement in Second Quarter of 2007
International Development Association1465001Total Disbursement in Third Quarter of 2007
International Development Association3098426Total Disbursement in Third Quarter of 2007
International Development Association10354922Total Disbursement in Third Quarter of 2007
International Development Association-209670Total Interest Repayment in Third Quarter of 2007
International Development Association2014422Total Disbursement in Fourth Quarter of 2007
International Development Association2792712Total Disbursement in Fourth Quarter of 2007
International Development Association3255308Total Disbursement in Fourth Quarter of 2007
International Development Association1621725Total Disbursement in First Quarter of 2008
International Development Association2414281Total Disbursement in First Quarter of 2008
International Development Association-225960Total Interest Repayment in First Quarter of 2008
International Development Association2802711Total Disbursement in Second Quarter of 2008
International Development Association3167829Total Disbursement in Second Quarter of 2008
International Development Association17300775Total Disbursement in Second Quarter of 2008
International Development Association40000000Total Commitment in Second Quarter of 2008
International Development Association314496Total Disbursement in Third Quarter of 2008
International Development Association3535789Total Disbursement in Third Quarter of 2008
International Development Association3764578Total Disbursement in Third Quarter of 2008
International Development Association-304277Total Interest Repayment in Third Quarter of 2008
International Development Association3263420Total Disbursement in Fourth Quarter of 2008
International Development Association10272881Total Disbursement in Fourth Quarter of 2008
International Development Association2900000Total Disbursement in Fourth Quarter of 2008
International Development Association1230367Total Disbursement in First Quarter of 2009
International Development Association5624542Total Disbursement in First Quarter of 2009
International Development Association-332005Total Interest Repayment in First Quarter of 2009
International Development Association-4996Total Interest Repayment in First Quarter of 2009
International Development Association-425043Total Interest Repayment in Third Quarter of 2009
International Development Association-10873Total Interest Repayment in Third Quarter of 2009
International Development Association120030Total Disbursement in Fourth Quarter of 2009
International Development Association2543216Total Disbursement in Fourth Quarter of 2009
International Development Association203288Total Disbursement in Fourth Quarter of 2009
International Development Association100275Total Disbursement in First Quarter of 2010
International Development Association487663Total Disbursement in First Quarter of 2010
International Development Association661784Total Disbursement in First Quarter of 2010
International Development Association-436788Total Interest Repayment in First Quarter of 2010
International Development Association9146Total Disbursement in First Quarter of 2010
International Development Association12661Total Disbursement in First Quarter of 2010
International Development Association-11676Total Interest Repayment in First Quarter of 2010
International Development Association39330Total Disbursement in Second Quarter of 2010
International Development Association44515Total Disbursement in Second Quarter of 2010
International Development Association214366Total Disbursement in Second Quarter of 2010
International Development Association6320Total Disbursement in Second Quarter of 2010
International Development Association18137Total Disbursement in Second Quarter of 2010
International Development Association19568Total Disbursement in Second Quarter of 2010
International Development Association3998711Total Disbursement in Third Quarter of 2010
International Development Association-410500Total Interest Repayment in Third Quarter of 2010
International Development Association2324498Total Disbursement in Third Quarter of 2010
International Development Association-11356Total Interest Repayment in Third Quarter of 2010
International Development Association144097Total Disbursement in Fourth Quarter of 2010
International Development Association556826Total Disbursement in Fourth Quarter of 2010
International Development Association651166Total Disbursement in Fourth Quarter of 2010
International Development Association106538Total Disbursement in Fourth Quarter of 2010
International Development Association585976Total Disbursement in Fourth Quarter of 2010
International Development Association629856Total Disbursement in First Quarter of 2011
International Development Association816892Total Disbursement in First Quarter of 2011
International Development Association-457498Total Interest Repayment in First Quarter of 2011
International Development Association74654Total Disbursement in First Quarter of 2011
International Development Association94940Total Disbursement in First Quarter of 2011
International Development Association-20486Total Interest Repayment in First Quarter of 2011
International Development Association37663Total Disbursement in Second Quarter of 2011
International Development Association1419320Total Disbursement in Second Quarter of 2011
International Development Association28261Total Disbursement in Second Quarter of 2011
International Development Association113735Total Disbursement in Second Quarter of 2011
International Development Association181794Total Disbursement in Third Quarter of 2011
International Development Association-470646Total Interest Repayment in Third Quarter of 2011
International Development Association340627Total Disbursement in Third Quarter of 2011
International Development Association-25089Total Interest Repayment in Third Quarter of 2011
International Development Association123203Total Disbursement in Fourth Quarter of 2011
International Development Association1676999Total Disbursement in Fourth Quarter of 2011
International Development Association1865387Total Disbursement in Fourth Quarter of 2011
International Development Association173527Total Disbursement in Fourth Quarter of 2011
International Development Association203455Total Disbursement in Fourth Quarter of 2011
International Development Association250563Total Disbursement in Fourth Quarter of 2011
International Development Association-2195472Total Disbursement in First Quarter of 2012
International Development Association1853048Total Disbursement in First Quarter of 2012
International Development Association-464195Total Interest Repayment in First Quarter of 2012
International Development Association86160Total Disbursement in First Quarter of 2012
International Development Association764601Total Disbursement in First Quarter of 2012
International Development Association-26009Total Interest Repayment in First Quarter of 2012
International Development Association-5000000Total Commitment Cancellations in Second Quarter of 2012
International Development Association-518129Total Disbursement in Second Quarter of 2012
International Development Association1201740Total Disbursement in Second Quarter of 2012
International Development Association81131Total Disbursement in Second Quarter of 2012
International Development Association193264Total Disbursement in Second Quarter of 2012
International Development Association-461119Total Interest Repayment in Third Quarter of 2012
International Development Association144580Total Disbursement in Third Quarter of 2012
International Development Association168193Total Disbursement in Third Quarter of 2012
International Development Association-30308Total Interest Repayment in Third Quarter of 2012
International Development Association46443Total Disbursement in Fourth Quarter of 2012
International Development Association301133Total Disbursement in Fourth Quarter of 2012
International Development Association468264Total Disbursement in Fourth Quarter of 2012
International Development Association-205559Total Disbursement in First Quarter of 2013
International Development Association-472649Total Interest Repayment in First Quarter of 2013
International Development Association1407021Total Disbursement in First Quarter of 2013
International Development Association-33692Total Interest Repayment in First Quarter of 2013
International Development Association-30816Total Disbursement in Second Quarter of 2013
International Development Association-260Total Disbursement in Second Quarter of 2013
International Development Association102779Total Disbursement in Second Quarter of 2013
International Development Association1121949Total Disbursement in Second Quarter of 2013
International Development Association1337690Total Disbursement in Second Quarter of 2013
International Development Association2002883Total Disbursement in Second Quarter of 2013
International Development Association-465661Total Interest Repayment in Third Quarter of 2013
International Development Association517190Total Disbursement in Third Quarter of 2013
International Development Association1012086Total Disbursement in Third Quarter of 2013
International Development Association1490126Total Disbursement in Third Quarter of 2013
International Development Association-41321Total Interest Repayment in Third Quarter of 2013
International Development Association-132706Total Commitment Cancellations in Fourth Quarter of 2013
International Development Association212819Total Disbursement in Fourth Quarter of 2013
International Development Association1547002Total Disbursement in Fourth Quarter of 2013
International Development Association2471278Total Disbursement in Fourth Quarter of 2013
International Development Association-476067Total Interest Repayment in First Quarter of 2014
International Development Association785609Total Disbursement in First Quarter of 2014
International Development Association1010600Total Disbursement in First Quarter of 2014
International Development Association3509583Total Disbursement in First Quarter of 2014
International Development Association-74723Total Interest Repayment in First Quarter of 2014
International Development Association610266Total Disbursement in Second Quarter of 2014
International Development Association1142718Total Disbursement in Second Quarter of 2014
International Development Association1691740Total Disbursement in Second Quarter of 2014
International Development Association-479568Total Interest Repayment in Third Quarter of 2014
International Development Association366181Total Disbursement in Third Quarter of 2014
International Development Association540339Total Disbursement in Third Quarter of 2014
International Development Association1464132Total Disbursement in Third Quarter of 2014
International Development Association-107882Total Interest Repayment in Third Quarter of 2014
International Development Association522295Total Disbursement in Fourth Quarter of 2014
International Development Association975097Total Disbursement in Fourth Quarter of 2014
International Development Association1018737Total Disbursement in Fourth Quarter of 2014
International Development Association-442772Total Interest Repayment in First Quarter of 2015
International Development Association1487058Total Disbursement in First Quarter of 2015
International Development Association-122179Total Interest Repayment in First Quarter of 2015
International Development Association-365041Total Commitment Cancellations in Second Quarter of 2015
International Development Association-304923Total Disbursement in Second Quarter of 2015
International Development Association-430677Total Interest Repayment in Third Quarter of 2015
International Development Association-1148527Total Loan Repayment in Third Quarter of 2015
International Development Association-129630Total Interest Repayment in Third Quarter of 2015
International Development Association-423270Total Interest Repayment in First Quarter of 2016
International Development Association-1140052Total Loan Repayment in First Quarter of 2016
International Development Association-128104Total Interest Repayment in First Quarter of 2016
International Development Association-420491Total Interest Repayment in Third Quarter of 2016
International Development Association-1143963Total Loan Repayment in Third Quarter of 2016
International Development Association-128545Total Interest Repayment in Third Quarter of 2016
International Development Association-405935Total Interest Repayment in First Quarter of 2017
International Development Association-1115654Total Loan Repayment in First Quarter of 2017
International Development Association-125364Total Interest Repayment in First Quarter of 2017
International Development Association-387066Total Interest Repayment in Third Quarter of 2017
International Development Association-1151682Total Loan Repayment in Third Quarter of 2017
International Development Association-127137Total Interest Repayment in Third Quarter of 2017
International Development Association-418991Total Interest Repayment in First Quarter of 2018
International Development Association-1191225Total Loan Repayment in First Quarter of 2018
International Development Association-133394Total Interest Repayment in First Quarter of 2018
International Development Association-440484Total Interest Repayment in Third Quarter of 2018
International Development Association-1155731Total Loan Repayment in Third Quarter of 2018
International Development Association-132350Total Interest Repayment in Third Quarter of 2018
International Development Association-346314Total Loan Repayment in Third Quarter of 2018
International Development Association-386645Total Interest Repayment in First Quarter of 2019
International Development Association-1152040Total Loan Repayment in First Quarter of 2019
International Development Association-123549Total Interest Repayment in First Quarter of 2019
International Development Association-345208Total Loan Repayment in First Quarter of 2019
International Development Association-408580Total Interest Repayment in Third Quarter of 2019
International Development Association-1141508Total Loan Repayment in Third Quarter of 2019
International Development Association-130195Total Interest Repayment in Third Quarter of 2019
International Development Association-342071Total Loan Repayment in Third Quarter of 2019Project Information DocumentProject Information DocumentProject Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportCredit AgreementFinancing AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Nosy Be
-13.3140 48.2590
Baie d' Hellville
-13.4060 48.2830
Fausse Baie des Galions
-25.0500 46.9670
Antananarivo
-18.9140 47.5360
Nosy Tanihely
-13.4830 48.2360
Fort Dauphin
-25.0320 46.9830
Intermediate Results Indicator
Number of individual recipients of subsidized BDS services
Intermediate Results Indicator
Component C: 1.1: Number of tourist arrivals by air or sea per annum
Intermediate Results Indicator
Component C: 1.2: Number of formal and direct tourism related jobs in Nosy Be
Intermediate Results Indicator
Component D: 4: Number of formal jobs in mining, construction, agribusiness and in Ehoala Park/Port
Intermediate Results Indicator
Component C: 2.1: People provided with access to “Improved Water Sources” under the project
Intermediate Results Indicator
Component D: 1.2: Number of formal and direct tourism related jobs in Taolagnaro
Intermediate Results Indicator
Component C: 2.8: People in urban areas provided with access to regular solid waste collection under the project
Intermediate Results Indicator
Component D: 1.1: Number of tourist arrivals in Taolagnaro per annum
Intermediate Results Indicator
Component D: 2.1: People provided with access to “Improved Water Sources” under the project
Intermediate Results Indicator
Component D: 2.7: People in urban areas provided with access to regular solid waste collection under the project
Intermediate Results Indicator
Annual sales value of assisted firms in selected value chains (cum.)
Intermediate Results Indicator
Component C: 1.3: Increase in hotel rooms
Intermediate Results Indicator
Component D: 1.3: Increase in hotel rooms
Intermediate Results Indicator
Component C: 2.5: Value of additional Municipal revenue generated
Intermediate Results Indicator
Component D: 2.4: Value of additional Municipal revenue generated
Intermediate Results Indicator
Days required to start a business
Intermediate Results Indicator
Component C: 2.7: Existing electricity networks rehabilitated
Intermediate Results Indicator
Component D: 3: Volume of traffic handled by Ehoala Port
Intermediate Results Indicator
Component D: 2.6: Existing electricity networks rehabilitated
Intermediate Results Indicator
Constructed
Intermediate Results Indicator
Rehabilitated
Intermediate Results Indicator
Constructed
Intermediate Results Indicator
Rehabilitated
Intermediate Results Indicator
Component C: 2.4: Time required to issue a construction permit by the municipality of Nosy Be
Intermediate Results Indicator
Component D: 2.3: Time required to issue a construction permit by the Municipality of Taolagnaro
Intermediate Results Indicator
PDO 4: Adoption by National Assembly of a new Investment Law and amended Free Zone law
Intermediate Results Indicator
PDO 3.1: EDBM is fully staffed and operational
Intermediate Results Indicator
PDO 3.2: Adoption of regional development plans
Intermediate Results Indicator
Component C: 2.3: Completion of upgrading works of Hellville and Ankify ports
Intermediate Results Indicator
Component C: 2.2: Roads rehabilitated
Intermediate Results Indicator
Component D: 2.2: Roads rehabilitated
Intermediate Results Indicator
Urban
Intermediate Results Indicator
Rural
Intermediate Results Indicator
Urban
Intermediate Results Indicator
Rural
Intermediate Results Indicator
Component C: 2.6: Additional generation capacity installed - conventional
Intermediate Results Indicator
Component D: 2.5: Additional generation capacity installed - conventional
PDO Indicator
Female beneficiaries
PDO Indicator
Number of businesses registered in Nosy Be
PDO Indicator
Number of businesses registered in Fort Dauphin
PDO Indicator
Number of formal jobs in Nosy Be
PDO Indicator
Number of formal jobs in Fort Dauphin
PDO Indicator
Number of businesses registered in the two poles
PDO Indicator
Number of formal jobs in the two poles
PDO Indicator
Direct project beneficiaries
1000000.00
1000000.00
1000000.00
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
2666666.67
2666666.67
2666666.66
3333333.33
3333333.33
3333333.34
3333333.33
3333333.33
3333333.34
3333333.33
3333333.33
3333333.34
3333333.33
3333333.33
3333333.34
4000000.00
4000000.00
4000000.00
4000000.00
4000000.00
4000000.00
4000000.00
4000000.00
4000000.00
2166666.67
2166666.67
2166666.66
2166666.67
2166666.67
2166666.66
2166666.67
2166666.67
2166666.66
2166666.67
2166666.67
2166666.66
666666.67
666666.67
666666.66
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
600000.00
600000.00
600000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
4955411.03
4955411.03
4955411.03
126246.64
126246.64
126246.65
1280495.22
1280495.22
1280495.24
133851.42
133851.44
133851.44
1497124.78
1497124.79
1497124.79
666517.38
666517.38
666517.39
2460688.90
2460688.91
2460688.91
4908006.74
4908006.74
4908006.74
2594597.42
2594597.42
2594597.44
1258670.75
1258670.77
1258670.77
7073765.03
7073765.03
7073765.03
2518432.28
2518432.29
2518432.29
2518432.28
2518432.29
2518432.29
2518432.28
2518432.29
2518432.29
1762902.59
1762902.61
1762902.61
1762902.59
1762902.61
1762902.61
1754793.25
1754793.25
1754793.25
1511059.37
1511059.37
1511059.37
1511059.37
1511059.37
1511059.37
1511059.37
1511059.37
1511059.37
1007372.90
1007372.92
1007372.92
1007372.90
1007372.92
1007372.92
1007372.90
1007372.92
1007372.92
1007372.90
1007372.92
1007372.92
1007372.90
1007372.92
1007372.92
1007372.90
1007372.92
1007372.92
1007372.90
1007372.92
1007372.92
1007372.90
1007372.92
1007372.92
1007372.90
1007372.92
1007372.92
1007372.90
1007372.92
1007372.92
1007372.90
1007372.92
1007372.92
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Finance Agreement :Section 3.05 | Description :Borrower to ensure that the sites included in the Tourism Reserve of Nosy Be can beleased by private investors | Due Date :30-Sep-2006
Finance Agreement :Section 3.08 | Description :Borrower to appoint a local representative of the NPS at each pole | Due Date:31-Mar-2006
Finance Agreement :Section 3.09 | Description :Borrower to employ an environmental specialist for the NPS | Due Date :31-Jan-2006
Finance Agreement :Section 4.02 | Description :Submission of FMR according to agreed schedule | Due Date :15-Mar-2006
Finance Agreement :Section 3.06 | Description :Ensure that the tourism sector be given appropriate incentives for its development |Due Date :28-Mar-2007
Finance Agreement :Add. Financing | Description :Submission of management plan for water/electricity in Nosy Be and Fort Dauphin |Due Date :31-Oct-2008
Finance Agreement :Add . Financing | Description :No later than March 31, 2013, the Recipient shall have submitted to theAssociation astrategy and an action plan, in form and substance satisfactory to the Association, thatoutlines a road map toensure the financial sustainability of EDBM and the activities ofthe one stop shop. | Due Date :31-Mar-2013
Finance Agreement :Add. Financing | Description :No later than June 30, 2014, the Recipient shall have taken all necessarymeasures, inform and substance satisfactory to the Association, to implement the strategy and actionplan to ensure the financialsustainability of EDBM and the activities of the one stopshop. | Due Date :30-Jun-2014
Finance Agreement :Add. Financing | Description :the Recipient shall have submitted a plan in form andsubstance satisfactory tothe Association, to ensure an autonomous managementof thepower section of JIRAMA in Nosy Be. | Due Date :31-Oct-2013
44000-P166425
World Bank
International Development Association
MINISTRY OF FINANCE
International Development Association
MINISTRY OF FINANCEMADAGASCAR
MG - Second Inclusive and Resilient Growth DPO
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Djibrilla Adamou Issa
dissa1@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Sub-National GovernmentSocial ProtectionBanking InstitutionsRural and Inter-Urban RoadsOther Energy and ExtractivesAccess to EnergyAdaptationRural Infrastructure and service deliveryPublic AdministrationFinancial Infrastructure and AccessLand Policy and TenureMunicipal Institution BuildingCivil Registration and IdentificationFinancial inclusionEnergySocial ProtectionRural DevelopmentSocial Safety NetsClimate change
International Development Association60000000Total Commitment in Third Quarter of 2018
International Development Association59123274Total Disbursement in Fourth Quarter of 2018Project Information DocumentFinancing AgreementContract AwardsProject URLProcurement Notices
0.00
0.00
44000-P103950
World Bank
International Development Association
OFFICE OF THE PRESIDENT
International Development Association
OFFICE OF THE PRESIDENTMADAGASCAR
Governance and Institutional Development Project II
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Anne-Lucie Lefebvre
alefebvre@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Sub-National GovernmentOther Public AdministrationCentral Government (Central Agencies)Law and JusticeTransparency, Accountability and Good GovernancePublic Expenditure ManagementAdministrative and Civil Service ReformMSME DevelopmentPublic AdministrationPublic Finance ManagementEnterprise Development
International Development Association40000000Total Commitment in Second Quarter of 2008
International Development Association8852231Total Disbursement in Fourth Quarter of 2008
International Development Association-17899Total Interest Repayment in First Quarter of 2009
International Development Association-33907Total Interest Repayment in Third Quarter of 2009
International Development Association-33916Total Interest Repayment in First Quarter of 2010
International Development Association21600Total Disbursement in Third Quarter of 2010
International Development Association44752Total Disbursement in Third Quarter of 2010
International Development Association329174Total Disbursement in Third Quarter of 2010
International Development Association-31935Total Interest Repayment in Third Quarter of 2010
International Development Association-36276Total Interest Repayment in First Quarter of 2011
International Development Association77460Total Disbursement in Second Quarter of 2011
International Development Association2285352Total Disbursement in Third Quarter of 2011
International Development Association-37613Total Interest Repayment in Third Quarter of 2011
International Development Association-42548Total Interest Repayment in First Quarter of 2012
International Development Association-7999999Total Commitment Cancellations in Second Quarter of 2012
International Development Association792078Total Disbursement in Second Quarter of 2012
International Development Association840236Total Disbursement in Third Quarter of 2012
International Development Association-43957Total Interest Repayment in Third Quarter of 2012
International Development Association3795370Total Disbursement in Fourth Quarter of 2012
International Development Association-48948Total Interest Repayment in First Quarter of 2013
International Development Association3652475Total Disbursement in Second Quarter of 2013
International Development Association-66326Total Interest Repayment in Third Quarter of 2013
International Development Association3621184Total Disbursement in Fourth Quarter of 2013
International Development Association-88142Total Interest Repayment in First Quarter of 2014
International Development Association-91309Total Interest Repayment in Third Quarter of 2014
International Development Association48190Total Disbursement in Fourth Quarter of 2014
International Development Association69502Total Disbursement in Fourth Quarter of 2014
International Development Association135365Total Disbursement in Fourth Quarter of 2014
International Development Association-3658938Total Commitment Cancellations in First Quarter of 2015
International Development Association647547Total Disbursement in First Quarter of 2015
International Development Association-85217Total Interest Repayment in First Quarter of 2015
International Development Association-86049Total Interest Repayment in Third Quarter of 2015
International Development Association-85746Total Interest Repayment in First Quarter of 2016
International Development Association-86483Total Interest Repayment in Third Quarter of 2016
International Development Association-36849Total Disbursement in Fourth Quarter of 2016
International Development Association-83790Total Interest Repayment in First Quarter of 2017
International Development Association-36829Total Commitment Cancellations in Second Quarter of 2017
International Development Association-692Total Disbursement in Second Quarter of 2017
International Development Association-86410Total Interest Repayment in Third Quarter of 2017
International Development Association-89483Total Interest Repayment in First Quarter of 2018
International Development Association-89063Total Interest Repayment in Third Quarter of 2018
International Development Association-231522Total Loan Repayment in Third Quarter of 2018
International Development Association-83023Total Interest Repayment in First Quarter of 2019
International Development Association-229956Total Loan Repayment in First Quarter of 2019
International Development Association-85219Total Interest Repayment in Third Quarter of 2019
International Development Association-226000Total Loan Repayment in Third Quarter of 2019Project Information DocumentProject Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportFinancing AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Fort Dauphin
-25.0320 46.9830
Nosy Be
-13.3140 48.2590
Antsiranana
-12.2790 49.2920
Antananarivo
-18.9140 47.5360
Moramanga
-18.9490 48.2300
Intermediate Results Indicator
Number of PEFA audited self-evaluation reports published and discussed
Draft national PEFA Self-Assessment was completed on December 31, 2013. Comments on the draft Assessment have been received fromthe EU, the PEFA Secretariat, and the World Bank. Team is awaiting comments from IMF to be provided by the end of May 2014 for GoMtocomplete the Assessment and seek PEFA accreditation.The city of Antanananrivo PEFA Self-Assessment is on- going and the city ofMahajanga also requested support to complete PEFA Self-Assessment.
Intermediate Results Indicator
Number of IFMIS Centralization/integration indicators rated « satisfactory »
Note the IFMIS module on Revenues is partially integrated.
Intermediate Results Indicator
Number of bids , of the central Government, awarded under open competition
Note: This figure includes all the tenders below the threshold for mandatory public tender competition.
Intermediate Results Indicator
The Number of Public Institutions that endorse, publicly, the “Access to information and Knowledge Sharing Charter”
“Access to information and Knowledge Sharing Charter” was signed by government, civil society and private sector on December 12,2013.
Intermediate Results Indicator
Number of land parcels recorded for local taxation
The land parcel census operation was significantly more successful than originally anticipated. The procedure used bygovernment to record parcels is relatively simple.The baseline for this indicator was also underestimated when the project wasrestructured in 2012.
Intermediate Results Indicator
Number of land parcels with secured ownership rights registered
Intermediate Results Indicator
Number of social accountability initiatives implemented at the local level
Tender has been completed and executing agencies have been selected. Executing agency is in the process of identifying potentialactivities. However, activities supporting this indicator have not started yet due to delay of payment of communal grant.
Intermediate Results Indicator
Number visitor of the INSTAT Website
Intermediate Results Indicator
Percentage of FDL communes with an improved CGF score (D+) (FDL communes)
Intermediate Results Indicator
Percentage of communes publishing information on public service in compliance with BIANCO recommendations.
Contract with the executing agency signed. 123 targeted communes have been trained on public service compliance. Local communalanti-corruption plans have been completed Plan implementation has started.
Intermediate Results Indicator
Percentage of GDLN budget that is covered by own resources.
The figure excludes the activities financed directly by the project.
Intermediate Results Indicator
Knowledge management database available and accessible via internet
Delays in procurement. However, the tendering process is completed and the activities have started.
PDO Indicator
Number of selected indicators that increase their rating in the PEFA self evaluation report
As per December 2013 PEFA Self-Assessment:Indicator P1-26 “Scope, nature and follow-up of external audit” slightly improved from“D” in 2008 to “D+” in 2013.
PDO Indicator
Number of ministries publishing quarterly budget execution report through media or internet.
The Ministry of Finance and Budget is publishing on the web a quarterly budget execution report which includes information onbudget execution for 35 Ministries and the Prime Minister's Office. The Bank team will engage with the client to revise target. Newtarget will be reported in the December 2013 ISR.
PDO Indicator
The Local Governance Index (IGL ) average is increased in targeted Local Governments.
The Local Governance Index (IGL) measuring transparency, accountability and participation at the communal level declined becauseofthe delays of payment of the communal grant. The delay is the result of a joint decision from the Bank to postpone thedisbursementuntil after the nomination of the new government to avoid political interference. Important also to note that theinitial baselinewas calculated referring to 50 communes while the current indicator now compiles data received from 123 communes.
PDO Indicator
Direct Project Beneficiaries
- Persons trained: 6800- Commune befitting from communal grants: 0- OSC benefiting from Social Accountability grants: 0
- Persons trained: 8000- Commune befitting from communal grants: 100- OSC benefiting from Social Accountability grants: 45
- Persons trained: 7900- Commune befitting from communal grants: 0. - OSC benefiting from Social Accountability grants:47.Communal grant proposal not completed. The PUI is taking additional fiduciary measures to prevent potential misuse of funds.We measures are welcome, they are slowing down the grant approval process.
1333333.33
1333333.33
1333333.34
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2950743.55
2950743.55
2950743.55
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
131841.78
131841.78
131841.79
0.00
0.00
0.00
0.00
0.00
0.00
25820.07
25820.07
25820.08
761784.00
761784.00
761784.00
0.00
0.00
0.00
0.00
0.00
0.00
264025.70
264025.71
264025.71
546666.66
546666.67
546666.67
148666.66
148666.67
148666.67
833333.33
833333.33
833333.34
33333.33
33333.33
33333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Recruitment of a Grant Administrator
Establishment of a Social Accountability Grant Committee
Revision of the Project Implementation Manual
First Grant Agreement Signed
Recruitment of a chief accountant and procurement specialist
Agreement with Fond de DEveloppement Local, to Act as the Communal Grant Committee
44000-P051922
World Bank
International Development Association
MINISTRY OF AGRICULTURE (MOA)
International Development Association
MINISTRY OF AGRICULTURE (MOA)MADAGASCAR
Rural Development Support Project
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Ziva Razafintsalama
zrazafintsalama@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Central Government (Central Agencies)Social ProtectionAgricultural Extension, Research, and Other Support ActivitiesIrrigation and DrainageAgricultural markets, commercialization and agri-businessJobsLandscape ManagementLabor Market InstitutionsParticipation and Civic EngagementLand Administration and ManagementActive Labor Market ProgramsRural DevelopmentRenewable Natural Resources Asset ManagementSocial InclusionBiodiversityLabor Market Policy and Programs
International Development Association73752378Total Commitment in Second Quarter of 2001
International Development Association15297622Total Commitment in Second Quarter of 2001
International Development Association2711954Total Disbursement in Fourth Quarter of 2001
International Development Association27637Total Disbursement in First Quarter of 2002
International Development Association70618Total Disbursement in Second Quarter of 2002
International Development Association178870Total Disbursement in Second Quarter of 2002
International Development Association-10520Total Interest Repayment in Second Quarter of 2002
International Development Association384558Total Disbursement in Third Quarter of 2002
International Development Association1274594Total Disbursement in Third Quarter of 2002
International Development Association87683Total Disbursement in Fourth Quarter of 2002
International Development Association520055Total Disbursement in Fourth Quarter of 2002
International Development Association562747Total Disbursement in Fourth Quarter of 2002
International Development Association-12360Total Interest Repayment in Fourth Quarter of 2002
International Development Association383613Total Disbursement in First Quarter of 2003
International Development Association639242Total Disbursement in First Quarter of 2003
International Development Association1416145Total Disbursement in First Quarter of 2003
International Development Association572718Total Disbursement in Second Quarter of 2003
International Development Association787711Total Disbursement in Second Quarter of 2003
International Development Association1267326Total Disbursement in Second Quarter of 2003
International Development Association-27520Total Interest Repayment in Second Quarter of 2003
International Development Association617884Total Disbursement in Third Quarter of 2003
International Development Association828900Total Disbursement in Third Quarter of 2003
International Development Association1106995Total Disbursement in Third Quarter of 2003
International Development Association465239Total Disbursement in Fourth Quarter of 2003
International Development Association1103890Total Disbursement in Fourth Quarter of 2003
International Development Association1200410Total Disbursement in Fourth Quarter of 2003
International Development Association-45280Total Interest Repayment in Fourth Quarter of 2003
International Development Association1433956Total Disbursement in First Quarter of 2004
International Development Association1612605Total Disbursement in First Quarter of 2004
International Development Association3311594Total Disbursement in First Quarter of 2004
International Development Association945479Total Disbursement in Second Quarter of 2004
International Development Association1564150Total Disbursement in Second Quarter of 2004
International Development Association1607948Total Disbursement in Second Quarter of 2004
International Development Association-281439Total Interest Repayment in Second Quarter of 2004
International Development Association342178Total Disbursement in Third Quarter of 2004
International Development Association591737Total Disbursement in Third Quarter of 2004
International Development Association2892916Total Disbursement in Third Quarter of 2004
International Development Association1043512Total Disbursement in Fourth Quarter of 2004
International Development Association2111285Total Disbursement in Fourth Quarter of 2004
International Development Association2640679Total Disbursement in Fourth Quarter of 2004
International Development Association-287061Total Interest Repayment in Fourth Quarter of 2004
International Development Association1178098Total Disbursement in First Quarter of 2005
International Development Association3188735Total Disbursement in First Quarter of 2005
International Development Association3458424Total Disbursement in First Quarter of 2005
International Development Association2154260Total Disbursement in Second Quarter of 2005
International Development Association2451725Total Disbursement in Second Quarter of 2005
International Development Association2800535Total Disbursement in Second Quarter of 2005
International Development Association-274270Total Interest Repayment in Second Quarter of 2005
International Development Association1748744Total Disbursement in Third Quarter of 2005
International Development Association1843556Total Disbursement in Third Quarter of 2005
International Development Association3351738Total Disbursement in Third Quarter of 2005
International Development Association129210Total Disbursement in Fourth Quarter of 2005
International Development Association818731Total Disbursement in Fourth Quarter of 2005
International Development Association1408186Total Disbursement in Fourth Quarter of 2005
International Development Association-281466Total Interest Repayment in Fourth Quarter of 2005
International Development Association250236Total Disbursement in First Quarter of 2006
International Development Association2020512Total Disbursement in First Quarter of 2006
International Development Association2323706Total Disbursement in First Quarter of 2006
International Development Association-15612419Total Disbursement in Second Quarter of 2006
International Development Association1039584Total Disbursement in Second Quarter of 2006
International Development Association1980147Total Disbursement in Second Quarter of 2006
International Development Association-286614Total Interest Repayment in Second Quarter of 2006
International Development Association17394727Total Disbursement in Second Quarter of 2006
International Development Association731626Total Disbursement in Third Quarter of 2006
International Development Association1227244Total Disbursement in Third Quarter of 2006
International Development Association1892465Total Disbursement in Third Quarter of 2006
International Development Association1197955Total Disbursement in Fourth Quarter of 2006
International Development Association1351199Total Disbursement in Fourth Quarter of 2006
International Development Association1611843Total Disbursement in Fourth Quarter of 2006
International Development Association-262630Total Interest Repayment in Fourth Quarter of 2006
International Development Association198903Total Disbursement in First Quarter of 2007
International Development Association1172437Total Disbursement in First Quarter of 2007
International Development Association2255906Total Disbursement in First Quarter of 2007
International Development Association-1227631Total Commitment Cancellations in Second Quarter of 2007
International Development Association158142Total Disbursement in Second Quarter of 2007
International Development Association472088Total Disbursement in Second Quarter of 2007
International Development Association1308995Total Disbursement in Second Quarter of 2007
International Development Association-261190Total Interest Repayment in Second Quarter of 2007
International Development Association-213083Total Disbursement in Third Quarter of 2007
International Development Association326435Total Disbursement in Third Quarter of 2007
International Development Association743940Total Disbursement in Third Quarter of 2007
International Development Association242867Total Disbursement in Fourth Quarter of 2007
International Development Association691282Total Disbursement in Fourth Quarter of 2007
International Development Association1302362Total Disbursement in Fourth Quarter of 2007
International Development Association-280880Total Interest Repayment in Fourth Quarter of 2007
International Development Association1458091Total Disbursement in First Quarter of 2008
International Development Association1619797Total Disbursement in First Quarter of 2008
International Development Association248490Total Disbursement in Second Quarter of 2008
International Development Association427105Total Disbursement in Second Quarter of 2008
International Development Association880453Total Disbursement in Second Quarter of 2008
International Development Association-302209Total Interest Repayment in Second Quarter of 2008
International Development Association25793Total Disbursement in Third Quarter of 2008
International Development Association173734Total Disbursement in Third Quarter of 2008
International Development Association537645Total Disbursement in Third Quarter of 2008
International Development Association1341645Total Disbursement in Fourth Quarter of 2008
International Development Association2308326Total Disbursement in Fourth Quarter of 2008
International Development Association-291831Total Interest Repayment in Fourth Quarter of 2008
International Development Association30000000Total Commitment in Fourth Quarter of 2008
International Development Association649154Total Disbursement in First Quarter of 2009
International Development Association-295601Total Interest Repayment in Second Quarter of 2009
International Development Association-319937Total Interest Repayment in Fourth Quarter of 2009
International Development Association-310118Total Interest Repayment in Second Quarter of 2010
International Development Association1046729Total Disbursement in Third Quarter of 2010
International Development Association1049883Total Disbursement in Third Quarter of 2010
International Development Association4593124Total Disbursement in Third Quarter of 2010
International Development Association-307754Total Interest Repayment in Fourth Quarter of 2010
International Development Association-9389Total Interest Repayment in Fourth Quarter of 2010
International Development Association3579224Total Disbursement in First Quarter of 2011
International Development Association3834488Total Disbursement in First Quarter of 2011
International Development Association-338751Total Interest Repayment in Second Quarter of 2011
International Development Association4167942Total Disbursement in Second Quarter of 2011
International Development Association-27263Total Interest Repayment in Second Quarter of 2011
International Development Association1810752Total Disbursement in Third Quarter of 2011
International Development Association11857Total Disbursement in Fourth Quarter of 2011
International Development Association49080Total Disbursement in Fourth Quarter of 2011
International Development Association49198Total Disbursement in Fourth Quarter of 2011
International Development Association-334683Total Interest Repayment in Fourth Quarter of 2011
International Development Association-886723Total Loan Repayment in Fourth Quarter of 2011
International Development Association-64425Total Interest Repayment in Fourth Quarter of 2011
International Development Association58140Total Disbursement in First Quarter of 2012
International Development Association111140Total Disbursement in First Quarter of 2012
International Development Association1054735Total Disbursement in First Quarter of 2012
International Development Association51651Total Disbursement in Second Quarter of 2012
International Development Association376817Total Disbursement in Second Quarter of 2012
International Development Association-318733Total Interest Repayment in Second Quarter of 2012
International Development Association-873157Total Loan Repayment in Second Quarter of 2012
International Development Association3178059Total Disbursement in Second Quarter of 2012
International Development Association5226231Total Disbursement in Second Quarter of 2012
International Development Association-67955Total Interest Repayment in Second Quarter of 2012
International Development Association22070Total Disbursement in Third Quarter of 2012
International Development Association40632Total Disbursement in Third Quarter of 2012
International Development Association-1116050Total Commitment Cancellations in Fourth Quarter of 2012
International Development Association-1079467Total Disbursement in Fourth Quarter of 2012
International Development Association85005Total Disbursement in Fourth Quarter of 2012
International Development Association-305265Total Interest Repayment in Fourth Quarter of 2012
International Development Association-869113Total Loan Repayment in Fourth Quarter of 2012
International Development Association-5383950Total Commitment Cancellations in Fourth Quarter of 2012
International Development Association-5383500Total Disbursement in Fourth Quarter of 2012
International Development Association2100000Total Disbursement in Fourth Quarter of 2012
International Development Association-93329Total Interest Repayment in Fourth Quarter of 2012
International Development Association-313871Total Interest Repayment in Second Quarter of 2013
International Development Association-844220Total Loan Repayment in Second Quarter of 2013
International Development Association-83669Total Interest Repayment in Second Quarter of 2013
International Development Association102000Total Disbursement in Third Quarter of 2013
International Development Association86500Total Disbursement in Third Quarter of 2013
International Development Association-21320Total Commitment Cancellations in Fourth Quarter of 2013
International Development Association-300320Total Interest Repayment in Fourth Quarter of 2013
International Development Association-853542Total Loan Repayment in Fourth Quarter of 2013
International Development Association-48691Total Commitment Cancellations in Fourth Quarter of 2013
International Development Association-47527Total Disbursement in Fourth Quarter of 2013
International Development Association-85365Total Interest Repayment in Fourth Quarter of 2013
International Development Association-316696Total Interest Repayment in Second Quarter of 2014
International Development Association-865112Total Loan Repayment in Second Quarter of 2014
International Development Association-87681Total Interest Repayment in Second Quarter of 2014
International Development Association-294318Total Interest Repayment in Fourth Quarter of 2014
International Development Association-823559Total Loan Repayment in Fourth Quarter of 2014
International Development Association-83139Total Interest Repayment in Fourth Quarter of 2014
International Development Association-273411Total Interest Repayment in Second Quarter of 2015
International Development Association-783972Total Loan Repayment in Second Quarter of 2015
International Development Association-78859Total Interest Repayment in Second Quarter of 2015
International Development Association-268472Total Interest Repayment in Fourth Quarter of 2015
International Development Association-778178Total Loan Repayment in Fourth Quarter of 2015
International Development Association-78277Total Interest Repayment in Fourth Quarter of 2015
International Development Association-243102Total Interest Repayment in Second Quarter of 2016
International Development Association-789610Total Loan Repayment in Second Quarter of 2016
International Development Association-77450Total Interest Repayment in Second Quarter of 2016
International Development Association-285418Total Interest Repayment in Fourth Quarter of 2016
International Development Association-769365Total Loan Repayment in Fourth Quarter of 2016
International Development Association-79316Total Interest Repayment in Fourth Quarter of 2016
International Development Association-239145Total Interest Repayment in Second Quarter of 2017
International Development Association-762876Total Loan Repayment in Second Quarter of 2017
International Development Association-75564Total Interest Repayment in Second Quarter of 2017
International Development Association-273660Total Interest Repayment in Fourth Quarter of 2017
International Development Association-780953Total Loan Repayment in Fourth Quarter of 2017
International Development Association-79716Total Interest Repayment in Fourth Quarter of 2017
International Development Association-259489Total Interest Repayment in Second Quarter of 2018
International Development Association-796393Total Loan Repayment in Second Quarter of 2018
International Development Association-80393Total Interest Repayment in Second Quarter of 2018
International Development Association-249111Total Interest Repayment in Fourth Quarter of 2018
International Development Association-772201Total Loan Repayment in Fourth Quarter of 2018
International Development Association-77675Total Interest Repayment in Fourth Quarter of 2018
International Development Association-207134Total Loan Repayment in Fourth Quarter of 2018
International Development Association-246047Total Interest Repayment in Second Quarter of 2019
International Development Association-771932Total Loan Repayment in Second Quarter of 2019
International Development Association-76870Total Interest Repayment in Second Quarter of 2019
International Development Association-207062Total Loan Repayment in Second Quarter of 2019Project Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportCredit AgreementAgreementContract AwardsProject URLProcurement Notices
Intermediate Results Indicator
Water users provided with irrigation and drainage services (number)
The end target will be revised with the cancellation of US$ 6.5 million
Irrigation sub-projects (category A1) being supported are now underway
Intermediate Results Indicator
Water users associations that are operational (number)
The end target will be revised with the cancellation of US$ 6.5 million
Irrigation sub-projects (category A1) being supported are now underway
Intermediate Results Indicator
Infrastructure built or rehabilitated (number)
The end target will be revised with the cancellation of US$ 6.5 million
Intermediate Results Indicator
Sub-projects financed and executed (number)
The end target will be revised with the cancellation of US$ 6.5 million
Intermediate Results Indicator
Saving schemes established and functioning (number)
The end target will be revised with the cancellation of US$ 6.5 million
Updated data not provided
Intermediate Results Indicator
Processing Units
The end target will be revised with the cancellation of US$ 6.5 million
Intermediate Results Indicator
Storage Facilities
The end target will be revised with the cancellation of US$ 6.5 million
Intermediate Results Indicator
Slaughterhouses
The end target will be revised with the cancellation of US$ 6.5 million
Intermediate Results Indicator
Research studies developed (number)
The end target will be revised with the cancellation of US$ 6.5 million
Intermediate Results Indicator
ACSs established and functioning (number)
Intermediate Results Indicator
CROAs established and functioning (number)
Intermediate Results Indicator
Client days of training provided (number)
The end target will be revised with the cancellation of US$ 6.5 million
Intermediate Results Indicator
Dams
The end target will be revised with the cancellation of US$ 6.5 million
Intermediate Results Indicator
Average financial rate of return of sub-projects (%)
Intermediate Results Indicator
Production of key crops financed through the sub projects (increase in %, suppl. value: crops in tons)
see disaggregated data on each crop
see disaggregated data on each crop
Intermediate Results Indicator
Targeted clients satisfied with agricultural services (%)
The end target will be revised with the cancellation of US$ 6.5 million
Updated data not provided yet. To be provided by the final evaluation
Intermediate Results Indicator
Rice Production
The end target will be revised with the cancellation of US$ 6.5 million
Intermediate Results Indicator
Maize Production
The end target will be revised with the cancellation of US$ 6.5 million
Intermediate Results Indicator
Peanuts Production
The end target will be revised with the cancellation of US$ 6.5 million
Intermediate Results Indicator
National Germplasm Bank rehabilitated and material at risk regenerated (yes/no)
The end target will be revised with the cancellation of US$ 6.5 million
Intermediate Results Indicator
Diagnostic study on the national agricultural research system completed (yes/no)
The end target will be revised with the cancellation of US$ 6.5 million
Intermediate Results Indicator
Rice Production
Intermediate Results Indicator
Maize Production
Intermediate Results Indicator
Peanuts Production
Intermediate Results Indicator
Additional area provided with irrigation and drainage services (ha)
The end target will be revised with the cancellation of US$ 6.5 million
Intermediate Results Indicator
Area cultivated with improved technologies and inputs provided through Project-supported sub-projects (ha)
The end target will be revised with the cancellation of US$ 6.5 million
PDO Indicator
Female beneficiaries (among members of organizations)
PDO Indicator
Direct project beneficiaries
Number of members of organizations supported by the Project * 5 (average number of persons per rural household in Madagascar)
PDO Indicator
Female beneficiaries
PDO Indicator
Average revenue increase among beneficiaries (%)
PDO Indicator
Infrastructure functioning one year after completion and mechanism in place to finance operations and maintenance (%)
The 85% target applies to sub- projects financed under the additional credit. Data will also be available for sub-projects thatwere financed under the original credit, but these will be reported separately
PDO Indicator
Sub-projects functioning one year after completion (%)
The 85% target applies to sub- projects financed under the additional credit. Data will also be available for sub-projects thatwere financed under the original credit, but these will be reported separately.
PDO Indicator
Sub-projects having satisfactorily developed and implemented an Environ-mental Action Plan (%)
PDO Indicator
Members of organizations supported by the Project
Updated data not provided
0.00
525000.00
525000.00
525000.00
525000.00
525000.00
525000.00
525000.00
525000.00
525000.00
525000.00
525000.00
525000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1095833.33
1095833.33
1095833.33
1095833.33
1095833.33
1095833.33
1095833.33
1095833.33
1095833.33
1095833.33
1095833.33
1095833.37
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
525000.00
525000.00
525000.00
525000.00
525000.00
525000.00
525000.00
525000.00
525000.00
525000.00
525000.00
525000.00
1400000.01
1400000.01
1400000.02
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1400000.00
1095833.33
1095833.33
1095833.33
1095833.33
1095833.33
1095833.33
1095833.33
1095833.33
1095833.33
1095833.33
1095833.33
1095833.33
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
750000.00
750000.00
750000.00
750000.00
750000.00
750000.00
750000.00
750000.00
750000.00
750000.00
750000.00
750000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
1500000.00
333333.33
333333.33
333333.34
333333.33
333333.33
333333.34
333333.33
333333.33
333333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Borrower to maintain full project staff at national, provincial levels
Carry out the project according to procedures of Implementation Manual
Submit to IDA an annual work plan
Annual progress reviews
Terms and conditions of Grants to farmers
44000-P160442
World Bank
International Development Association
International Development Association
MADAGASCAR
Madagascar Basic Education Support Project
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Anna Olefir
aolefir@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Primary EducationEarly Childhood EducationStandards, Curriculum and TextbooksDisaster Risk ManagementClimate changeTeachersDisaster Risk ReductionAccess to EducationPrivate Sector Delivery of EducationNeglected tropical diseasesEducationAdaptationDisease Control
International Development Association55000000Total Commitment in First Quarter of 2018
International Development Association634276Total Disbursement in Third Quarter of 2018
International Development Association1129720Total Disbursement in Fourth Quarter of 2018
International Development Association2700000Total Disbursement in Fourth Quarter of 2018
International Development Association132362Total Disbursement in First Quarter of 2019
International Development Association539894Total Disbursement in First Quarter of 2019
International Development Association174967Total Disbursement in Second Quarter of 2019
International Development Association329616Total Disbursement in Second Quarter of 2019
International Development Association-19743Total Interest Repayment in Second Quarter of 2019
International Development Association349089Total Disbursement in Third Quarter of 2019Project Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementGrant or Trust Fund AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Diana Region
-13.5000 49.0000
Sava Region
-14.2000 49.8000
Sofia Region
-15.2000 48.4000
Analanjirofo Region
-16.5000 49.5000
Boeny Region
-16.3000 46.1000
Betsiboka Region
-17.2000 47.1000
Alaotra Mangoro Region
-17.9000 48.4000
Melaky Region
-17.6000 44.8000
Bongolava Region
-18.5000 46.1000
Vakinankaratra Region
-19.7000 46.9000
Itasy Region
-18.9500 46.9500
Analamanga Region
-18.4500 47.5000
Atsinanana Region
-19.0000 48.9000
Menabe Region
-20.2000 45.0700
Amoron'i Mania Region
-20.5000 46.7000
Haute Matsiatra Region
-21.3700 46.5000
Vatovavy Fitovinany Region
-21.3000 47.9000
Ihorombe Region
-22.3000 46.2000
Atsimo-Atsinanana Region
-23.2000 47.4000
Anosy Region
-24.1000 46.3000
Androy Region
-24.7500 45.5000
Atsimo-Andrefana Region
-23.2000 44.4000
Intermediate Results Indicator
Teachers recruited or trained
Intermediate Results Indicator
No of children benefiting from stimulation activities provided by ECD educators trained under the project
Intermediate Results Indicator
No. of trained and certifed preschool educators
Intermediate Results Indicator
Students benefiting from direct interventions to enhance learning
Intermediate Results Indicator
No of teachers trained in teaching reading, writing, and mathematics for the early grades
Intermediate Results Indicator
Students benefiting from direct interventions to enhance learning - Female
Intermediate Results Indicator
Number of qualified teachers deployed and redeployed in rural schools
Intermediate Results Indicator
Number of students learning assessment and SDI reports disseminated
Intermediate Results Indicator
No of EMIS reports available timely (within 8 months after the beginning of the school year)
Intermediate Results Indicator
No of classrooms constructed or rehabilitated under the project
Intermediate Results Indicator
No of project total direct beneficiaries
Intermediate Results Indicator
Teachers recruited or trained - Female (RMS requirement)
Intermediate Results Indicator
No of students benefitting from the national school deworming and folic acid supplementation program
Intermediate Results Indicator
No of school principals and local supervisors receiving training under the project
Intermediate Results Indicator
Percentage of schools receiving school grants funded by the project within the first month of the beginning of the school year
Intermediate Results Indicator
School principals absence rate
Intermediate Results Indicator
of which percentage of female
Intermediate Results Indicator
Publicly available yearly survey reports of project beneficiaries and education stakeholders (Citizen engagement indicator)
PDO Indicator
Average number of words correctly read per minute in Malagasy a 2nd grader in public schools
PDO Indicator
No of qualified teachers deployed and redeployed in rural schools
PDO Indicator
No of students using classrooms constructed under the project
PDO Indicator
No of established community-based ECD centers in under-served areas
PDO Indicator
Average promotion rate in the first two sub-cycles of basic education in public schools
0.00
34980.00
70004.00
167948.00
205260.00
241120.00
275132.00
310596.00
353936.00
392832.00
422224.00
219736.00
457776.00
484440.00
508816.00
532488.00
549340.00
570680.00
603680.00
884573.33
884573.33
884573.33
884573.33
884573.33
884573.33
884573.33
884573.33
884573.33
884573.33
884573.33
884573.37
1031962.33
1031962.33
1031962.33
1031962.33
1031962.33
1031962.33
1031962.33
1031962.33
1031962.33
1031962.33
1031962.33
1031962.37
1284581.33
1284581.33
1284581.33
1284581.33
1284581.33
1284581.33
1284581.33
1284581.33
1284581.33
1284581.33
1284581.33
1284581.37
1131734.22
1131734.22
1131734.22
1131734.22
1131734.22
1131734.22
1131734.22
1131734.22
1131734.24
0.00
0.00
0.00
0.00
36666.67
36666.67
36666.66
210000.00
210000.00
210000.00
257000.00
257000.00
257000.00
692000.00
692000.00
692000.00
740000.00
740000.00
740000.00
1420333.33
1420333.33
1420333.34
1843333.33
1843333.33
1843333.34
1700333.33
1700333.33
1700333.34
2436666.67
2436666.67
2436666.66
2110000.00
2110000.00
2110000.00
2270000.00
2270000.00
2270000.00
2316666.67
2316666.67
2316666.66
2787000.00
2787000.00
2787000.00
2220000.00
2220000.00
2220000.00
2370000.00
2370000.00
2370000.00
2613333.33
2613333.33
2613333.34
2430000.00
2430000.00
2430000.00
1846666.67
1846666.67
1846666.66
1696666.67
1696666.67
1696666.66
1570000.00
1570000.00
1570000.00
Schedule 2. Section I.I. The Recipient shall, not later than six (6) months after the Effective Date select and at all times duringProject implementation retain the services of an independent verification agent for the purpose of certifying the accuracy of theDLI achievement.
Schedule 2. Section 1 C.2. The annual work plan and budget for the Project for the first year of Project implementation shall befurnished no later than one (1) month after the Effective Date.
44000-P113971
World Bank
International Development Association
SECRETARIAT NATIONAL
International Development Association
SECRETARIAT NATIONALMADAGASCAR
Integrated Growth Poles and Corridor Project 2
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Eneida Herrera Fernandes
efernandes1@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Agricultural markets, commercialization and agri-businessOther Public AdministrationOther Water Supply, Sanitation and Waste ManagementRural and Inter-Urban RoadsTradeEnterprise DevelopmentPublic Private PartnershipsMSME DevelopmentRural MarketsMunicipal Institution BuildingMSME FinanceJob CreationFinancial Infrastructure and AccessJobsRural DevelopmentAdministrative and Civil Service ReformRural Infrastructure and service deliveryUrban Infrastructure and Service DeliveryInvestment and Business ClimateFragility, Conflict and ViolencePublic AdministrationUrban DevelopmentBusiness Enabling Environment
International Development Association50000000Total Commitment in Fourth Quarter of 2014
International Development Association4638837Total Disbursement in First Quarter of 2015
International Development Association212301Total Disbursement in Third Quarter of 2015
International Development Association260193Total Disbursement in Third Quarter of 2015
International Development Association117416Total Disbursement in Fourth Quarter of 2015
International Development Association133575Total Disbursement in Fourth Quarter of 2015
International Development Association283631Total Disbursement in Fourth Quarter of 2015
International Development Association-20288Total Interest Repayment in Fourth Quarter of 2015
International Development Association316803Total Disbursement in First Quarter of 2016
International Development Association433924Total Disbursement in First Quarter of 2016
International Development Association448548Total Disbursement in First Quarter of 2016
International Development Association478335Total Disbursement in Second Quarter of 2016
International Development Association1848474Total Disbursement in Second Quarter of 2016
International Development Association-22184Total Interest Repayment in Second Quarter of 2016
International Development Association277608Total Disbursement in Third Quarter of 2016
International Development Association1313936Total Disbursement in Fourth Quarter of 2016
International Development Association1343358Total Disbursement in Fourth Quarter of 2016
International Development Association2225378Total Disbursement in Fourth Quarter of 2016
International Development Association-32208Total Interest Repayment in Fourth Quarter of 2016
International Development Association1949945Total Disbursement in First Quarter of 2017
International Development Association3217395Total Disbursement in First Quarter of 2017
International Development Association787270Total Disbursement in Second Quarter of 2017
International Development Association2252942Total Disbursement in Second Quarter of 2017
International Development Association-55146Total Interest Repayment in Second Quarter of 2017
International Development Association608588Total Disbursement in Third Quarter of 2017
International Development Association724948Total Disbursement in Third Quarter of 2017
International Development Association813534Total Disbursement in Fourth Quarter of 2017
International Development Association1582749Total Disbursement in Fourth Quarter of 2017
International Development Association2070293Total Disbursement in Fourth Quarter of 2017
International Development Association-89775Total Interest Repayment in Fourth Quarter of 2017
International Development Association906209Total Disbursement in First Quarter of 2018
International Development Association1519710Total Disbursement in First Quarter of 2018
International Development Association121152Total Disbursement in Second Quarter of 2018
International Development Association762337Total Disbursement in Second Quarter of 2018
International Development Association1676338Total Disbursement in Second Quarter of 2018
International Development Association-112417Total Interest Repayment in Second Quarter of 2018
International Development Association1376643Total Disbursement in Third Quarter of 2018
International Development Association1511107Total Disbursement in Third Quarter of 2018
International Development Association316549Total Disbursement in Fourth Quarter of 2018
International Development Association2446665Total Disbursement in Fourth Quarter of 2018
International Development Association2456031Total Disbursement in Fourth Quarter of 2018
International Development Association-125862Total Interest Repayment in Fourth Quarter of 2018
International Development Association394887Total Disbursement in First Quarter of 2019
International Development Association465846Total Disbursement in First Quarter of 2019
International Development Association824945Total Disbursement in Second Quarter of 2019
International Development Association1700057Total Disbursement in Second Quarter of 2019
International Development Association-153497Total Interest Repayment in Second Quarter of 2019
International Development Association454077Total Disbursement in Third Quarter of 2019
International Development Association1466527Total Disbursement in Third Quarter of 2019Project Information DocumentProject Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Toliara
-23.3500 43.6670
Fort Dauphin
-25.0320 46.9830
Antsiranana
-12.2790 49.2920
Antananarivo
-18.9140 47.5360
Intermediate Results Indicator
Increase in revenues from target cash crop production for smallholders in the target corridors in the target poles (MGA billion)
Intermediate Results Indicator
Number of recommended reforms or policies adopted
Intermediate Results Indicator
Increase in annual municipal revenues collected in the target poles (MGA billion)
Intermediate Results Indicator
Of which urban municipalities
Intermediate Results Indicator
Of which rural municipalities
Intermediate Results Indicator
Increase in export value for the selected crops in the targeted poles (In US$ Million)
Intermediate Results Indicator
Hotel rooms for establishments in the target poles
Intermediate Results Indicator
Percentage of municipal budgets executed for investment by targeted municipalities
Intermediate Results Indicator
Roads Rehabilitated
PDO Indicator
Number of formal jobs created in the targeted poles
PDO Indicator
Of which in tourism
PDO Indicator
Of which in agribusiness
PDO Indicator
Number of formal businesses newly registered in the targeted poles
PDO Indicator
Of which in tourism
PDO Indicator
of which in agribusiness
0.00
0.00
0.00
700000.00
230000.00
230000.00
230000.00
250000.00
250000.00
250000.00
566666.66
566666.67
566666.67
1583333.33
1583333.33
1583333.34
1693333.33
1693333.33
1693333.34
1633333.33
1633333.33
1633333.34
1250000.00
1250000.00
1250000.00
1166666.66
1166666.67
1166666.67
1083333.33
1083333.33
1083333.34
1050000.00
1050000.00
1050000.00
966666.66
966666.67
966666.67
933333.33
933333.33
933333.34
816666.66
816666.67
816666.67
700000.00
700000.00
700000.00
666666.66
666666.67
666666.67
640000.00
640000.00
640000.00
620000.00
620000.00
620000.00
583333.33
583333.33
583333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
662691.00
662691.00
662691.00
662691.00
662691.00
662691.00
662691.03
377766.69
377766.69
377766.69
377766.69
377766.69
377766.69
377766.69
377766.69
377766.69
377766.69
377766.69
377766.64
1113986.06
1113986.06
1113986.06
1113986.06
1113986.06
1113986.06
1113986.06
1113986.06
1113986.06
1113986.06
1113986.06
1113986.08
1100000.00
1100000.00
1100000.00
1100000.00
1100000.00
1100000.00
1100000.00
1100000.00
1100000.00
1100000.00
1100000.00
1100000.00
909177.50
909177.50
909177.50
909177.50
909177.50
909177.50
909177.50
909177.50
909177.50
909177.50
909177.50
909177.50
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.33
83333.37
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Finance Agreement :PIU Staff | Description :Without limitation to the provisions of paragraph (a) of Schedule 2, Section 1.2 of theFinancing Agreement, the PIU shall include, inter alia:(i) at the central level: (A) a coordinator; (B) a procurement specialist;(C) a financial manager; (D) an accountant; (E) a monitoring and evaluation specialist; (F) an environmental and social safeguardspecialist; and (G) an accounts assistant; recruite | Due Date :31-May-2015
Finance Agreement :External Auditor | Description :In addition, no later than three (3) months after the Effective Date, theRecipient shall recruit an internal auditor in accordance with the provisions of Section III of Schedule 2 to this Agreement, andon the basis of terms of reference, qualifications and experience acceptable to the Association, to be assigned at the centrallevel. | Due Date :31-Aug-2015
Finance Agreement :PIU_Targeted Regions | Description :In each Targeted Region: No later than six (6) months after the EffectiveDate, the Recipient shall recruit (x) a coordinator and (y) one (1) account assistant, all in accordance with the provisions ofSection III of Schedule 2 to this Agreement, and each on the basis of terms of reference, qualifications and experience acceptableto the Association, to be assigned one in each Targeted Region. | Due Date :30-Nov-2015
Finance Agreement :Investment Climate Reform Committee | Description :No later than three (3) months after the Effective Date, theRecipient shall establish and thereafter maintain a structure satisfactory to the Association to lead and manage the investmentclimate reform process within the country of the Recipient to be established under the control of the Office of the President, withmandate, composition and resources acceptable to the Association. | Due Date :31-Aug-2015
Finance Agreement :Project Monitoring, Reporting and Evaluation | Description :No later than twelve (12) months after the EffectiveDate, or such other date agreed with the Association, and each year afterwards, the Recipient shall cause an operational audit forsubcomponent 1.2(d) of the Project (or selected activities under said subcomponent) to be carried out by an independent auditor. |Due Date :31-Mar-2016
Finance Agreement :Financial Management, Financial Reports and Audits | Description :In order to ensure the timely carrying out ofthe audits referred to in Section II. B.3 of this Schedule, the Recipient shall engage independent auditors for the purpose notlater than six (6) months after the Effective Date, in accordance with the provisions of Section III of Schedule 2 of the FinancingAgreement. | Due Date :18-Sep-2015
Finance Agreement :Investment Climate Reform Committee | Description :No later than three (3) months after the Effective Date, theRecipient shall establish and thereafter maintain a structure satisfactory to the Association to lead and manage the investmentclimate reform process within the country of the Recipient to be established under the control of the Office of the President, withmandate, composition and resources acceptable to the Association. | Due Date :31-Aug-2015
Finance Agreement :Project Monitoring, Reporting and Evaluation | Description :Twenty-four (24) months after the Effective Date, orat any other date agreed with the Association, the Recipient shall, in conjunction with the Association, carry out a mid-termreview of the Project (the “Mid-term Review”), covering the progress achieved in the implementation of the Project. | Due Date:20-Jun-2017
Finance Agreement :Project Monitoring, Reporting and Evaluation | Description :The Recipient shall prepare and furnish to theAssociation not less than three (3) months prior to the beginning of the Mid-term Review, a report integrating the results of themonitoring and evaluation activities performed pursuant to this Agreement, on the progress achieved in the carrying out of theProject during the period preceding the date of such report, and setting out the measures recomm | Due Date :20-Mar-2017
Finance Agreement :Project Monitoring, Reporting and Evaluation | Description :For purposes of Section 4.08 (c) of the GeneralConditions, the report on the execution of the Project and related plan required pursuant to that Section shall be furnished to theAssociation not later than six months before the Closing Date. | Due Date :29-Mar-2019
Finance Agreement :PIU Staff-Internal Auditor | Description :In addition, no later than three (3) months after the Effective Date,the Recipient shall recruit an internal auditor within the PIU in accordance with the provisions of Section III of Schedule 2 tothis Agreement, and on the basis of terms of reference, qualifications and experience acceptable to the Association, to be assignedat the central level. | Due Date :31-Aug-2015
44000-P154698
World Bank
International Development Association
PN-BVPI
International Development Association
PN-BVPIMADAGASCAR
GEF Sustainable Landscape Management Project
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Giuseppe Fantozzi
gfantozzi@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Agricultural markets, commercialization and agri-businessIrrigation and DrainagePublic Administration - Agriculture, Fishing & ForestryOther Agriculture, Fishing and ForestryRural and Inter-Urban RoadsRenewable Natural Resources Asset ManagementLandscape ManagementRural MarketsGeospatial ServicesAdaptationClimate changeRural DevelopmentRural Infrastructure and service deliveryMitigation
International Development Association65000000Total Commitment in First Quarter of 2017
International Development Association672621Total Disbursement in Fourth Quarter of 2017
International Development Association-1057Total Interest Repayment in First Quarter of 2018
International Development Association3617700Total Disbursement in Second Quarter of 2018
International Development Association-2579Total Interest Repayment in Third Quarter of 2018
International Development Association19898Total Disbursement in First Quarter of 2019
International Development Association46126Total Disbursement in First Quarter of 2019
International Development Association-17118Total Interest Repayment in First Quarter of 2019
International Development Association-107266Total Disbursement in Second Quarter of 2019
International Development Association103441Total Disbursement in Second Quarter of 2019
International Development Association553922Total Disbursement in Second Quarter of 2019
International Development Association184410Total Disbursement in Third Quarter of 2019
International Development Association-16413Total Interest Repayment in Third Quarter of 2019Project Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Vavatenina
-17.4670 49.2000
Soanierana Ivongo
-16.9170 49.5830
Sava Region
-14.2000 49.8000
Sofia Region
-15.2000 48.4000
Analanjirofo Region
-16.5000 49.5000
Boeny Region
-16.3000 46.1000
Bealanana
-14.5430 48.7500
Marovoay
-16.1110 46.6440
Andapa
-14.6500 49.6500
Intermediate Results Indicator
Landscape management plans approved by the National Steering Committee and Regional Monitoring Committees
Intermediate Results Indicator
COBA operational
Intermediate Results Indicator
Pilot payment for environmental services mechanism established (Number, Custom)
Intermediate Results Indicator
CTDs
Intermediate Results Indicator
Producer associations which have adopted good practices according to defined criteria
Intermediate Results Indicator
Farmers reached with agricultural assets and services (disaggregated by sex)
Intermediate Results Indicator
Female
Intermediate Results Indicator
Policy Briefs prepared, validated and disseminated to stakeholders
Intermediate Results Indicator
Area in protected areas in the targeted landscapes with Management Effectiveness Tracking Tool (METT) score over 70 (Number, Custom)
Intermediate Results Indicator
Irrigation systems managed by Water User Associations
Intermediate Results Indicator
CSAs, STDs and CTDs operational (disaggregated by institution)
Intermediate Results Indicator
CSAs
Intermediate Results Indicator
STDs
Intermediate Results Indicator
Share of target beneficiaries with score âSatisfiedâ or above on application of integrated landscape approach in targeted landscapes (disaggregated by sex)
Intermediate Results Indicator
Female
Intermediate Results Indicator
Male
Intermediate Results Indicator
Spatial information system established and operational
Intermediate Results Indicator
Area under conservation with a management plan (Hectare(Ha), Custom)
PDO Indicator
Clients who have adopted an improved agr. technology promoted by the project
PDO Indicator
Direct project beneficiaries
PDO Indicator
Clients who adopted an improved agr. technology promoted by project – female
PDO Indicator
Area provided with irrigation and drainage services (ha)
PDO Indicator
Land area where sustainable land mgt. practices were adopted as a result of proj
PDO Indicator
Area provided with irrigation and drainage services - Improved (ha)
PDO Indicator
Female beneficiaries
0.00
0.00
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
2527500.00
2527500.00
2527500.00
2527500.00
2527500.00
2527500.00
2527500.00
2527500.00
2527500.00
2527500.00
2527500.00
2527500.00
3508333.33
3508333.33
3508333.33
3508333.33
3508333.33
3508333.33
3508333.33
3508333.33
3508333.33
3508333.33
3508333.33
3508333.33
1333333.33
1333333.33
1333333.33
1333333.33
1333333.33
1333333.33
1333333.33
1333333.33
1333333.33
1333333.33
1333333.33
1333333.33
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
666666.67
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
2527500.00
2527500.00
2527500.00
2527500.00
2527500.00
2527500.00
2527500.00
2527500.00
2527500.00
2527500.00
2527500.00
2527500.00
3508333.33
3508333.33
3508333.33
3508333.33
3508333.33
3508333.33
3508333.33
3508333.33
3508333.33
3508333.33
3508333.33
3508333.33
1333333.33
1333333.33
1333333.33
1333333.33
1333333.33
1333333.33
1333333.33
1333333.33
1333333.33
1333333.33
1333333.33
1333333.33
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Finance Agreement :Annual Work Plan and Budget for the first year of Project implementation | Description :The annual work plan andbudget for the Project for the first year of Project implementation, and the evidence which may be required for the implementationof the activities included in the annual work plan and budget for that period, shall be furnished to the Association, not laterthanone (1) month after the Effectiveness Date. | Due Date :26, November 2017
Finance Agreement :Establishment of a Procurement complaint handling mechanism | Description :The Recipient shall have establisheda procurement complaint handling mechanism acceptable to the Association not later than three (3) months after the EffectivenessDate. | Due Date :26 January, 2018
Finance Agreement :Irrigation infrastructure and large dams | Description :The Project shall not finance any new constructions orrehabilitation of large-scale irrigation facilities; nor shall it finance any dams above 15 meters or reservoirs of more than three(3) million cubic meter.
44000-P164137
World Bank
International Development Association
MINISTRY OF FINANCE AND BUDGET (MFB)
International Development Association
MINISTRY OF FINANCE AND BUDGET (MFB)MADAGASCAR
Public Finance Sustainability and Investment DPF II
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Natasha Sharma
nsharma9@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Insurance and PensionOther Energy and ExtractivesCentral Government (Central Agencies)Law and JusticeOther Non-bank Financial InstitutionsJudicial and other Dispute Resolution MechanismsFinancial StabilityEnergy Policies & ReformDomestic Revenue AdministrationFinancial inclusionRule of LawPublic Assets and Investment ManagementEnergyPublic Finance ManagementFinancial Infrastructure and AccessPublic Private PartnershipsPublic Administration
International Development Association45000000Total Commitment in Fourth Quarter of 2017
International Development Association45161468Total Disbursement in Fourth Quarter of 2017Financing AgreementContract AwardsProject URLProcurement Notices
Intermediate Results Indicator
Value of tax expenditures eliminated (in billion MGA)
Intermediate Results Indicator
Revenue effort increased (in percent of GDP)
Intermediate Results Indicator
Share of new PPPs that follow appraisal and selection processes under the PPP Act
Intermediate Results Indicator
Share of domestically financed investment projects above MGA 5 billion subject to the new standardized selection criteria and appraisal methodology
Intermediate Results Indicator
Selected transfers reduced as a share of total expenditure
Intermediate Results Indicator
• o/w: transfer to the Pension Fund
Intermediate Results Indicator
• o/w: Fuel subsidies
Intermediate Results Indicator
Share of priority spending on social sectors (percent of GDP)
Intermediate Results Indicator
Share (in value) of new power generation contracts awarded competitively and published of the total contracts
Intermediate Results Indicator
Percentage of cases randomly assigned (at commercial justice)
Intermediate Results Indicator
Number of days to resolve a commercial conflict
Intermediate Results Indicator
Extent of risk based supervision - risk-based supervision in place for MFIs
0.00
0.00
44000-P162279
World Bank
International Development Association
MINISTRY OF FINANCE AND BUDGET
International Development Association
MINISTRY OF FINANCE AND BUDGETMADAGASCAR
MG - Inclusive and Resilient Growth DPO
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Francesco Strobbe
fstrobbe@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Banking InstitutionsRural and Inter-Urban RoadsEnergy Transmission and DistributionCentral Government (Central Agencies)Social ProtectionEnergy Policies & ReformRural Infrastructure and service deliveryLand Administration and ManagementDomestic Revenue AdministrationFinancial Infrastructure and AccessRural DevelopmentPublic Finance ManagementFinancial inclusionEnergySocial ProtectionCivil Registration and IdentificationSocial Safety NetsPublic Administration
International Development Association45000000Total Commitment in Fourth Quarter of 2017
International Development Association45320330Total Disbursement in Fourth Quarter of 2017Financing AgreementContract AwardsProject URLProcurement Notices
0.00
0.00
44000-P160848
World Bank
International Development Association
International Development Association
MADAGASCAR
Improving Nutrition Outcomes using the Multiphase Programmatic Approach
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Voahirana Hanitriniala Rajoela
vrajoela@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Public Administration - HealthHealthHealth System StrengtheningReproductive and Maternal HealthHealth Service DeliveryClimate changeNutrition and Food SecurityHealth FinanceMitigationChild HealthNeglected tropical diseasesDisease ControlNutritionAdaptationHealth Systems and Policies
International Development Association80000000Total Commitment in Fourth Quarter of 2017
International Development Association278650Total Disbursement in Second Quarter of 2018
International Development Association1017333Total Disbursement in Second Quarter of 2018
International Development Association1782343Total Disbursement in Third Quarter of 2018
International Development Association9316990Total Disbursement in Third Quarter of 2018
International Development Association265763Total Disbursement in Fourth Quarter of 2018
International Development Association986543Total Disbursement in Fourth Quarter of 2018
International Development Association-615Total Disbursement in First Quarter of 2019
International Development Association324333Total Disbursement in First Quarter of 2019
International Development Association1094731Total Disbursement in Second Quarter of 2019
International Development Association1946551Total Disbursement in Second Quarter of 2019
International Development Association415483Total Disbursement in Third Quarter of 2019
International Development Association1695928Total Disbursement in Third Quarter of 2019Project Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementGrant or Trust Fund AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Republic of Madagascar
-20.0000 47.0000
Intermediate Results Indicator
People who have received essential health, nutrition, and population (HNP) services
Intermediate Results Indicator
Number of community health and nutrition workers trained by the project
Intermediate Results Indicator
Number of children immunized
Intermediate Results Indicator
Number of women and children who have received basic nutrition services
Intermediate Results Indicator
Number of women receiving ANC during the first 3 months of pregnancy
Intermediate Results Indicator
Number of functioning community sites
Intermediate Results Indicator
Number of severe acute malnutrition (SAM) cases treated in the outpatient SAM treatment program
Intermediate Results Indicator
Number of primary care facilities having tracer medications in stock
Intermediate Results Indicator
Grievances responded to and/or resolved within the stipulated service standard for response times
Intermediate Results Indicator
Percentage of community health and nutrition workers achieving satisfactory score on the community service delivery indicator (SDI)score
Intermediate Results Indicator
Percentage of providers at the primary care facilities achieving satisfactory score on the service delivery indicator (SDI) score
Intermediate Results Indicator
Percentage of primary care facilities providing monthly activity reports on time
Intermediate Results Indicator
Percentage of communes that organized at least 1 CoSan meeting in the past 6 months
PDO Indicator
Number of facility-based deliveries
PDO Indicator
Percentage of children 6-59 months of age receiving vitamin A supplementation within the past 6 months (by sex)
PDO Indicator
Percentage of infants 0-5 months of age exclusively breastfed (by sex)
PDO Indicator
Percentage of women receiving any IFA tablets at last pregnancy
PDO Indicator
Percentage of children 6-23 months of age with minimum meal frequency (by sex)
0.00
0.00
234960.00
401040.00
238320.00
550560.00
645760.00
357680.00
790240.00
901600.00
490800.00
1050000.00
1126640.00
1207760.00
634960.00
1321840.00
1382640.00
716960.00
1494400.00
1566560.00
808080.00
1671680.00
1756080.00
914720.00
1896160.00
1942480.00
975120.00
2015840.00
2101920.00
2111920.00
1036720.00
2049600.00
2082160.00
1035920.00
2016960.00
1949440.00
962960.00
1899920.00
1858320.00
910400.00
1785120.00
1744160.00
1705760.00
840480.00
1652000.00
1615680.00
792080.00
1549200.00
1493760.00
728640.00
1430320.00
1392720.00
679600.00
1324160.00
1284640.00
1244400.00
605520.00
1176080.00
1132080.00
548480.00
1064480.00
1034240.00
509600.00
997280.00
962720.00
468960.00
914720.00
884560.00
854240.00
415280.00
59920.00
0.00
0.00
234960.00
401040.00
238320.00
550560.00
645760.00
357680.00
790240.00
901600.00
490800.00
1050000.00
1126640.00
1207760.00
634960.00
1321840.00
1382640.00
716960.00
1494400.00
1566560.00
808080.00
1671680.00
1756080.00
914720.00
1896160.00
1942480.00
975120.00
2015840.00
2101920.00
2111920.00
1036720.00
2049600.00
2082160.00
1035920.00
2016960.00
1949440.00
962960.00
1899920.00
1858320.00
910400.00
1785120.00
1744160.00
1705760.00
840480.00
1652000.00
1615680.00
792080.00
1549200.00
1493760.00
728640.00
1430320.00
1392720.00
679600.00
1324160.00
1284640.00
1244400.00
605520.00
1176080.00
1132080.00
548480.00
1064480.00
1034240.00
509600.00
997280.00
962720.00
468960.00
914720.00
884560.00
854240.00
415280.00
59920.00
Schedule 2. Section I. F (1). The Recipient shall, not later than six (6) months after the Effective Date, adopt a FiduciaryCapacity Building Plan in form and content satisfactory to the Association.
Schedule 2. Section I. E (2). The Recipient shall furnish to the Association, the annual work plan and budget for the Project forthe first year of Project implementation approved by the Steering Committee, for the Association's review and approval no laterthan one (1) month after the Effective Date.
Schedule 2. Section I. C (1). The Recipient shall, not later than three months after the Effective Date, adopt the PBF OperationsManual.
44000-P074086
World Bank
International Development Association
MINISTRY OF AGRICULTURE
International Development Association
MINISTRY OF AGRICULTUREMADAGASCAR
Irrigation and Watershed Management Project
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Ziva Razafintsalama
zrazafintsalama@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Other Public AdministrationCropsAgricultural markets, commercialization and agri-businessOther Agriculture, Fishing and ForestryIrrigation and DrainageWater Institutions, Policies and ReformAgriculture FinanceLandscape ManagementBiodiversityLand Administration and ManagementRural Infrastructure and service deliveryRural MarketsWater Resource ManagementFinance for DevelopmentRenewable Natural Resources Asset ManagementRural Development
International Development Association30000000Total Commitment in Fourth Quarter of 2006
International Development Association1250000Total Disbursement in Third Quarter of 2007
International Development Association-50370Total Interest Repayment in Fourth Quarter of 2007
International Development Association333578Total Disbursement in First Quarter of 2008
International Development Association1268698Total Disbursement in First Quarter of 2008
International Development Association889274Total Disbursement in Second Quarter of 2008
International Development Association-27208Total Interest Repayment in Second Quarter of 2008
International Development Association477646Total Disbursement in Third Quarter of 2008
International Development Association717541Total Disbursement in Third Quarter of 2008
International Development Association387916Total Disbursement in Fourth Quarter of 2008
International Development Association-28119Total Interest Repayment in Fourth Quarter of 2008
International Development Association800299Total Disbursement in First Quarter of 2009
International Development Association-20381Total Interest Repayment in Second Quarter of 2009
International Development Association-23292Total Interest Repayment in Fourth Quarter of 2009
International Development Association1616707Total Disbursement in Second Quarter of 2010
International Development Association-22596Total Interest Repayment in Second Quarter of 2010
International Development Association829850Total Disbursement in Third Quarter of 2010
International Development Association155583Total Disbursement in Fourth Quarter of 2010
International Development Association-26605Total Interest Repayment in Fourth Quarter of 2010
International Development Association229762Total Disbursement in First Quarter of 2011
International Development Association484924Total Disbursement in First Quarter of 2011
International Development Association497327Total Disbursement in Second Quarter of 2011
International Development Association710000Total Disbursement in Second Quarter of 2011
International Development Association-36001Total Interest Repayment in Second Quarter of 2011
International Development Association734191Total Disbursement in Third Quarter of 2011
International Development Association814346Total Disbursement in Fourth Quarter of 2011
International Development Association955046Total Disbursement in Fourth Quarter of 2011
International Development Association-43507Total Interest Repayment in Fourth Quarter of 2011
International Development Association309964Total Disbursement in First Quarter of 2012
International Development Association1257870Total Disbursement in First Quarter of 2012
International Development Association1341959Total Disbursement in Second Quarter of 2012
International Development Association-50758Total Interest Repayment in Second Quarter of 2012
International Development Association350054Total Disbursement in Third Quarter of 2012
International Development Association1374938Total Disbursement in Third Quarter of 2012
International Development Association278611Total Disbursement in Fourth Quarter of 2012
International Development Association533335Total Disbursement in Fourth Quarter of 2012
International Development Association1044792Total Disbursement in Fourth Quarter of 2012
International Development Association-61903Total Interest Repayment in Fourth Quarter of 2012
International Development Association416813Total Disbursement in First Quarter of 2013
International Development Association349786Total Disbursement in Second Quarter of 2013
International Development Association-71692Total Interest Repayment in Second Quarter of 2013
International Development Association215366Total Disbursement in Third Quarter of 2013
International Development Association350233Total Disbursement in Third Quarter of 2013
International Development Association925938Total Disbursement in Third Quarter of 2013
International Development Association392442Total Disbursement in Fourth Quarter of 2013
International Development Association671356Total Disbursement in Fourth Quarter of 2013
International Development Association-77252Total Interest Repayment in Fourth Quarter of 2013
International Development Association296160Total Disbursement in First Quarter of 2014
International Development Association324205Total Disbursement in First Quarter of 2014
International Development Association898563Total Disbursement in First Quarter of 2014
International Development Association413232Total Disbursement in Second Quarter of 2014
International Development Association563645Total Disbursement in Second Quarter of 2014
International Development Association1168611Total Disbursement in Second Quarter of 2014
International Development Association-88806Total Interest Repayment in Second Quarter of 2014
International Development Association123376Total Disbursement in Third Quarter of 2014
International Development Association631231Total Disbursement in Third Quarter of 2014
International Development Association1262948Total Disbursement in Third Quarter of 2014
International Development Association72236Total Disbursement in Fourth Quarter of 2014
International Development Association80000Total Disbursement in Fourth Quarter of 2014
International Development Association-99277Total Interest Repayment in Fourth Quarter of 2014
International Development Association221762Total Disbursement in First Quarter of 2015
International Development Association1098319Total Disbursement in First Quarter of 2015
International Development Association-827986Total Commitment Cancellations in Second Quarter of 2015
International Development Association13228Total Disbursement in Second Quarter of 2015
International Development Association-100395Total Interest Repayment in Second Quarter of 2015
International Development Association-102729Total Interest Repayment in Fourth Quarter of 2015
International Development Association-101644Total Interest Repayment in Second Quarter of 2016
International Development Association-104093Total Interest Repayment in Fourth Quarter of 2016
International Development Association-95062Total Interest Repayment in Second Quarter of 2017
International Development Association-268557Total Loan Repayment in Second Quarter of 2017
International Development Association-108658Total Interest Repayment in Fourth Quarter of 2017
International Development Association-274942Total Loan Repayment in Fourth Quarter of 2017
International Development Association-102894Total Interest Repayment in Second Quarter of 2018
International Development Association-280418Total Loan Repayment in Second Quarter of 2018
International Development Association-98907Total Interest Repayment in Fourth Quarter of 2018
International Development Association-271840Total Loan Repayment in Fourth Quarter of 2018
International Development Association-97826Total Interest Repayment in Second Quarter of 2019
International Development Association-271745Total Loan Repayment in Second Quarter of 2019Project Information DocumentProject Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportFinancing AgreementContract AwardsProject URLProcurement Notices
Marovoay
-16.1110 46.6440
Mahajanga
-15.7170 46.3170
Farihy Itasy
-19.0670 46.7830
Tahiry Nanaharin' Ankarafantsika
-16.1500 47.0330
Andapa
-14.6500 49.6500
Farihy Alaotra
-17.5000 48.5000
Marojejy National Park
-12.5000 49.1660
GEO Indicator
Area under sustainable land management in the targeted project intervention areas (ha)
Intermediate Results Indicator
O&M cost coverage by collected fees in irrigation schemes (%)
Intermediate Results Indicator
Famers adopting new production technologies (number)
Intermediate Results Indicator
Water users provided with irrigation and drainage services (number)
Intermediate Results Indicator
Operational water user associations (number)
Intermediate Results Indicator
Beneficiaries adopting SLM (number)
Intermediate Results Indicator
Anti-erosion measures implemented (number)
Intermediate Results Indicator
Guichet fonciers operational (number)
Intermediate Results Indicator
Sub-projects financed and executed (number)
Intermediate Results Indicator
Agro-ecological
Intermediate Results Indicator
Intensification
PDO Indicator
Female beneficiaries
PDO Indicator
Area cultivated with improved technologies and/ or inputs provided through the sub-projects (ha)
PDO Indicator
Direct project beneficiaries
PDO Indicator
Area provided with irrigation and drainage services (ha)
181250.00
181250.00
181250.00
181250.00
181250.00
181250.00
181250.00
181250.00
361666.67
361666.67
361666.67
361666.67
361666.67
361666.67
361666.67
361666.67
361666.67
361666.67
361666.67
361666.63
579166.67
579166.67
579166.67
579166.67
579166.67
579166.67
579166.67
579166.67
579166.67
579166.67
579166.67
579166.63
880000.00
880000.00
880000.00
880000.00
880000.00
880000.00
880000.00
880000.00
880000.00
880000.00
880000.00
880000.00
558333.33
558333.33
558333.33
558333.33
558333.33
558333.33
558333.33
558333.33
558333.33
558333.33
558333.33
558333.37
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
181250.00
181250.00
181250.00
181250.00
181250.00
181250.00
181250.00
181250.00
361666.67
361666.67
361666.67
361666.67
361666.67
361666.67
361666.67
361666.67
361666.67
361666.67
361666.67
361666.63
579166.67
579166.67
579166.67
579166.67
579166.67
579166.67
579166.67
579166.67
579166.67
579166.67
579166.67
579166.63
880000.00
880000.00
880000.00
880000.00
880000.00
880000.00
880000.00
880000.00
880000.00
880000.00
880000.00
880000.00
558333.33
558333.33
558333.33
558333.33
558333.33
558333.33
558333.33
558333.33
558333.33
558333.33
558333.33
558333.37
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Finance Agreement :Schedule 2,10(a) | Description :ensure that the project is implemented in accordance with the provisions of theRAPs/RPF and RESA and the Pest and Pesticides Mgmt Plan incl. associated training, technical assistance, annual reviews | Due Date:28-Feb-2011
Finance Agreement :Schedule 2,10(b) | Description :ensure that DGDR recruits international technical assistance specialists for thepreparation of the Watershed Master Plans in each of the Project Areas | Due Date :22-Feb-2007
Finance Agreement :Schedule 2,10(c) | Description :ensure that within 90 days after effective date, a MOU, 1 per project area, beentered into by MAEP through NIWMP and MINENVEF through the 3rd Env. Support Program | Due Date :31-Jul-2007
Finance Agreement :Shedule 2,10(d) | Description :adopt, by December 31, 2006, and thereafter implement a national strategy onfertilizers | Due Date :31-Dec-2006
Finance Agreement :Schedule 2,10(e) | Description :issue, by December 31, 2007, and thereafter implement legislative guidelines forthe application of the new seeds legislation | Due Date :30-Jun-2013
Finance Agreement :Schedule 2,10(f) | Description :a baseline survey for the Project be completed by December 31, 2006 | Due Date:31-Dec-2006
Finance Agreement :Schedule 2,10(g) | Description :the watershed Master Plans, one per Project Area, be completed by September 30,2007 | Due Date :31-Jul-2008
Finance Agreement :Schedule 2,10(h) | Description :operational modalities of management and replenishment of FERHA be defined bySeptember 30, 2007 | Due Date :16-Jun-2014
Finance Agreement :Shedule 2,10(i) | Description :the irrigation related legal framework, including but not limited to Law 90-016and subsequent implementation texts be harmonized with the provisions of the Program | Due Date :13-Jun-2014
44000-P151469
World Bank
International Development Association
MINISTRY OF AGRICULTURE
International Development Association
MINISTRY OF AGRICULTUREMADAGASCAR
Madagascar Agriculture Rural Growth and Land Management Project
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Giuseppe Fantozzi
gfantozzi@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Agricultural markets, commercialization and agri-businessPublic Administration - Industry, Trade and ServicesPublic Administration - Agriculture, Fishing & ForestryRural and Inter-Urban RoadsJobsFinance for DevelopmentAgriculture FinanceLand Administration and ManagementMitigationAdaptationRural Infrastructure and service deliveryRural MarketsRural DevelopmentClimate change
International Development Association53000000Total Commitment in First Quarter of 2016
International Development Association691236Total Disbursement in Third Quarter of 2016
International Development Association3100000Total Disbursement in Fourth Quarter of 2016
International Development Association176429Total Disbursement in Second Quarter of 2017
International Development Association1881232Total Disbursement in Second Quarter of 2017
International Development Association-10035Total Interest Repayment in Second Quarter of 2017
International Development Association243866Total Disbursement in Third Quarter of 2017
International Development Association5079088Total Disbursement in Third Quarter of 2017
International Development Association178217Total Disbursement in Fourth Quarter of 2017
International Development Association201334Total Disbursement in Fourth Quarter of 2017
International Development Association295465Total Disbursement in Fourth Quarter of 2017
International Development Association-21730Total Interest Repayment in Fourth Quarter of 2017
International Development Association28632Total Disbursement in First Quarter of 2018
International Development Association176331Total Disbursement in First Quarter of 2018
International Development Association202196Total Disbursement in First Quarter of 2018
International Development Association43479Total Disbursement in Second Quarter of 2018
International Development Association275455Total Disbursement in Second Quarter of 2018
International Development Association300916Total Disbursement in Second Quarter of 2018
International Development Association-51320Total Interest Repayment in Second Quarter of 2018
International Development Association922314Total Disbursement in Third Quarter of 2018
International Development Association1234747Total Disbursement in Third Quarter of 2018
International Development Association5792753Total Disbursement in Third Quarter of 2018
International Development Association107063Total Disbursement in Fourth Quarter of 2018
International Development Association1824180Total Disbursement in Fourth Quarter of 2018
International Development Association-50769Total Interest Repayment in Fourth Quarter of 2018
International Development Association132941Total Disbursement in First Quarter of 2019
International Development Association246965Total Disbursement in First Quarter of 2019
International Development Association691598Total Disbursement in First Quarter of 2019
International Development Association52000000Total Commitment in First Quarter of 2019
International Development Association970667Total Disbursement in Second Quarter of 2019
International Development Association1500000Total Disbursement in Second Quarter of 2019
International Development Association-88926Total Interest Repayment in Second Quarter of 2019
International Development Association569870Total Disbursement in Third Quarter of 2019
International Development Association699044Total Disbursement in Third Quarter of 2019Project Information DocumentProject Information DocumentProject Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementFinancing AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Toamasina
-18.1490 49.4020
Vondrozo
-22.8170 47.2830
Vohibe
-25.5330 45.4830
Vohemary
-21.3670 44.8330
Vatomandry
-19.3300 48.9780
Fort Dauphin
-25.0320 46.9830
Soanierana Ivongo
-16.9170 49.5830
Soanierana Ivongo
-16.9170 49.5830
Soalala
-16.1000 45.3170
Sambava
-14.2670 50.1670
Nosy Varika
-20.5830 48.5330
Morombe
-21.7450 43.3610
Morafenobe
-17.8170 44.9170
Mitsinjo
-23.5170 44.0000
Midongy Atsimo
-23.5900 47.0150
Mananjary
-21.2300 48.3420
Mampikony
-16.1000 47.6330
Mahanoro
-24.9830 46.7500
Kandreho
-17.4830 46.1000
Ivohibe
-23.5330 44.4000
Ihosy
-22.4030 46.1260
Fenoarivo Atsinanana
-17.3810 49.4080
Benenitra
-23.4500 45.0830
Belo sur Tsiribihina
-19.6980 44.5460
Antsirabe
-19.8660 47.0330
Antanambao-Manampotsy
-19.4830 48.5670
Antalaha
-14.9000 50.2790
Analalava
-14.6330 47.7500
Ambilobe
-13.2000 49.0500
Ambanja
-17.3000 44.4670
Ambanja
-13.6830 48.4500
Analanjirofo Region
-16.5000 49.5000
Vakinankaratra Region
-19.7000 46.9000
Itasy Region
-18.9500 46.9500
Analamanga Region
-18.4500 47.5000
Atsinanana Region
-19.0000 48.9000
Ambatondrazaka District
-17.8910 48.4440
Amparafaravola District
-17.3790 48.3640
Brickaville
-18.8200 49.0640
Moramanga District
-18.8020 48.2600
Antsohihy
-14.9630 48.0870
Befandriana Avaratra District
-15.1450 48.7800
Mandritsara
-15.9880 48.7160
Antananarivo-Renivohitra District
-18.9600 47.5660
Toamasina I
-18.0650 49.3750
Toamasina II
-17.9410 49.1460
Andapa District
-14.6500 49.6500
Marovoay District
-16.1500 46.6170
Vavatenina District
-17.5170 48.9500
Maroantsetra District
-15.3840 49.5650
Mananara Nord District
-16.2160 49.5480
Betroka District
-23.3570 45.9370
Farafangana District
-22.8020 47.5980
Iakora
-23.1000 46.6500
Ifanadiana
-21.3000 47.6330
Mandoto
-19.5670 46.2830
Marolambo
-23.2170 47.7170
Vohipeno
-17.1670 49.3000
Vangaindrano District
-23.4930 47.4500
Amboasary District
-24.6720 46.3840
Bealanana District
-14.5730 48.7710
Betafo District
-19.7540 46.5020
Miandrivazo District
-19.1790 45.3870
Toliara II District
-23.0360 43.8150
Toliara I District
-23.2900 43.7010
Andilamena District
-16.9510 48.5470
Ambato Boeny
-16.4670 46.7170
Antsalova
-16.6500 45.0670
Befotaka
-18.2500 44.1330
Besalampy
-22.4500 44.3330
Ambatofinandrahana District
-20.4570 46.7870
Morondava District
-20.5270 44.3680
Mahabo District
-20.6360 45.1650
Manja District
-21.4360 44.1820
Beroroha District
-21.5140 45.2340
Ankazobe District
-18.3170 47.1160
Sakaraha District
-22.9180 44.5300
Ampanihy District
-24.6960 44.7460
Betioky District
-23.7220 44.3800
Ambovombe District
-25.1770 46.0870
Beloha District
-25.1740 45.0600
Bekily District
-24.1830 45.3830
Tsihombe
-25.3850 45.4790
Taolagnaro
-24.5800 47.0780
Anjozorobe
-18.1370 47.7120
Tsiroanomandidy
-18.8400 46.0450
Fenoarivobe
-18.1290 46.3330
Ambalavao
-21.9200 46.6800
Ikalamavony
-21.2270 46.2100
Ikongo
-21.9520 47.4680
Manakara
-21.9340 47.8500
Mahajanga II
-15.6790 46.8110
Mahajanga I
-15.5970 46.4350
Maevatanana
-17.2280 46.8130
Tsaratanana
-17.1430 47.6470
Maintirano
-17.8800 44.2290
Ambatomainty
-17.7450 45.5710
Nosy Boraha
-16.9020 49.8980
Nosy Be
-13.3420 48.2580
Intermediate Results Indicator
Communal land offices that have land certification capacity operational
Intermediate Results Indicator
Client days of training provided (number)
Intermediate Results Indicator
Land tenure deals with the private sector following the principles for responsible agriculture investments.
Intermediate Results Indicator
Targeted farming households reporting larger volumes of agricultural products brought by buyers
Intermediate Results Indicator
Targeted farming households reporting hiring additional paid non-family labour
Intermediate Results Indicator
Roads constructed or rehabilitated
PDO Indicator
Horticulture value chains (green beans, onions, potatoes)
PDO Indicator
Cereals for and animal feed
PDO Indicator
Spices (cloves, vanilla, pepper)
PDO Indicator
Direct project beneficiaries
PDO Indicator
Land parcels with use or ownership rights recorded as a result of the project
PDO Indicator
Targeted farmers with improved perception of land tenure rights being recognized by a public authority (civic engagement indicator, gender indicator) (disaggregated by gender)
PDO Indicator
Targeted farmers with improved perception of land tenure rights being recognized of which female
PDO Indicator
Female beneficiaries
PDO Indicator
Targeted farmers with perception of improved access to markets (disaggregated by value chain)
PDO Indicator
Targeted farmers with perception of improved access to markets (disaggregated by value chain) of which female
0.00
0.00
0.00
0.00
937500.00
937500.00
937500.00
937500.00
937500.00
937500.00
937500.00
937500.00
937500.00
937500.00
937500.00
937500.00
1183333.33
1183333.33
1183333.33
1183333.33
1183333.33
1183333.33
1183333.33
1183333.33
1183333.33
1183333.33
1183333.33
1183333.37
1441666.67
1441666.67
1441666.67
1441666.67
1441666.67
1441666.67
1441666.67
1441666.67
1441666.67
1441666.67
1441666.67
1441666.63
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
354166.67
354166.67
354166.67
354166.67
354166.67
354166.67
354166.67
354166.67
354166.67
354166.67
354166.67
354166.63
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
44940.00
157038.00
195048.00
232344.00
129486.00
284298.00
319914.00
176778.00
385980.00
420168.00
219492.00
455532.00
483126.00
251622.00
517482.00
532854.00
271950.00
557214.00
579348.00
608202.00
317100.00
656292.00
684684.00
352002.00
720384.00
751758.00
389172.00
795354.00
804930.00
403200.00
822276.00
838278.00
837522.00
416682.00
838572.00
844914.00
424452.00
851088.00
851886.00
427770.00
859950.00
865872.00
434196.00
871710.00
876456.00
439278.00
878262.00
878346.00
884352.00
443142.00
885570.00
884688.00
445032.00
894264.00
894726.00
445746.00
887544.00
879858.00
439194.00
879522.00
883764.00
887250.00
444444.00
890190.00
892248.00
447048.00
896154.00
898506.00
389214.00
552342.00
Finance Agreement: Procurement Complaint Handling Mechanism | Description: The Recipient shall have established a procurementcomplaint handling mechanism acceptable to the Association no later than three (3) months after the Project Effectiveness Date. |Due Date: 30-Sep-2016
Finance Agreement: Regional Implementation Units (RIUs) | Description: The Recipient shall establish and maintain two RegionalImplementation Units (RIUs) within the PIU, located in Antsirabe and Toamasina, with mandate, composition and resources acceptableto the Association, no later than three months after the Project Effectiveness Date. | Due Date: 30-Sep-2016
Finance Agreement: External Audit | Description: The Recipient shall recruit an external auditor for the Project no later than six(6) months after the Project Effectiveness Date. | Due Date: 30-Dec-2016
Finance Agreement: National Land Program | Description: The Recipient shall have adopted in a manner satisfactory to theAssociation, the National Land Program no later than three (3) months after the Project Effectiveness Date. | Due Date: 30-Sep-2016
Finance Agreement: PPCG Fund | Description: No later than six (6) months before the Closing Date, the Recipient shall, inconjunction with the Association and the Fund Manager, carry out a pre-closing review of the Project, covering the progressachieved in the performance of the PPCG Fund and the Fund Manager. | Due Date: 29-Jan-2021
Finance Agreement: Annual Work Plan and Budget for the first year of Project implementation | Description: The Recipient shallfurnish to the Association the annual work plan and budget for the Project for the first year of Project implementation, and theevidence which may be required for the implementation of the activities included in the draft annual work plan and budget for suchperiod which shall be furnished no later than one (1) month after the Effectiveness Date. | Due Date: 30-Jul-2016
44000-P090615
World Bank
International Development Association
PPMS
International Development Association
PPMSMADAGASCAR
Second Multisectoral STI/HIV/AIDS Prevention project
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Jumana N. Qamruddin
jqamruddin@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
HealthSocial ProtectionSocial InclusionReproductive and Maternal HealthHIV/AIDSParticipation and Civic EngagementSocial Safety NetsHealth Systems and PoliciesSocial ProtectionGenderDisease Control
International Development Association30000000Total Commitment in Third Quarter of 2005
International Development Association-66610Total Interest Repayment in Second Quarter of 2006
International Development Association2250000Total Disbursement in Fourth Quarter of 2006
International Development Association-45850Total Interest Repayment in Fourth Quarter of 2006
International Development Association-38336Total Interest Repayment in Second Quarter of 2007
International Development Association664711Total Disbursement in Fourth Quarter of 2007
International Development Association891108Total Disbursement in Fourth Quarter of 2007
International Development Association891402Total Disbursement in Fourth Quarter of 2007
International Development Association-37804Total Interest Repayment in Fourth Quarter of 2007
International Development Association271830Total Disbursement in First Quarter of 2008
International Development Association296573Total Disbursement in First Quarter of 2008
International Development Association633232Total Disbursement in First Quarter of 2008
International Development Association549508Total Disbursement in Second Quarter of 2008
International Development Association872796Total Disbursement in Second Quarter of 2008
International Development Association1738536Total Disbursement in Second Quarter of 2008
International Development Association-38562Total Interest Repayment in Second Quarter of 2008
International Development Association597980Total Disbursement in Third Quarter of 2008
International Development Association795266Total Disbursement in Third Quarter of 2008
International Development Association1461662Total Disbursement in Third Quarter of 2008
International Development Association788215Total Disbursement in Fourth Quarter of 2008
International Development Association1256333Total Disbursement in Fourth Quarter of 2008
International Development Association-49185Total Interest Repayment in Fourth Quarter of 2008
International Development Association320426Total Disbursement in First Quarter of 2009
International Development Association434386Total Disbursement in First Quarter of 2009
International Development Association683145Total Disbursement in First Quarter of 2009
International Development Association-53950Total Interest Repayment in Second Quarter of 2009
International Development Association657306Total Disbursement in Fourth Quarter of 2009
International Development Association1149781Total Disbursement in Fourth Quarter of 2009
International Development Association-60451Total Interest Repayment in Fourth Quarter of 2009
International Development Association465251Total Disbursement in First Quarter of 2010
International Development Association-61374Total Interest Repayment in Second Quarter of 2010
International Development Association280995Total Disbursement in Third Quarter of 2010
International Development Association833730Total Disbursement in Third Quarter of 2010
International Development Association916176Total Disbursement in Third Quarter of 2010
International Development Association897435Total Disbursement in Fourth Quarter of 2010
International Development Association1262391Total Disbursement in Fourth Quarter of 2010
International Development Association-72329Total Interest Repayment in Fourth Quarter of 2010
International Development Association156082Total Disbursement in First Quarter of 2011
International Development Association690828Total Disbursement in First Quarter of 2011
International Development Association1024874Total Disbursement in First Quarter of 2011
International Development Association532430Total Disbursement in Second Quarter of 2011
International Development Association918964Total Disbursement in Second Quarter of 2011
International Development Association-89260Total Interest Repayment in Second Quarter of 2011
International Development Association-40076Total Disbursement in Third Quarter of 2011
International Development Association419015Total Disbursement in Third Quarter of 2011
International Development Association995621Total Disbursement in Third Quarter of 2011
International Development Association357325Total Disbursement in Fourth Quarter of 2011
International Development Association741840Total Disbursement in Fourth Quarter of 2011
International Development Association-97755Total Interest Repayment in Fourth Quarter of 2011
International Development Association-24556Total Disbursement in First Quarter of 2012
International Development Association193922Total Disbursement in First Quarter of 2012
International Development Association279020Total Disbursement in First Quarter of 2012
International Development Association-140570Total Disbursement in Second Quarter of 2012
International Development Association155911Total Disbursement in Second Quarter of 2012
International Development Association-101782Total Interest Repayment in Second Quarter of 2012
International Development Association6000000Total Commitment in Second Quarter of 2012
International Development Association120097Total Disbursement in Third Quarter of 2012
International Development Association126022Total Disbursement in Third Quarter of 2012
International Development Association331698Total Disbursement in Third Quarter of 2012
International Development Association192318Total Disbursement in Fourth Quarter of 2012
International Development Association485938Total Disbursement in Fourth Quarter of 2012
International Development Association-105499Total Interest Repayment in Fourth Quarter of 2012
International Development Association1179112Total Disbursement in First Quarter of 2013
International Development Association-906258Total Commitment Cancellations in Second Quarter of 2013
International Development Association-49674Total Disbursement in Second Quarter of 2013
International Development Association-109025Total Interest Repayment in Second Quarter of 2013
International Development Association198829Total Disbursement in Second Quarter of 2013
International Development Association439810Total Disbursement in Second Quarter of 2013
International Development Association600000Total Disbursement in Second Quarter of 2013
International Development Association-789Total Interest Repayment in Second Quarter of 2013
International Development Association439004Total Disbursement in Third Quarter of 2013
International Development Association1685133Total Disbursement in Third Quarter of 2013
International Development Association-113645Total Interest Repayment in Fourth Quarter of 2013
International Development Association381572Total Disbursement in Fourth Quarter of 2013
International Development Association-10561Total Interest Repayment in Fourth Quarter of 2013
International Development Association41127Total Disbursement in First Quarter of 2014
International Development Association193549Total Disbursement in First Quarter of 2014
International Development Association353378Total Disbursement in First Quarter of 2014
International Development Association-113712Total Interest Repayment in Second Quarter of 2014
International Development Association250998Total Disbursement in Second Quarter of 2014
International Development Association262024Total Disbursement in Second Quarter of 2014
International Development Association-15992Total Interest Repayment in Second Quarter of 2014
International Development Association-106486Total Interest Repayment in Fourth Quarter of 2014
International Development Association35017Total Disbursement in Fourth Quarter of 2014
International Development Association176765Total Disbursement in Fourth Quarter of 2014
International Development Association-17494Total Interest Repayment in Fourth Quarter of 2014
International Development Association-651193Total Commitment Cancellations in First Quarter of 2015
International Development Association-737Total Disbursement in First Quarter of 2015
International Development Association151219Total Disbursement in First Quarter of 2015
International Development Association-100863Total Interest Repayment in Second Quarter of 2015
International Development Association-17626Total Interest Repayment in Second Quarter of 2015
International Development Association-104088Total Interest Repayment in Fourth Quarter of 2015
International Development Association-270994Total Loan Repayment in Fourth Quarter of 2015
International Development Association-18264Total Interest Repayment in Fourth Quarter of 2015
International Development Association-102144Total Interest Repayment in Second Quarter of 2016
International Development Association-275552Total Loan Repayment in Second Quarter of 2016
International Development Association-18125Total Interest Repayment in Second Quarter of 2016
International Development Association-96687Total Interest Repayment in Fourth Quarter of 2016
International Development Association-262661Total Loan Repayment in Fourth Quarter of 2016
International Development Association-17292Total Interest Repayment in Fourth Quarter of 2016
International Development Association-92234Total Interest Repayment in Second Quarter of 2017
International Development Association-270848Total Loan Repayment in Second Quarter of 2017
International Development Association-17519Total Interest Repayment in Second Quarter of 2017
International Development Association-106203Total Interest Repayment in Fourth Quarter of 2017
International Development Association-276895Total Loan Repayment in Fourth Quarter of 2017
International Development Association-18546Total Interest Repayment in Fourth Quarter of 2017
International Development Association-98279Total Interest Repayment in Second Quarter of 2018
International Development Association-276073Total Loan Repayment in Second Quarter of 2018
International Development Association-18196Total Interest Repayment in Second Quarter of 2018
International Development Association-95266Total Interest Repayment in Fourth Quarter of 2018
International Development Association-270219Total Loan Repayment in Fourth Quarter of 2018
International Development Association-17782Total Interest Repayment in Fourth Quarter of 2018
International Development Association-94535Total Interest Repayment in Second Quarter of 2019
International Development Association-271069Total Loan Repayment in Second Quarter of 2019
International Development Association-17838Total Interest Repayment in Second Quarter of 2019Project Information DocumentProject Information DocumentProject Appraisal Document Implementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementContract AwardsProject URLProcurement Notices
Toamasina
-18.1490 49.4020
Toliara
-23.3500 43.6670
Mahajanga
-15.7170 46.3170
Fianarantsoa
-21.4530 47.0860
Antsiranana
-12.2790 49.2920
Antananarivo
-18.9140 47.5360
Intermediate Results Indicator
Number of children under five treated with Zinc/SRO for diarrhea in project areas
Intermediate Results Indicator
Number of children under five receiving Vitamin A supplementation in project areas
Intermediate Results Indicator
Number of health personnel trained in monitoring and evaluation
Intermediate Results Indicator
Number of Pregnant women attended their first antenatal visit before the end of the first quarter (<4 months) of pregnancy in project areas
Intermediate Results Indicator
Number of condoms distributed through the public sector and NGO programs per year in project areas
Intermediate Results Indicator
Number of syphilis treatments distributed in public health centers in project areas (number)
Intermediate Results Indicator
Number of STI treatment kits sold in public and private sectors (number)
Intermediate Results Indicator
Number of births attended by skilled personnel in project areas
Intermediate Results Indicator
Number of SW, Youth aged 15-24 (by gender) and Military tested for HIV in the last 12 months and received their test results in project areas
Intermediate Results Indicator
Monitoring committee meetings held within 2 weeks of submission of quarterly Independent verification Agency Report
Intermediate Results Indicator
Quaterly Independant Verification Agency Reports submitted within 45 days of the end of the quarter
Intermediate Results Indicator
Health personnel receiving training (number)
Intermediate Results Indicator
Number of national surveys and studies undertaken in accordance with agreed timetable
Intermediate Results Indicator
Annual Operation Plan reflects recommendations of Consolidated Annual Report
Intermediate Results Indicator
Number of children under five enrolled in the growth monitoring and promotion program in project areas
Intermediate Results Indicator
Percentage of capacity-building plan implemented by year
Intermediate Results Indicator
Percentage of IFRs submitted by deadline
Intermediate Results Indicator
Percentage of PIU audits without reserves
Intermediate Results Indicator
Percentage of PLWHA reference centers having submitted monthly reports within 15 days of the end of the month
Intermediate Results Indicator
Number of pregnant women receiving iron folic acid in project areas
Intermediate Results Indicator
Annual Reporting allows identifying each donor contribution to the program in a coherent manner
Intermediate Results Indicator
Number and percentage of pregnant women test for syphilis during prenatal consultations
Intermediate Results Indicator
Number of condoms distributed and sold through the public sector and NGO programs per year
Intermediate Results Indicator
Number of women involved in growth monitoring and promotion activities in project areas
Intermediate Results Indicator
The National Strategic Plan for HIV/AIDS is revised and disseminated by the end of 2006
Intermediate Results Indicator
The national communication plan is updated according to recommendatins of midterm evaluation
Intermediate Results Indicator
ARV Treatment Guidelines are adequate and implemented
PDO Indicator
of which Female (HIV Interventions - direct project beneficiaries)
PDO Indicator
of which Female (Health and Nutrition Inteventions - Direct Project Beneficiairies)
PDO Indicator
Direct project beneficiaries
PDO Indicator
Percentage of targeted groups who can cite three methods of HIV/AIDS prevention IN PROJECT AREAS (%)
PDO Indicator
Female beneficiaries
PDO Indicator
Percentage of men and women aged 15-49 who report having sex with a non-regular partner in the last 12 months.
PDO Indicator
Percentage of SW reporting the use of a condom in their last act of sexual intercourse with a client.
PDO Indicator
Percentage of youth aged 15-24 that have received an HIV test in the last 12 months and who know their results (by age and by gender)
PDO Indicator
Percentage of target population reporting the use of a condom in their last act of sexual intercourse with a non-regular partner inthe last 12 months in project areas.
PDO Indicator
HIV Interventions - Direct Project Beneficiaries
PDO Indicator
Health and Nutrition Interventions - Direct Project Beneficiaries
PDO Indicator
Decrease in Syphilis prevalence among SW (%)
PDO Indicator
Percentage of targeted groups who can cite three methods of HIV/AIDS prevention
PDO Indicator
Percentage of SW that have received an HIV test in the last 12 months and who kow their results (by gender) (%)
PDO Indicator
Children immunized - under 5 years against Polio (number)
PDO Indicator
Pregnant Women tested positive and treated for syphilis during prenatal consultations in project areas (number)
PDO Indicator
Pregnant women receiving antenatal care during a visit to a health provider (number)
PDO Indicator
Children 0-24 months obtaining monthly adequate minimum weight in project areas (number)
PDO Indicator
Children immunized (number)
PDO Indicator
People with access to a basic package of health, nutrition, or reproductive health services (number)
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
738767.14
738767.14
738767.15
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
770865.58
770865.58
770865.59
372610.32
372610.32
372610.32
959053.43
959053.43
959053.41
898703.54
898703.54
898703.53
674005.81
674005.81
674005.83
478065.21
478065.21
478065.21
0.00
0.00
0.00
0.00
0.00
0.00
564515.14
564515.14
564515.15
150696.10
150696.10
150696.09
0.00
0.00
0.00
662536.93
662536.93
662536.93
682397.72
682397.72
682397.72
590843.53
590843.53
590843.54
451107.25
451107.25
451107.27
430357.59
430357.59
430357.60
349569.53
349569.53
349569.53
143013.64
143013.64
143013.62
5737.56
5737.56
5737.56
187620.80
187620.80
187620.80
217989.76
217989.76
217989.77
83333.33
83333.33
83333.35
83333.33
83333.33
83333.35
333333.33
333333.33
333333.34
333333.33
333333.33
333333.34
321335.93
321335.93
321335.94
234323.44
234323.44
234323.42
83333.33
83333.33
83333.35
83333.21
83333.21
83333.21
498536.14
498536.14
498536.14
498536.14
498536.14
498536.14
The Borrower shall update the Procurement Plan and furnish it to the Association not later than 12 months after the date of thepreceding plan for IDA's approval
furnish to IDA at least 6 mos. after end of FY: (A) certified copies of audits and b) the auditors'opinion
Borrower shall prepare and furnish to the Association a Financial Monitoring Report, in form and substance satisfactory to theAssociation
The first FMR shall be furnished to IDA within 45 days after the end of the first calendar quarter after the Effective Date and 45days after each subsequent calandar quarter
not later than September 30 of each year, beginning September 30, 2006, a proposed annual work program and budget for theforthcoming Fiscal Year.
six-monthly progress reports on the status of the Project, to be submitted not later than two months after the end of the relevantreporting period.
The Borrower shall, not later than December 31 of each year, undertake, in conjunction with the Association and other interestedparties, an annual review of the Project.
The Recipient shall take all measures necessary on its part to regularly collect, compile, and submit to the Association, on aquarterly basis, reports on the status of compliance with the Medical Waste Management Plan.
The Recipient shall prepare and furnish to the Association, not later than 45 days after the end of each calendar quarter, interimunaudited financial reports of the Project covering the quarter, in form and substance satisfactory to the Association.
Each Financial Statements shall cover the period of one Fiscal Year. The audited Financial Statements for each period shall befurnished to the Association not later than six months after the end of such period.
The Borrower shall update the Procurement Plan and furnish it to the Association not later than 12 months after the date of thepreceding plan for IDA's approval
The Recipient shall, not later than Sept. 30 of each year, submit to the IDA, for its review & approval, a proposed annual workprogram & budget for the forthcoming FY, except that, in the case of the period of time between the Effective Date and the end ofthe FY 2013, the proposed annual work program and budget shall be submitted to the Association not later than 30 days afterEffectiveness
The Recipient shall, not later than Dec. 31 of each year, undertake in conjonction with IDA an annual review of the projectfocusing on the project progress
Not later than one month prior to the annual review, the Recipient shall furnish to IDA, for its comments, a progress report
No later than 2 months after the Effective Date, the Recipient shall have recruited an independent agency with TORs,qualificationsand experience satisfactory to IDA for the purpose of independently collecting data & monitoring indicators for theProject
The Recipient shall comply with its obligations of repayment of ineligible expenditures incurred during the implementation of theoriginal project
The Recipient regularly collect, compile and submit to IDA, on a quarterly basis, reports on the status of compliance with theMedical Waste Management Plan
The Recipient shall monitor and evaluate the progress of the Project & prepare Project Reports covering the period of onesemester,and shall be furnished to IDA not later than 2 months after the end of the period covered by such report.
The Recipient shall prepare and furnish to IDA not later than 45 days after the end of each calendar quarter, interim unauditedfinancial reports for the Project covering the quarter.
44000-P095240
World Bank
International Development Association
JIRAMA, MINISTRY OF ENERGY AND MINES
International Development Association
JIRAMA, MINISTRY OF ENERGY AND MINESMADAGASCAR
Power Sector Improvement and Recovery
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Nataliya Kulichenko
nkulichenko@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Renewable Energy HydroCentral Government (Central Agencies)Other Energy and ExtractivesRural DevelopmentRural Infrastructure and service deliveryRegulation and Competition PolicyUrban Infrastructure and Service DeliveryJob CreationBusiness Enabling EnvironmentUrban DevelopmentJobs
International Development Association10000000Total Commitment in Third Quarter of 2006
International Development Association500000Total Disbursement in First Quarter of 2007
International Development Association927050Total Disbursement in Second Quarter of 2007
International Development Association45117Total Disbursement in Third Quarter of 2007
International Development Association133558Total Disbursement in Third Quarter of 2007
International Development Association-22610Total Interest Repayment in Third Quarter of 2007
International Development Association53299Total Disbursement in Fourth Quarter of 2007
International Development Association95525Total Disbursement in Fourth Quarter of 2007
International Development Association370849Total Disbursement in Fourth Quarter of 2007
International Development Association503162Total Disbursement in First Quarter of 2008
International Development Association623506Total Disbursement in First Quarter of 2008
International Development Association-11840Total Interest Repayment in First Quarter of 2008
International Development Association157588Total Disbursement in Second Quarter of 2008
International Development Association53113Total Disbursement in Third Quarter of 2008
International Development Association59741Total Disbursement in Third Quarter of 2008
International Development Association355780Total Disbursement in Third Quarter of 2008
International Development Association-16755Total Interest Repayment in Third Quarter of 2008
International Development Association6584Total Disbursement in Fourth Quarter of 2008
International Development Association45532Total Disbursement in Fourth Quarter of 2008
International Development Association58361Total Disbursement in First Quarter of 2009
International Development Association692630Total Disbursement in First Quarter of 2009
International Development Association-14279Total Interest Repayment in First Quarter of 2009
International Development Association145865Total Disbursement in Second Quarter of 2009
International Development Association-17912Total Interest Repayment in Third Quarter of 2009
International Development Association-17991Total Interest Repayment in First Quarter of 2010
International Development Association-17288Total Interest Repayment in Third Quarter of 2010
International Development Association126914Total Disbursement in Fourth Quarter of 2010
International Development Association211749Total Disbursement in First Quarter of 2011
International Development Association-18595Total Interest Repayment in First Quarter of 2011
International Development Association-20521Total Interest Repayment in Third Quarter of 2011
International Development Association-465000Total Disbursement in Fourth Quarter of 2011
International Development Association-17950Total Interest Repayment in First Quarter of 2012
International Development Association-17438Total Interest Repayment in Third Quarter of 2012
International Development Association127031Total Disbursement in First Quarter of 2013
International Development Association350000Total Disbursement in First Quarter of 2013
International Development Association500000Total Disbursement in First Quarter of 2013
International Development Association-17540Total Interest Repayment in First Quarter of 2013
International Development Association674449Total Disbursement in Second Quarter of 2013
International Development Association1352224Total Disbursement in Second Quarter of 2013
International Development Association-10393Total Disbursement in Third Quarter of 2013
International Development Association497481Total Disbursement in Third Quarter of 2013
International Development Association532877Total Disbursement in Third Quarter of 2013
International Development Association-24209Total Interest Repayment in Third Quarter of 2013
International Development Association-1675390Total Commitment Cancellations in Fourth Quarter of 2013
International Development Association31938Total Disbursement in Fourth Quarter of 2013
International Development Association-33937Total Interest Repayment in First Quarter of 2014
International Development Association-32698Total Interest Repayment in Third Quarter of 2014
International Development Association-30079Total Interest Repayment in First Quarter of 2015
International Development Association-30048Total Interest Repayment in Third Quarter of 2015
International Development Association-29607Total Interest Repayment in First Quarter of 2016
International Development Association-29851Total Interest Repayment in Third Quarter of 2016
International Development Association-79838Total Loan Repayment in Third Quarter of 2016
International Development Association-28331Total Interest Repayment in First Quarter of 2017
International Development Association-77099Total Loan Repayment in First Quarter of 2017
International Development Association-28101Total Interest Repayment in Third Quarter of 2017
International Development Association-81032Total Loan Repayment in Third Quarter of 2017
International Development Association-29994Total Interest Repayment in First Quarter of 2018
International Development Association-83093Total Loan Repayment in First Quarter of 2018
International Development Association-31005Total Interest Repayment in Third Quarter of 2018
International Development Association-79899Total Loan Repayment in Third Quarter of 2018
International Development Association-28237Total Interest Repayment in First Quarter of 2019
International Development Association-79559Total Loan Repayment in First Quarter of 2019Project Information DocumentProject Information DocumentProject Information DocumentProject Appraisal Document Implementation Completion and Results ReportImplementation Completion Report ReviewImplementation Status and Results ReportImplementation Status and Results ReportAgreementAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Intermediate Results Indicator
Number of Compact Fluorescent Lamps distributed
NA
The procurement of CFL is completed.
Intermediate Results Indicator
Number of prepayment meter installed
Intermediate Results Indicator
Adequate technical,commercial,and financial reporting in place
Intermediate Results Indicator
Scoping study of 6 potential sites and prefeasibility study of the selected hydro site completed
Scoping study completed
Phase 1 (scoping) completed
Intermediate Results Indicator
Analytical works and studies completed
ToRs under discussion
PDO Indicator
Generation from rehabilitated hydro under project (over 6 months of operation)
No impact before the completion of rehabilitation.
PDO Indicator
Direct project beneficiaries
PDO Indicator
Revenue management: revenue collected/energy billed
PDO Indicator
Financial outcomes: EBITDA margin
The value for the end target is: >0%
Full year data not yet available
PDO Indicator
for industrial clients
PDO Indicator
Reduction of electricity losses: energy billed/energy produced
PDO Indicator
for households
PDO Indicator
Female beneficiaries
666666.67
666666.67
666666.66
666666.67
666666.67
666666.66
416666.67
416666.67
416666.66
416666.67
416666.67
416666.66
416666.67
416666.67
416666.66
416666.67
416666.67
416666.66
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
83333.33
83333.33
83333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
166666.67
166666.67
166666.66
309016.78
309016.78
309016.77
59558.36
59558.36
59558.37
173224.39
173224.39
173224.39
375555.89
375555.89
375555.89
52529.29
52529.29
52529.29
156211.32
156211.32
156211.32
17371.94
17371.94
17371.95
250330.33
250330.33
250330.34
48621.60
48621.60
48621.59
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
42304.63
42304.63
42304.62
70583.10
70583.10
70583.10
0.00
0.00
0.00
0.00
0.00
0.00
-155000.00
-155000.00
-155000.00
0.00
0.00
0.00
0.00
0.00
0.00
700025.70
700025.70
700025.71
1066333.31
1066333.31
1066333.31
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
No later than November 30, 2006, the Recipient shall have adopted the Electricity tariff Indexation Formula
Recipient shall have publicly disclosed Elec Tariff Indexation Formula & adjusted elec tariffs in accord. w/said formula, & shallsubsequently adjust said tariffs in accord. w/said formula every 6 mos
Recipient shall have established terms and conditions to be used in the contracting of JIRAMA's private partner satisfactory totheAssociation and have launched the prequalification process
Recipient shall have launched the bidding process for the recruitment of a new private operator for the management of JIRAMA'soperations.
JIRAMA will prepare quarterly mgmt rpts satisfactory to IDA (incl. relevant tech, commercial, & financial data) & submit said rptto IDA no later than 60 days after end of each quarter
Accounts receivable not to exceed 3 months billings by October 1, 2007 and onwards
Recip. to define, in agree. w/IDA, no later than Sept 30 each yr during proj. implementation, amounts to be injected byBeneficiary, into JIRAMA during following calendar yr so as to allow normal OPs
No disbursement under Category 1 (a) unless the Recipient has submitted a report satisfactory to IDA on the condition of theVatomandry dam and the proposed safety measures to be implemented
No disbursement under category 1 (c) unless Recipient has recruited a technical advisor w/qualifications and experiencesatisfactory to IDA
No later than April 1, 2013, the Recipient shall have publicly disclosed the Electricity tariff Indexation Formula and adjustedelectricity tariffs in accordance with said formula
44000-P164536
World Bank
International Development Association
International Development Association
MADAGASCAR
Madagascar Integrated Growth Poles and Corridor SOP-2
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Eneida Herrera Fernandes
efernandes1@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Agricultural markets, commercialization and agri-businessPublic Administration - Industry, Trade and ServicesTourismAdaptationUrban DevelopmentRural Infrastructure and service deliveryUrban Infrastructure and Service DeliveryRural Non-farm Income GenerationClimate changeMitigationRural MarketsMunicipal FinanceMSME DevelopmentRural DevelopmentInvestment and Business ClimateBusiness Enabling EnvironmentEnterprise Development
International Development Association70000000Total Commitment in Third Quarter of 2018
International Development Association621296Total Disbursement in Second Quarter of 2019
International Development Association4763870Total Disbursement in Third Quarter of 2019Project Appraisal Document Implementation Status and Results ReportAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Toliara
-23.3500 43.6670
Fort Dauphin
-25.0320 46.9830
Nosy Be
-13.3140 48.2590
Diana Region
-13.5000 49.0000
Anosy Region
-24.1000 46.3000
Atsimo-Andrefana Region
-23.2000 44.4000
Nosy Sainte Marie
-16.8330 49.9170
Intermediate Results Indicator
Number of formal businesses newly registered in the Target Regions
Intermediate Results Indicator
Increase in annual sales revenue for MBIF BPC recipient enterprises (MGA million)
Intermediate Results Indicator
Increase in revenues from target cash crop production for smallholders in the Target Regions (MGA billion)
Intermediate Results Indicator
Of which increase in annual sales revenue for women-owned enterprises (MGA million)
Intermediate Results Indicator
Hotel rooms available in the Target Regions
Intermediate Results Indicator
Annual municipal revenues collected in the supported municipalities (MGA billion)
Intermediate Results Indicator
Of which urban
Intermediate Results Indicator
Of which rural
Intermediate Results Indicator
Percentage of registered complaints that have been addressed by the project
Intermediate Results Indicator
Increase in average daily tourist expenditures on products and services for overnight tourists
Intermediate Results Indicator
Percentage of municipal budgets executed for investment by targeted municipalities
Intermediate Results Indicator
Kilometers of rural roads rehabilitated
Intermediate Results Indicator
Kilometers of urban roads rehabilitated
Intermediate Results Indicator
Increase in the value of exports of the selected crops in the Target Regions (US$ million)
Intermediate Results Indicator
Of which cocoa
PDO Indicator
Number of formal jobs created in Target Regions
PDO Indicator
Of which in tourism
PDO Indicator
Of which in agribusiness
PDO Indicator
Value of private investment enabled by the projecty (in million)
0.00
0.00
76375.00
178685.00
209950.00
241150.00
131300.00
282165.00
309075.00
351000.00
189410.00
396955.00
410085.00
420875.00
435825.00
221260.00
444340.00
434980.00
427960.00
437320.00
226980.00
481260.00
500500.00
517920.00
553540.00
292370.00
603005.00
632255.00
676260.00
725010.00
370695.00
755105.00
794105.00
854100.00
446160.00
913575.00
961155.00
1028885.00
1102530.00
574535.00
1197235.00
1262625.00
1329705.00
695305.00
1441895.00
1500265.00
1544140.00
1599650.00
823680.00
1687335.00
1736280.00
1797770.00
1868750.00
952640.00
1928095.00
1952340.00
1974310.00
2014220.00
1019460.00
2056795.00
2091505.00
2130570.00
2164695.00
1094470.00
2213575.00
2246855.00
2280850.00
6786330.00
0.00
0.00
76375.00
178685.00
209950.00
241150.00
131300.00
282165.00
309075.00
351000.00
189410.00
396955.00
410085.00
420875.00
435825.00
221260.00
444340.00
434980.00
427960.00
437320.00
226980.00
481260.00
500500.00
517920.00
553540.00
292370.00
603005.00
632255.00
676260.00
725010.00
370695.00
755105.00
794105.00
854100.00
446160.00
913575.00
961155.00
1028885.00
1102530.00
574535.00
1197235.00
1262625.00
1329705.00
695305.00
1441895.00
1500265.00
1544140.00
1599650.00
823680.00
1687335.00
1736280.00
1797770.00
1868750.00
952640.00
1928095.00
1952340.00
1974310.00
2014220.00
1019460.00
2056795.00
2091505.00
2130570.00
2164695.00
1094470.00
2213575.00
2246855.00
2280850.00
6786330.00
Schedule 2, Section I, A, 4, (a). The Recipient shall, not later than, nine (9) months after the Effective Date establish an MBIFImplementation Unit which shall report to the PIU on overall MBIF fiduciary management.
Schedule 2, Section I, A, 2 (the one on PIU), (c), (ii). In each Target Region, the Recipient shall, not later than six (6) monthsafter the Effective Date recruit: (a) a coordinator; and (b) one (1) account assistant, all in accordance with the provisions ofSection III of Schedule 2 to this Agreement, and each on the basis of terms of reference, qualifications and experience acceptableto the Association, to be assigned one in each Target Region.
Schedule 2, Section I, A, 5 (a). The Recipient shall, not later than twelve (12) months after the Effective Date establish and,throughout Project implementation, maintain Regional MBIF Validation Committees which shall be responsible for ensuring thecoherence of the MBIF with the regional and national economic context and priorities.
Schedule 2, Section I, D, 2. The Recipient shall furnish to the Association, as soon as available, but in any case not later thanNovember 30 of each year, the annual work plans and budgets approved by the PSC and the evidences referred to in subparagraph 1(b)above, for the Association's review and approval; except for the annual work plan and budget for the Project for the first year ofProject implementation, and the evidence which may be required for the implementation of the activities included in the draftannual work plan and budget for such period which shall be furnished no later than one (1) month after the Effective Date. Only theactivities included in an annual work plan and budget expressly approved by the Association (each an “Annual Work Plan and Budget”)are eligible to a financing from the proceeds of the Financing.
44000-P149323
World Bank
International Development Association
FONDS D'INTERVENTION POUR LE DEVELOPPMENT (FID)
International Development Association
FONDS D'INTERVENTION POUR LE DEVELOPPMENT (FID)MADAGASCAR
Social Safety Net Project
Planned start date of the activity
Actual start date of the activity
Planned end date of the activity
The World Bank
Laura B. Rawlings
lrawlings@worldbank.org+1-202-473-1000
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Social ProtectionPublic Administration - Social ProtectionDisaster Risk FinanceDisaster PreparednessDisaster Response and RecoverySocial Safety NetsSocial ProtectionDisaster Risk ReductionFinance for DevelopmentDisaster Risk ManagementJobs
International Development Association40000000Total Commitment in Third Quarter of 2015
International Development Association2309464Total Disbursement in First Quarter of 2016
International Development Association1736820Total Disbursement in Second Quarter of 2016
International Development Association4001817Total Disbursement in Third Quarter of 2016
International Development Association-8662Total Interest Repayment in Third Quarter of 2016
International Development Association6199267Total Disbursement in Fourth Quarter of 2016
International Development Association35000000Total Commitment in Fourth Quarter of 2016
International Development Association-41413Total Interest Repayment in First Quarter of 2017
International Development Association1210816Total Disbursement in First Quarter of 2017
International Development Association6826083Total Disbursement in First Quarter of 2017
International Development Association51721Total Disbursement in Second Quarter of 2017
International Development Association495287Total Disbursement in Second Quarter of 2017
International Development Association3584162Total Disbursement in Second Quarter of 2017
International Development Association140513Total Disbursement in Third Quarter of 2017
International Development Association2173984Total Disbursement in Third Quarter of 2017
International Development Association-53790Total Interest Repayment in Third Quarter of 2017
International Development Association133789Total Disbursement in Third Quarter of 2017
International Development Association464623Total Disbursement in Third Quarter of 2017
International Development Association3249319Total Disbursement in Third Quarter of 2017
International Development Association2553324Total Disbursement in Fourth Quarter of 2017
International Development Association393111Total Disbursement in Fourth Quarter of 2017
International Development Association613151Total Disbursement in Fourth Quarter of 2017
International Development Association1855990Total Disbursement in Fourth Quarter of 2017
International Development Association164626Total Disbursement in First Quarter of 2018
International Development Association4158682Total Disbursement in First Quarter of 2018
International Development Association4202172Total Disbursement in First Quarter of 2018
International Development Association-68568Total Interest Repayment in First Quarter of 2018
International Development Association187925Total Disbursement in First Quarter of 2018
International Development Association2597909Total Disbursement in First Quarter of 2018
International Development Association86276Total Disbursement in Second Quarter of 2018
International Development Association304089Total Disbursement in Second Quarter of 2018
International Development Association896220Total Disbursement in Second Quarter of 2018
International Development Association3234767Total Disbursement in Third Quarter of 2018
International Development Association-106416Total Interest Repayment in Third Quarter of 2018
International Development Association380572Total Disbursement in Third Quarter of 2018
International Development Association470957Total Disbursement in Third Quarter of 2018
International Development Association3019777Total Disbursement in Third Quarter of 2018
International Development Association-10756Total Disbursement in Fourth Quarter of 2018
International Development Association396624Total Disbursement in Fourth Quarter of 2018
International Development Association117006Total Disbursement in Fourth Quarter of 2018
International Development Association148944Total Disbursement in Fourth Quarter of 2018
International Development Association165353Total Disbursement in Fourth Quarter of 2018
International Development Association2133130Total Disbursement in First Quarter of 2019
International Development Association5865012Total Disbursement in First Quarter of 2019
International Development Association-113843Total Interest Repayment in First Quarter of 2019
International Development Association2858330Total Disbursement in First Quarter of 2019
International Development Association90000000Total Commitment in First Quarter of 2019
International Development Association103217Total Disbursement in Second Quarter of 2019
International Development Association575093Total Disbursement in Second Quarter of 2019
International Development Association218719Total Disbursement in Second Quarter of 2019
International Development Association387839Total Disbursement in Second Quarter of 2019
International Development Association1600638Total Disbursement in Second Quarter of 2019
International Development Association-143985Total Interest Repayment in Third Quarter of 2019
International Development Association9857Total Disbursement in Third Quarter of 2019
International Development Association578490Total Disbursement in Third Quarter of 2019Project Information DocumentProject Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportImplementation Status and Results ReportAgreementAgreementFinancing AgreementFinancing AgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Republic of Madagascar
-20.0000 47.0000
Intermediate Results Indicator
Children 0 to 59 months monitored at the community nutrition sites
Intermediate Results Indicator
Beneficiaries of Safety Nets programs (number)
Intermediate Results Indicator
Number of employment days created under the PSN and disaster response Cash for Work activities
Intermediate Results Indicator
Number of Agreements with government, non-government and development partners signed by the MPSPPW to harmonize the social sector related programs and activities in the South of Madagascar
Intermediate Results Indicator
Regional Social Protection committees established in Anosy and Androy (South) and functioning through regular meetings.
Intermediate Results Indicator
Beneficiaries of Safety Nets programs - Conditional cash transfers (number)
Intermediate Results Indicator
Beneficiaries of Safety Nets programs - Female (number)
Intermediate Results Indicator
Beneficiaries of Safety Nets programs - Cash-for-work, food-for-work and public works (number)
Intermediate Results Indicator
Number of landscape development plans developed in a participatory way
Intermediate Results Indicator
Percentage of safety net beneficiaries in the South using the livelihood grant for productive activities
Intermediate Results Indicator
Percentage of registered complaints that have been addressed by FID
Intermediate Results Indicator
Operational costs of FID as a percentage of program implementation expenditures
Intermediate Results Indicator
Percentage of community assets maintained one year after their completion
Intermediate Results Indicator
Establishment of a social protection program monitoring system at the MPSPPW
Intermediate Results Indicator
Impact Evaluation carried out and results available publicly
Intermediate Results Indicator
Areas treated with soil and water conservation (SWC) measures
Intermediate Results Indicator
Area re/afforested through productive safety net activities
PDO Indicator
Integrated beneficiary registry established at MPSPWP
PDO Indicator
Direct project beneficiaries
PDO Indicator
Pregnant/lactating women, adolescent girls and/or children under age five-reached by basic nutrition services (number)
PDO Indicator
Children under age five treated for moderate or severe acute malnutrition (number)
PDO Indicator
Children under the age of 24 months benefiting from improved infant and young child feeding (IYCF) practices
PDO Indicator
Female beneficiaries
PDO Indicator
Percentage of beneficiaries of the safety net programs (HDCT, PSN) belonging to the 30% poorest population.
PDO Indicator
Percentage of primary school aged children of HDCT beneficiary families who attend school at least 80% of the time
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1433333.33
1433333.33
1433333.34
708333.33
708333.33
708333.34
708333.33
708333.33
708333.34
708333.33
708333.33
708333.34
708333.33
708333.33
708333.34
891666.66
891666.67
891666.67
891666.66
891666.67
891666.67
891666.66
891666.67
891666.67
891666.66
891666.67
891666.67
1041666.66
1041666.67
1041666.67
1041666.66
1041666.67
1041666.67
1041666.66
1041666.67
1041666.67
1041666.66
1041666.67
1041666.67
1333333.33
1333333.33
1333333.34
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
81450.00
394110.00
239940.00
564120.00
323370.00
726480.00
402390.00
889020.00
491400.00
1075050.00
1181250.00
623970.00
1310760.00
691470.00
1448910.00
752490.00
1555470.00
806580.00
1681200.00
871560.00
1799910.00
928260.00
1927440.00
1000530.00
2085390.00
1076850.00
2185290.00
1097010.00
2267820.00
1175310.00
2381400.00
1183860.00
2316870.00
2323980.00
1173690.00
2311470.00
1123020.00
2193120.00
1083330.00
2137410.00
1051830.00
2062980.00
1009980.00
1985850.00
974610.00
1918980.00
945540.00
1858500.00
914760.00
1793970.00
878580.00
1712700.00
832050.00
1628550.00
800280.00
1566810.00
1515870.00
738360.00
1445220.00
705960.00
1375200.00
667980.00
1298340.00
630360.00
1221570.00
593010.00
1163520.00
573300.00
1121940.00
546300.00
1064340.00
518760.00
1012050.00
493380.00
961020.00
467190.00
67410.00
Finance Agreement :Procurement Complaint Handling Mechanism | Description :No later than three (3) months after the Effective Date,FID and the MPSPPW shall each have established a procurement complaint handling mechanism acceptable to the Association. | Due Date:10-Mar-2016
Finance Agreement :Auditors | Description :The Recipient shall engage independent auditors for the purpose of timely carrying outof the audits not later than six (6) months after the Effective Date, in accordance with the provisions of Section III of Schedule2 of the Financing Agreement. | Due Date :30-Jun-2016
Finance Agreement :Schedule 2, section 1, B 1 (b) | Description :The Recipient and the Project Implementing Agency [FID] shall, notlater than 30 days after the Effective Date, amend the Subsidiary Agreement to include the amount of the Additional Financing aswell as the activities, which have been added to the Original Project.