44000-P154149
World Bank
Vanuatu Aviation Investment Project
International Development Association
AIRPORTS VANUATU LTD.
International Development Association
AIRPORTS VANUATU LTD.Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Dung Anh Hoang
+1-202-473-1000dhoang1@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
VANUATU
Tafea Province
-19.5000 169.5000
Luganville
-15.5200 167.1620
Port-Vila
-17.7340 168.3220
Public Administration - TransportationAviationDisaster PreparednessDisaster Risk ManagementDisaster Risk FinanceTradeTrade FacilitationFinance for DevelopmentPublic Private PartnershipsDisaster Risk ReductionDisaster Response and Recovery
2125000.00
2125000.00
2125000.00
2125000.00
2125000.00
2125000.00
2125000.00
2125000.00
2125000.00
2125000.00
2125000.00
2125000.00
1666666.66
1666666.67
1666666.67
1666666.66
1666666.67
1666666.67
1666666.66
1666666.67
1666666.67
1666666.66
1666666.67
1666666.67
916666.66
916666.67
916666.67
916666.66
916666.67
916666.67
916666.66
916666.67
916666.67
916666.66
916666.67
916666.67
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
250000.00
0.00
0.00
0.00
0.00
0.00
0.00
166791.67
166791.67
166791.66
89963.94
89963.94
89963.95
0.00
0.00
0.00
588739.00
588739.00
588738.99
0.00
0.00
0.00
563273.42
563273.42
563273.43
183651.77
183651.77
183651.76
1666666.67
1666666.67
1666666.66
2000000.00
2000000.00
2000000.00
2250000.00
2250000.00
2250000.00
2000000.00
2000000.00
2000000.00
2250000.00
2250000.00
2250000.00
2250000.00
2250000.00
2250000.00
2250000.00
2250000.00
2250000.00
2250000.00
2250000.00
2250000.00
2024246.87
2024246.87
2024246.87
2000000.00
2000000.00
2000000.00
2000000.00
2000000.00
2000000.00
59500000Total Commitment in Second Quarter of 2015
International Development Association
500375Total Disbursement in Third Quarter of 2015
International Development Association
269892Total Disbursement in Fourth Quarter of 2015
International Development Association
633883Total Disbursement in Second Quarter of 2016
International Development Association
1132334Total Disbursement in Second Quarter of 2016
International Development Association
-3563Total Interest Repayment in Second Quarter of 2016
International Development Association
705543Total Disbursement in Fourth Quarter of 2016
International Development Association
984277Total Disbursement in Fourth Quarter of 2016
International Development Association
-7993Total Interest Repayment in Fourth Quarter of 2016
International Development Association
550955Total Disbursement in First Quarter of 2017
International Development Association
9500000Total Commitment in First Quarter of 2017
International Development Association
4600000Total Commitment in First Quarter of 2017
International Development Association
246611Total Disbursement in Second Quarter of 2017
International Development Association
453988Total Disbursement in Second Quarter of 2017
International Development Association
-14364Total Interest Repayment in Second Quarter of 2017
International Development Association
115712Total Disbursement in Third Quarter of 2017
International Development Association
352746Total Disbursement in Third Quarter of 2017
International Development Association
11810000Total Disbursement in Third Quarter of 2017
International Development Association
475990Total Disbursement in Fourth Quarter of 2017
International Development Association
-44392Total Interest Repayment in Fourth Quarter of 2017
International Development Association
175393Total Disbursement in First Quarter of 2018
International Development Association
227659Total Disbursement in First Quarter of 2018
International Development Association
10068116Total Disbursement in First Quarter of 2018
International Development Association
211358Total Disbursement in Second Quarter of 2018
International Development Association
10747366Total Disbursement in Second Quarter of 2018
International Development Association
-89760Total Interest Repayment in Second Quarter of 2018
International Development Association
124177Total Disbursement in Third Quarter of 2018
International Development Association
1184458Total Disbursement in Third Quarter of 2018
International Development Association
300000Total Disbursement in Third Quarter of 2018
International Development Association
200000Total Disbursement in Third Quarter of 2018
International Development Association
110018Total Disbursement in Fourth Quarter of 2018
International Development Association
2139461Total Disbursement in Fourth Quarter of 2018
International Development Association
-138238Total Interest Repayment in Fourth Quarter of 2018
International Development Association
-567Total Interest Repayment in Fourth Quarter of 2018
International Development Association
2676100Total Disbursement in First Quarter of 2019
International Development Association
5921118Total Disbursement in First Quarter of 2019
International Development Association
71735Total Disbursement in First Quarter of 2019
International Development Association
195766Total Disbursement in First Quarter of 2019
International Development Association
127145Total Disbursement in Second Quarter of 2019
International Development Association
6534368Total Disbursement in Second Quarter of 2019
International Development Association
-173962Total Interest Repayment in Second Quarter of 2019
International Development Association
1408204Total Disbursement in Second Quarter of 2019
International Development Association
2317589Total Disbursement in Second Quarter of 2019
International Development Association
3915220Total Disbursement in Second Quarter of 2019
International Development Association
-1119Total Interest Repayment in Second Quarter of 2019
International Development Association
126737Total Disbursement in Second Quarter of 2019
International Development Association
234039Total Disbursement in Third Quarter of 2019
International Development Association
567475Total Disbursement in Fourth Quarter of 2019
International Development Association
-214861Total Interest Repayment in Fourth Quarter of 2019
International Development Association
649568Total Disbursement in Fourth Quarter of 2019
International Development Association
921237Total Disbursement in Fourth Quarter of 2019
International Development Association
-24400Total Interest Repayment in Fourth Quarter of 2019
International Development Association
4068958Total Disbursement in Fourth Quarter of 2019
International Development Association
-216020Total Interest Repayment in Second Quarter of 2020
International Development Association
-34273Total Interest Repayment in Second Quarter of 2020
International Development Association
-223610Total Interest Repayment in Fourth Quarter of 2020
International Development Association
-36634Total Interest Repayment in Fourth Quarter of 2020
International Development Association
Project Information DocumentImplementation Status and Results ReportImplementation Status and Results ReportAgreementFinancing AgreementContract AwardsProject URLProcurement Notices
Financing Agreement :VPMU | Description :The VPMU shall be maintained throughout the Project implementation period with adequateresources and competent and qualified staff in adequate numbers required for the Project. | Frequency :CONTINUOUS
Financing Agreement :Program Steering Committee | Description :The Recipient shall nominate the chairman of the VPMU SteeringCommittee (or their designated representative) as its member to the Program Steering Committee. | Frequency :CONTINUOUS
Financing Agreement :Regional Procurement Evaluation Committee | Description :The Recipient shall, in collaboration with the otherProgram Countries, ensure that the Regional Procurement Evaluation Committee is maintained throughout the Project implementationperiod and comprised of representatives of the Program Countries, TAL (through TFSU) and PASO. | Frequency :CONTINUOUS
Finance Agreement :Safety and Security Levy | Description: The Recipient shall take all measures required on its part to ensurethat AVL shall, from not later than July 1, 2016, and thereafter throughout the Project implementation period, collect fromdeparting international passengers a levy in a minimum amount equivalent to five Australian Dollars (AU$5) to recover aviationsafety and security expenditures incurred by the Recipient.
Finance Agreement : Safeguards | Description: The Recipient shall ensure that the Project is carried out in accordance withtheSafeguard Instruments.
PDO Indicator
Regulatory certification of safety and security at Bauerfield (VLI) maintained
PDO Indicator
State requirements for safety measured by Universal Safety Oversight Audit Programme (USOAP) reaches global ICAO average
PDO Indicator
Modernization of air traffic management achieved
PDO Indicator
Regional safety and security levy for departing international passengers implemented
Intermediate Results Indicator
Repairs to Bauerfield, Whitegrass and Pekoa Airport pavements in line with implementation schedule
Intermediate Results Indicator
Aviation Sector Strategy in line with implementation schedule
Intermediate Results Indicator
Airport Master Plan in line with implementation schedule
Intermediate Results Indicator
Emergency Repairs to Bauerfieled and Whitegrass completed
Intermediate Results Indicator
Grievance registered related to delivery of project benefits by gender that are actually addressed
Intermediate Results Indicator
Navigation and safety aids in line with implementation schedule
Intermediate Results Indicator
Successful implementation of agreed training plan
Intermediate Results Indicator
Project-supported organization(s) publishing periodic reports on GRM and how issues were resolved
Intermediate Results Indicator
Fire Standards at VLI Achieved
Intermediate Results Indicator
Grievances responded and/or resolved within the stipulated services standards for response times
44000-P155256
World Bank
Pacific Resilience Program
International Development Association
International Development Association
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Artessa Saldivar-Sali
+1-202-473-1000asaldivarsali@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
VANUATU
Shefa Province
-17.3330 168.5000
Public Administration - Water, Sanitation and Waste ManagementDisaster Risk ManagementFinance for DevelopmentDisaster Risk FinanceDisaster PreparednessDisaster Response and RecoveryDisaster Risk Reduction
0.00
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
41666.66
41666.67
41666.67
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.63
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.63
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.67
41666.63
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1500000Total Commitment in Second Quarter of 2015
International Development Association
500000Total Disbursement in Fourth Quarter of 2015
International Development Association
-1539Total Interest Repayment in First Quarter of 2016
International Development Association
500000Total Disbursement in Fourth Quarter of 2016
International Development Association
-1844Total Interest Repayment in Fourth Quarter of 2016
International Development Association
-3352Total Interest Repayment in First Quarter of 2017
International Development Association
-3747Total Interest Repayment in Third Quarter of 2017
International Development Association
500000Total Disbursement in Fourth Quarter of 2017
International Development Association
-5072Total Interest Repayment in First Quarter of 2018
International Development Association
-5684Total Interest Repayment in Third Quarter of 2018
International Development Association
-5579Total Interest Repayment in First Quarter of 2019
International Development Association
-5499Total Interest Repayment in Third Quarter of 2019
International Development Association
-5519Total Interest Repayment in First Quarter of 2020
International Development Association
-5568Total Interest Repayment in Third Quarter of 2020
International Development Association
Project Information DocumentProject Appraisal Document Implementation Status and Results ReportImplementation Status and Results ReportFinancing AgreementContract AwardsProject URLProcurement Notices
In carrying out activities under the Project, the Recipient shall enter into an Insurance Contract with an Eligible Insurer underterms and conditions acceptable to the Association.
PDO Indicator
Participating PICs have received payment within a month of the occurrence of a covered (insured) event
Intermediate Results Indicator
The premiums are lower than the simulated price for a comparable coverage purchase individually in the market.
44000-P156505
World Bank
Vanuatu Infrastructure Reconstruction and Improvement Project
International Development Association
International Development Association
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Artessa Saldivar-Sali
+1-202-473-1000asaldivarsali@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
VANUATU
Tafea Province
-19.5000 169.5000
Malampa Province
-16.2500 167.7500
Penama Province
-15.5000 168.0000
Shefa Province
-17.3330 168.5000
Port Vila Harbour
-17.7500 168.3000
Tanna
-19.5000 169.3330
Erromango Island
-18.8000 169.0830
EfatE Island
-17.6670 168.4170
Shepherd Islands
-16.9170 168.5830
Other EducationHealthOther Public AdministrationRural and Inter-Urban RoadsClimate changeDisaster Risk ManagementDisease ControlFinance for DevelopmentAdaptationDisaster Risk FinanceDisaster PreparednessDisaster Response and RecoveryDisaster Risk ReductionPandemic Response
0.00
0.00
0.00
0.00
0.00
0.00
0.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
750000.00
750000.00
750000.00
750000.00
750000.00
750000.00
750000.00
750000.00
750000.00
833333.33
833333.33
833333.34
916666.66
916666.67
916666.67
916666.66
916666.67
916666.67
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
966666.66
966666.67
966666.67
950000.00
950000.00
950000.00
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
666666.66
666666.67
666666.67
166666.66
166666.67
166666.67
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
500000.00
666666.66
666666.67
666666.67
666666.66
666666.67
666666.67
750000.00
750000.00
750000.00
750000.00
750000.00
750000.00
750000.00
750000.00
750000.00
833333.33
833333.33
833333.34
916666.66
916666.67
916666.67
916666.66
916666.67
916666.67
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
1000000.00
966666.66
966666.67
966666.67
950000.00
950000.00
950000.00
833333.33
833333.33
833333.34
833333.33
833333.33
833333.34
666666.66
666666.67
666666.67
166666.66
166666.67
166666.67
0.00
0.00
0.00
0.00
0.00
0.00
25000000Total Commitment in Second Quarter of 2016
International Development Association
25000000Total Commitment in Second Quarter of 2016
International Development Association
1845870Total Disbursement in First Quarter of 2017
International Development Association
1837391Total Disbursement in Second Quarter of 2017
International Development Association
-3204Total Interest Repayment in Third Quarter of 2017
International Development Association
-7237Total Interest Repayment in First Quarter of 2018
International Development Association
831818Total Disbursement in Third Quarter of 2018
International Development Association
-7104Total Interest Repayment in Third Quarter of 2018
International Development Association
747616Total Disbursement in Third Quarter of 2018
International Development Association
998942Total Disbursement in Fourth Quarter of 2018
International Development Association
362704Total Disbursement in First Quarter of 2019
International Development Association
-12568Total Interest Repayment in First Quarter of 2019
International Development Association
868907Total Disbursement in First Quarter of 2019
International Development Association
1218570Total Disbursement in Second Quarter of 2019
International Development Association
634091Total Disbursement in Second Quarter of 2019
International Development Association
1385521Total Disbursement in Second Quarter of 2019
International Development Association
-17539Total Interest Repayment in Third Quarter of 2019
International Development Association
870662Total Disbursement in Third Quarter of 2019
International Development Association
879937Total Disbursement in Fourth Quarter of 2019
International Development Association
1402046Total Disbursement in Fourth Quarter of 2019
International Development Association
886399Total Disbursement in Fourth Quarter of 2019
International Development Association
896696Total Disbursement in Fourth Quarter of 2019
International Development Association
685401Total Disbursement in First Quarter of 2020
International Development Association
1102681Total Disbursement in First Quarter of 2020
International Development Association
-24645Total Interest Repayment in First Quarter of 2020
International Development Association
561297Total Disbursement in First Quarter of 2020
International Development Association
227209Total Disbursement in Second Quarter of 2020
International Development Association
507236Total Disbursement in Second Quarter of 2020
International Development Association
209788Total Disbursement in Second Quarter of 2020
International Development Association
664554Total Disbursement in Second Quarter of 2020
International Development Association
143621Total Disbursement in Third Quarter of 2020
International Development Association
324669Total Disbursement in Third Quarter of 2020
International Development Association
-38163Total Interest Repayment in Third Quarter of 2020
International Development Association
153102Total Disbursement in Third Quarter of 2020
International Development Association
337905Total Disbursement in Third Quarter of 2020
International Development Association
775337Total Disbursement in Fourth Quarter of 2020
International Development Association
1262290Total Disbursement in Fourth Quarter of 2020
International Development Association
156017Total Disbursement in Fourth Quarter of 2020
International Development Association
Project Appraisal Document Implementation Status and Results ReportFinancing AgreementContract AwardsProject URLProcurement Notices
Finance Agreement :Selected Public Buildings | Description :The Recipient shall ensure that: (i) only the Selected Public Buildingsincluded in an approved Annual Work Plan and Budget shall be eligible for financing under the Project; and (ii) the total financingfor any reconstruction/rehabilitation works for each respective Selected Public Building shall not exceed $300,000 (three hundredthousand Dollars) equivalent, unless as otherwise approved in writing by the Association. | Frequency :CONTINUOUS
Finance Agreement :Project Operations Manual | Description :The Recipient shall prepare, by not later than three months after theEffective Date, and thereafter adopt a Project Operations Manual, setting forth the arrangements and procedures for theimplementation of the Project.The Recipient shall establish, by not later than four months after the Effective Date, andthereafter maintain, throughout the Project implementation period, a Project Support Team (PST) within MIPU. | Due Date:01-Dec-2016
PDO Indicator
Population on project islands with improved road and pedestrian access (number).
PDO Indicator
Number of users/beneficiaries of schools reconstructed and upgraded to higher structural safety standards (number)
PDO Indicator
Population on project islands with improved road and pedestrian access (percentage of men).
PDO Indicator
Number of users/beneficiaries of schools reconstructed and upgraded to higher structural safety standards (percentage of women).
PDO Indicator
Population on project islands with improved road and pedestrian access (percentage of women).
PDO Indicator
Number of users/beneficiaries of schools reconstructed and upgraded to higher structural safety standards (percentage of men).
Intermediate Results Indicator
Work days created for local contractors (number, women).
Intermediate Results Indicator
Schools reconstructed to higher structural safety standards
Intermediate Results Indicator
Public buildings impacted by TC Pam reconstructed to be more resilient
Intermediate Results Indicator
Percentage of registered grievances appropriately responded within two weeks.
Intermediate Results Indicator
Percentage of beneficiaries that feel project investments reflected their needs (percent)
Intermediate Results Indicator
Work days created for local contractors (number, men)
Intermediate Results Indicator
Road assets reconstructed or improved (number).
Intermediate Results Indicator
Number of accredited IBCs able to construct assets/buildings to higher structural standards that are more climate resilient (text).
44000-P160658
World Bank
Rural Electrification Project Stage II
International Development Association
International Development Association
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Mitsunori Motohashi
+1-202-473-1000mmotohashi@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
VANUATU
Tafea Province
-19.5000 169.5000
Sanma Province
-15.3330 166.7500
Torba Province
-13.7500 167.5000
Malampa Province
-16.2500 167.7500
Penama Province
-15.5000 168.0000
Shefa Province
-17.3330 168.5000
Republic of Vanuatu
-16.0000 167.0000
Port Vila Harbour
-17.7500 168.3000
Luganville
-15.5200 167.1620
Port-Vila
-17.7340 168.3220
Tanna
-19.5000 169.3330
Malakula
-16.2500 167.5000
Efate Island
-17.6670 168.4170
Renewable Energy SolarEnergy Transmission and DistributionEnergyRural DevelopmentGenderMitigationAccess to EnergyClimate changeRural Infrastructure and service delivery
0.00
0.00
130000.00
130000.00
130000.00
130000.00
130000.00
130000.00
130000.00
130000.00
130000.00
130000.00
130000.00
130000.00
155833.33
155833.33
155833.33
155833.33
155833.33
155833.33
155833.33
155833.33
155833.33
155833.33
155833.33
155833.37
305833.33
305833.33
305833.33
305833.33
305833.33
305833.33
305833.33
305833.33
305833.33
305833.33
305833.33
305833.37
300000.00
300000.00
300000.00
300000.00
300000.00
300000.00
300000.00
300000.00
300000.00
300000.00
300000.00
300000.00
289166.67
289166.67
289166.67
289166.67
289166.67
289166.67
289166.67
289166.67
289166.67
289166.67
289166.67
289166.63
0.00
0.00
0.00
0.00
94295.67
94295.67
94295.67
94295.67
94295.67
94295.67
94295.67
94295.67
94295.67
94295.67
94295.67
94295.63
3713.83
3713.83
3713.83
3713.83
3713.83
3713.83
3713.83
3713.83
3713.83
3713.83
3713.83
3713.87
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
125000.00
416666.67
416666.67
416666.67
416666.67
416666.67
416666.67
416666.67
416666.67
416666.67
416666.67
416666.67
416666.63
541666.67
541666.67
541666.67
541666.67
541666.67
541666.67
541666.67
541666.67
541666.67
541666.67
541666.67
541666.63
0.00
0.00
2000000Total Commitment in Second Quarter of 2017
International Development Association
2000000Total Commitment in Second Quarter of 2017
International Development Association
189573Total Disbursement in First Quarter of 2018
International Development Association
188041Total Disbursement in First Quarter of 2018
International Development Association
-895Total Interest Repayment in Fourth Quarter of 2018
International Development Association
-685Total Interest Repayment in Second Quarter of 2019
International Development Association
-669Total Interest Repayment in Fourth Quarter of 2019
International Development Association
22426Total Disbursement in First Quarter of 2020
International Development Association
22426Total Disbursement in First Quarter of 2020
International Development Association
-21652Total Disbursement in Second Quarter of 2020
International Development Association
-703Total Interest Repayment in Second Quarter of 2020
International Development Association
8769Total Disbursement in Second Quarter of 2020
International Development Association
-691Total Interest Repayment in Fourth Quarter of 2020
International Development Association
Contract AwardsProject URLProcurement Notices
PDO Indicator
Generation capacity of energy constructed - renewable energy facilities
PDO Indicator
Annual electricity output from renewable energy as a result of renewable energy constructed under the project
PDO Indicator
Annual electricity output from renewable energy as a result of renewable energy constructed under the project
PDO Indicator
People provided with a new electricty service
PDO Indicator
People provided with a new electricity service
Intermediate Results Indicator
Households received a Solar Home Systems or micro grids
Intermediate Results Indicator
Public Institutions received a Solar Home System or micro grid
Intermediate Results Indicator
Number of mini grids constructed under the project
Intermediate Results Indicator
Number of People connected to electricity through a mini grid constructed under the project
Intermediate Results Indicator
Direct project beneficiaries of which are female
Intermediate Results Indicator
Total households of which are female headed households received a Solar Home System, micro grid or electricity through a mini-grid
Intermediate Results Indicator
Participants in consultation activities during project implementation (number)
Intermediate Results Indicator
Participants in consultation activities during project implementation - female
Intermediate Results Indicator
Grievances registered related to delivery of project benefits addressed (%)
44000-P167382
World Bank
Vanuatu Climate Resilient Transport Project
International Development Association
International Development Association
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Dung Anh Hoang
+1-202-473-1000dhoang1@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
VANUATU
Port Vila Harbour
-17.7500 168.3000
Sarakata
-15.5150 167.1710
Navaka
-15.6330 166.8670
Maniao
-15.5830 166.9330
Bouvo
-15.6170 166.7670
Bayalo
-15.6000 166.9000
Adson
-15.5830 166.9670
Wailapa
-15.5810 166.9450
Tasiriki
-15.6000 166.7670
Nakere
-15.5830 166.9830
Luganville
-15.5200 167.1620
Public Administration - TransportationRural and Inter-Urban RoadsClimate changeRoad SafetyUrban DevelopmentData production, accessibility and useAdaptationPublic TransportGenderFlood and Drought Risk ManagementDisaster PreparednessDisaster Risk ManagementData Development and Capacity Building
0.00
0.00
77550.00
86790.00
197142.00
229350.00
126192.00
273306.00
299112.00
161238.00
356400.00
391578.00
410784.00
209418.00
427350.00
219714.00
447480.00
451176.00
441672.00
217206.00
437118.00
454740.00
239910.00
501402.00
515262.00
266178.00
562056.00
600072.00
309078.00
641982.00
686664.00
736164.00
376398.00
766722.00
806322.00
425502.00
894762.00
927630.00
480414.00
1008282.00
1083852.00
567600.00
1182852.00
1248984.00
1314984.00
684420.00
1429890.00
1495362.00
768174.00
1567896.00
1624260.00
836352.00
1713294.00
1762992.00
901560.00
1865424.00
1923240.00
1957758.00
989604.00
1990428.00
2024748.00
1027488.00
2076228.00
2104080.00
1066956.00
2163348.00
2197998.00
1111308.00
2247630.00
2281422.00
2315940.00
1813812.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
77550.00
86790.00
197142.00
229350.00
126192.00
273306.00
299112.00
161238.00
356400.00
391578.00
410784.00
209418.00
427350.00
219714.00
447480.00
451176.00
441672.00
217206.00
437118.00
454740.00
239910.00
501402.00
515262.00
266178.00
562056.00
600072.00
309078.00
641982.00
686664.00
736164.00
376398.00
766722.00
806322.00
425502.00
894762.00
927630.00
480414.00
1008282.00
1083852.00
567600.00
1182852.00
1248984.00
1314984.00
684420.00
1429890.00
1495362.00
768174.00
1567896.00
1624260.00
836352.00
1713294.00
1762992.00
901560.00
1865424.00
1923240.00
1957758.00
989604.00
1990428.00
2024748.00
1027488.00
2076228.00
2104080.00
1066956.00
2163348.00
2197998.00
1111308.00
2247630.00
2281422.00
2315940.00
1813812.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
35500000Total Commitment in First Quarter of 2020
International Development Association
258414Total Disbursement in First Quarter of 2020
International Development Association
30500000Total Commitment in First Quarter of 2020
International Development Association
-523Total Interest Repayment in Second Quarter of 2020
International Development Association
266148Total Disbursement in Fourth Quarter of 2020
International Development Association
Contract AwardsProject URLProcurement Notices
PDO Indicator
Identified planning tools adopted and being used to improve climate resilience of roads
PDO Indicator
Length of road upgraded with climate resilience measures
PDO Indicator
Number of bridges constructed with climate resilience measures
PDO Indicator
Identified enabling environment solutions adopted and implemented
Intermediate Results Indicator
Road Inventory Management System upgraded with a module to integrate climate and disaster risk profiles of road assets
Intermediate Results Indicator
The MIPU-PWD's construction material testing laboratory accredited
Intermediate Results Indicator
Grievances registered related to delivery of project benefits that are addressed
Intermediate Results Indicator
Technical specifications for road design updated
Intermediate Results Indicator
An MOU signed between MIPU and MCCA for inter-ministerial collaboration
Intermediate Results Indicator
Proportion of Contractor staff who sign Codes of Conduct
Intermediate Results Indicator
Bridges repaired
Intermediate Results Indicator
Proportion of Contractor staff who attend GBV & VAC training
Intermediate Results Indicator
Box culverts installed
Intermediate Results Indicator
South Santo Road under piloting of multi-year performance-based maintenance contracts supported by VCRTP
Intermediate Results Indicator
Satisfactory road safety audit at design and post-construction phases
Intermediate Results Indicator
Number of people with enhanced access to transportation services
Intermediate Results Indicator
Development of the Gender Responsive Policy Inputs to VISIP M&E
Intermediate Results Indicator
Percentage of women employed in technical positions at MIPU-PWD at national and provincial levels
Intermediate Results Indicator
Public transport providers and drivers trained in GBV prevention
44000-P168749
World Bank
Vanuatu Disaster Risk Management Development Policy Grant with a Catastrophe-Deferred Drawdown Option (CAT-DDO)
International Development Association
International Development Association
Planned start date of the activity
Actual start date of the activity
Planned end date of the activityActual end date of the activity
The World Bank
Artessa Saldivar-Sali
+1-202-473-1000asaldivarsali@worldbank.org
pic@worldbank.org
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
VANUATUOther Public AdministrationRural DevelopmentDisease ControlDisaster Risk ManagementLand Administration and ManagementFlood and Drought Risk ManagementClimate changeDisaster Risk FinanceDisaster Risk ReductionPandemic ResponseFinance for DevelopmentAdaptationDisaster PreparednessGenderDisaster Response and Recovery
0.00
0.00
11750.00
13150.00
29870.00
34750.00
19120.00
41410.00
22200.00
47550.00
54000.00
29140.00
61070.00
31360.00
63810.00
65960.00
33760.00
68210.00
34190.00
66920.00
65840.00
33300.00
68900.00
36350.00
75970.00
78070.00
40330.00
85160.00
44980.00
92770.00
97270.00
51020.00
108090.00
56470.00
114610.00
118680.00
62080.00
131400.00
68640.00
140550.00
147870.00
77690.00
164220.00
86000.00
179220.00
189240.00
98370.00
204570.00
106970.00
221830.00
230810.00
118070.00
241220.00
124370.00
255530.00
263430.00
134470.00
276580.00
287500.00
146560.00
296630.00
149940.00
301580.00
306780.00
155680.00
314580.00
158690.00
321770.00
163200.00
330460.00
335530.00
169630.00
343110.00
348270.00
176110.00
274820.00
0.00
0.00
11750.00
13150.00
29870.00
34750.00
19120.00
41410.00
22200.00
47550.00
54000.00
29140.00
61070.00
31360.00
63810.00
65960.00
33760.00
68210.00
34190.00
66920.00
65840.00
33300.00
68900.00
36350.00
75970.00
78070.00
40330.00
85160.00
44980.00
92770.00
97270.00
51020.00
108090.00
56470.00
114610.00
118680.00
62080.00
131400.00
68640.00
140550.00
147870.00
77690.00
164220.00
86000.00
179220.00
189240.00
98370.00
204570.00
106970.00
221830.00
230810.00
118070.00
241220.00
124370.00
255530.00
263430.00
134470.00
276580.00
287500.00
146560.00
296630.00
149940.00
301580.00
306780.00
155680.00
314580.00
158690.00
321770.00
163200.00
330460.00
335530.00
169630.00
343110.00
348270.00
176110.00
274820.00
10000000Total Commitment in First Quarter of 2020
International Development Association
9925810Total Disbursement in Second Quarter of 2020
International Development Association
Contract AwardsProject URLProcurement Notices